Vous êtes sur la page 1sur 13

Influential Factors in the Outsourcing Decision

Increased manufacturing and operating costs of spreader production at the Temecula plant have
influenced the decision to consider relocating production to China to increase profit margin. After
thoroughly analyzing the present and future logistical and financial risks of both the Temecula and
China plants, the team determined that Scotts Miracle-Gro should maintain spreader operations at the
Temecula plant. The following quantitative and qualitative analyses support the teams conclusion.

Quantitative Factors & Sensitivity Analysis


When evaluating the decision to outsource production, the team analyzed the total quantitative
costs of the supply chain (Figure 1). Production, SG&A, and initial investment costs have a significant
impact on the decision to outsource the Scotts Miracle Grow spreader from Temecula to China.
Quantitative factors evaluated in the analysis include total costs for transportation, labor, raw materials,
electricity, management, overhead (startup, molds), and the initial investment. Detailed Net Present
Value (NPV) analyses are shown in Figure 2 for Temecula and Figure 3 for China. Upon conducting
the impact of the ten-year analysis, the quantitative factors that have the most significant impact on total
cost between operations in China and Temecula are transportation and labor costs.
Raw materials and electricity costs both have minor impacts on total cost of operations in both
China and Temecula. The estimated $1.4 million in savings (figure 3) at the Temecula plant has a
minimal impact on total cost of operations. The same applies to the effect of electricity costs on the total
cost of operations in both China and Temecula. The Temecula plant would cost an estimated $9 million
(figure 3) more for electricity operations and thus, along with raw material costs, both factors do not
make a significant impact.
Management, overhead, and investment costs mildly affected the decision for operations and
averaged around $15 million. Both overhead and management costs favored operations in China (figure
3), while investment costs were cheaper in Temecula due to the established operations. Lastly, labor
costs had the third largest impact on total cost favoring operations in China by almost $55 million. With
1

the number of workers remaining the same in both operations, it is evident that the cheaper labor rates
(18 times less than Temecula) in China are a significant advantage.
There are inherent risks and uncertainties in some of the factors that financially impact the
decision to outsource to China. Changes in Transportation and Labor costs can affect the total landed
costs of the product. Figure 4 and Figure 5 illustrates that an increase in transportation costs from 3% to
9.4% per year, shifts the financial drivers to favor Temecula over China. A detailed transportation cost
sensitivity analysis is graphically illustrated in Figure 6.

On the other hand, productivity at the

Temecula plant needs to increase by 16.2% annually as shown in Figure 7 and Figure 8 and hourly labor
cost in China requires an unprecedented increase of 39.5% annually to financially prefer Temecula over
China (Figure 9 and Figure 10). Transportation costs had the most significant impact on maintaining
operations at the Temecula facility. Freight charges accounted for over $90 million in additional
charges by outsourcing production to China. This expense is almost double the benefit of labor costs
and thus plays an instrumental part in maintaining production in the Temecula facility.

Qualitative Factors Influencing the Outsourcing Decision


Although many of Scotts outsourcing analysis factors are highly measurable in nature, some are
harder to quantify than others. According to Chopras review of Supplier Scoring and Assessment (p.
428), replenishment lead time greatly affects the amount of safety stock held in inventory to account for
potential deviations in the supply chain. Scotts option to source the spreader to China increases lead
time an additional eight weeks, which generates not only $460,000 in safety stock, but also leads to a
continuum of other challenges. Increased lead time translates to greater potential for delayed shipments,
which damages the suppliers on-time performance ratings and consequently causes Scotts to hold even
more safety stock while accruing holding costs.
Supply inflexibility is another consideration in the Chinese outsourcing option. Chinese suppliers
would likely impose a minimum batch size requirement, which leaves little room to respond to intense
swings in demand with smaller, more frequent deliveries. Larger batches also greatly increase cycle
2

inventory, associated holding costs, and risk. Given larger lot sizes, the potential for poor quality
production tremendously increases costs from replacement orders coupled with long lead time, rework,
and finally customer dissatisfaction in the form of missed sales. Supplier viability depends on
sustainability in the form of quality and reliability, thus an accepted level of quality deterioration for
cost savings tradeoff may eventually inhibit the suppliers sustainability.
The most visible tradeoff with the China option is decreased manufacturing and labor costs
versus increased inbound transportation costs at Temecula. However, the lack of information
coordination capabilities expressed by Chinese manufacturers accentuates freight costs associated with
lack of visibility and the bullwhip effect, which minimizes the optimism outlook. Lastly, if the Chinese
government allows the Yuan to float or begins charging taxes and duties on agricultural products, costs
in China would soar. Heavy financial hedging would protect Scott from general fluctuations but would
not be a sufficient strategy to evade the inevitable.

Outline & Recommendations


The team recommends that Scotts should not outsource the manufacturing capabilities to a
contractor in China. Scotts would offer up a core piece of the business (as well as all of the technical
knowledge and possibly even the In Mold machinery) to a contracted source. Labor rate forecasts in
China are on the rise for the next decade. The potential exists that once the operation is fully functional,
the cost of labor may no longer be a significant advantage and the unpredictability of the Chinese laws
can still result in a disadvantage to Scotts. Output from the Chinese facility predictions are lower than in
Temecula, as the employees in China would experience a learning curve coupled with low productivity
rates. As previously mentioned, Scotts will make the tradeoff of responsiveness for cost-savings, which
consequently increases safety stock and working capital costs.
In conclusion, the justification for outsourcing production to China looks very appealing in the
analysis, but there needs to be a balance between cost reduction and the other challenges that arise from
using overseas contract manufacturers.
3

Figure 1 Summary Sheet

COMPARISON OF NET PRESENT VALUES


Temecula Analysis
YEAR 0
YEAR 1
YEAR2
YEAR 3
YEAR 4
YEAR 5
YEAR 6
YEAR 7
YEAR 8
YEAR 9
YEAR 10
Total
Total Cost
$17,562,750 $17,288,907 $17,026,784 $16,531,368 $16,296,679 $16,072,730 $16,075,843 $16,082,082 $16,091,420 $16,103,832 $16,119,297 $181,251,691
15% Discount Rate
1.0000
0.8696
0.7561
0.6575
0.5718
0.4972
0.4323
0.3759
0.3269
0.2843
0.2472
NPV
$17,562,750 $15,033,832 $12,874,695 $10,869,643 $9,317,679 $7,990,987 $6,950,031 $6,045,850 $5,260,314 $4,577,714 $3,984,444 $100,467,939
Total NPV
$100,467,939

China Analysis
Total Cost
$19,466,742 $12,340,613 $12,624,736 $12,919,439 $13,225,061 $13,941,953 $13,870,484 $14,211,035 $14,564,005 $14,929,806 $15,708,870 $157,802,744
15% Discount Rate
1.0000
0.8696
0.7561
0.6575
0.5718
0.4972
0.4323
0.3759
0.3269
0.2843
0.2472
NPV
$19,466,742 $10,730,967 $9,546,115 $8,494,741 $7,561,471 $6,931,615 $5,996,593 $5,342,454 $4,760,999 $4,243,983 $3,882,992 $86,958,673
Total NPV
$86,958,673

SPECIFIC COST BREAKDOWN OVER THE TEN YEAR PERIOD


Raw Material
Labor
Electricity
Lease
Temecula ($1,420,679) $62,014,061 $16,100,688 $33,000,000
China
$0
$3,896,102 $7,387,529 $2,200,000
Difference* $1,420,679 ($58,117,959) ($8,713,159) ($30,800,000)
* Note: Black indicates money saved by staying in Temecula

Management
$18,815,401
$4,515,696
($14,299,705)

Overhead
Freight Safety Stock
$34,434,425 $12,807,796
$0
$14,387,997 $102,462,366 $5,060,000
($20,046,428) $89,654,570 $5,060,000

Investment
$5,500,000
$17,893,054
$12,393,054

TOTAL COST COMPARISON OVER THE 10 YEAR PERIOD


Temecula
China
Cost of Goods
$109,694,070 $13,483,631
S,G and A Cost
$66,057,621 $126,426,059
Investment Cost
$5,500,000 $17,893,054
Total
$181,251,691 $157,802,744
* Note: Black indicates money saved by staying in Temecula

Difference*
($96,210,439)
$60,368,437
$12,393,054
($23,448,948)
4

Figure 2 - Cash Flow and NPV Calculations for Temecula


Year:

10

PRODUCTION COSTS
Raw Materials
Current savings from use of regrind

($100,000)

Annual increase in savings due to regrind usage


Cost savings from use of regrind
Hourly Labor Costs

($100,000)

5%

5%

5%

5%

5%

5%

5%

5%

5%

5%

($105,000)

($110,250)

($115,763)

($121,551)

($127,628)

($134,010)

($140,710)

($147,746)

($155,133)

($162,889)

Only hourly w age employees counted (i.e. direct labor personal and temporary w orkers)
$16.25

Current Avg. hourly rate


Annual increase %
Avg. hourly labor rate

$16.25

Current no. of w orkers

3%

3%

3%

3%

3%

3%

3%

3%

3%

3%

$16.74

$17.24

$17.76

$18.29

$18.84

$19.40

$19.99

$20.59

$21.20

$21.84

6%

6%

6%

6%

3%

3%

3%

3%

3%

195

Annual productivity increase

6%

Number of hourly w orkers


Total annual hourly labor cost

195

183

$6,337,500

$6,135,968

(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
172
162
152
143
139
135
131
$5,940,844

$5,751,925

$5,569,014

$5,391,919

$5,387,066

$5,382,218

127

123

$5,377,374

$5,372,534

$5,367,699

$0.2368

(Assuming a 5 day w ork w eek, 8 hours/day and a 50 w eek year)


Electricity Costs

4.00% <--annual grow th rate


$0.1664
$0.1731

Avg. Kw H rate

$0.1600

Surcharge (per Kw H)
Annual pow er usage (Kw H)
Total annual electricity cost

$0.1800

$0.1872

$0.1947

$0.2025

$0.2105

$0.2190

$0.2277

$0.025

$0.025

$0.025

$0.000

$0.000

$0.000

$0.000

$0.000

$0.000

$0.000

$0.000

8,000,000

7,840,000
$1,500,576

7,683,200
$1,521,704

7,529,536
$1,355,153

7,378,945
$1,381,172

7,231,366
$1,407,690

7,086,739
$1,434,718

6,945,004
$1,462,264

6,806,104
$1,490,340

6,669,982
$1,518,954

6,536,582
$1,548,118

$1,480,000

Lease
TOTAL PRODUCTION COSTS

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$10,717,500

$10,531,544

$10,352,298

$9,991,315

$9,828,635

$9,671,981

$9,687,774

$9,703,772

$9,719,968

$9,736,356

$9,752,928

SG&A COSTS
Management Costs
Current Average annual rate

$125,000

Annual increase %
Avg. annual pay labor rate
Current no. of w orkers

0%

3%

3%

3%

3%

3%

3%

3%

3%

3%

3%

$125,000

$128,750

$132,613

$136,591

$140,689

$144,909

$149,257

$153,734

$158,346

$163,097

$167,990

6%

6%

6%

6%

3%

3%

3%

3%

3%

(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
14
13
12
12
11
10
10

$1,495,257

$1,447,707

16

Annual productivity increase


Number of salaried managers
Total annual management labor cost

6%
16

15

$2,000,000

$1,936,400

$1,874,822

$1,815,203

$1,757,480

$1,701,592

$1,647,481

$1,595,091

$1,544,367

Overhead Costs
Corporate Allocation
30% allocation of direct costs
CM Profit
Total annual OH costs

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$2,345,250

$2,290,963

$2,238,764

$2,132,123

$2,085,056

$2,039,883

$2,046,535

$2,053,345

$2,060,314

$2,067,447

$2,074,745

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$3,345,250

$3,290,963

$3,238,764

$3,132,123

$3,085,056

$3,039,883

$3,046,535

$3,053,345

$3,060,314

$3,067,447

$3,074,745

Freight Rate %
Freight
Safety Stock
TOTAL SG&A COSTS

0.03
$1,000,000

$1,030,000

$1,060,900

$1,092,727

$1,125,509

$1,159,274

$1,194,052

$1,229,874

$1,266,770

$1,304,773

$1,343,916

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$6,345,250

$6,257,363

$6,174,487

$6,040,053

$5,968,044

$5,900,749

$5,888,069

$5,878,310

$5,871,452

$5,867,476

$5,866,369

$500,000

INVESTMENTS
Annual Capital Outlays

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Additional Scott People To Manage CM

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Additional Scott Travel

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Molds

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$16,531,368

$16,296,679

$16,072,730

$16,075,843

$16,082,082

$16,091,420

$16,103,832

$16,119,297

Start Up Costs

TOTAL INVESTMENTS
Total Costs
Discout Factor @ 15%
NPV

$17,562,750
1.0

$17,562,750

$17,288,907
0.8696

$15,033,832

$17,026,784
0.7561

$12,874,695

0.6575

$10,869,643

0.5718

$9,317,679

0.4972

$7,990,987

0.4323

$6,950,031

0.3759

$6,045,850

0.3269

$5,260,314

0.2843

$4,577,714
10 YR NPV

0.2472

$3,984,444
$100,467,939

Figure 3 - Cash Flow and NPV Calculations for China


Year:

10

PRODUCTION COSTS
Raw Materials
Current savings from use of regrind

$0

Annual increase in savings due to regrind usage


Cost savings from use of regrind

$0

Hourly Labor Costs


Current Avg. hourly rate
Annual increase %
Avg. hourly labor rate
Current no. of workers
Annual productivity increase
Number of hourly workers
Total annual hourly labor cost

Electricity Costs
Avg. KwH rate
Surcharge (per KwH)
Annual power usage (KwH)
Total annual electricity cost

TOTAL PRODUCTION COSTS


SG&A COSTS
Management Costs
Current Average annual rate
Annual increase %
Avg. annual pay labor rate
Current no. of workers
Annual productivity increase

5%
$0

5%
$0

5%
$0

5%
$0

5%
$0

5%
$0

5%
$0

2%
$1.05

2%
$1.07

2%
$1.09

2%
$1.11

2%

2%

2%

2%

169
$353,907

166
$353,766

163
$353,624

159
$353,483

$0.0717
$0.000
8,000,000
$573,300

$0.0752
$0.000
8,000,000
$601,965

$0.0790
$0.000
8,000,000
$632,063

$0.0830
$0.000
8,000,000
$663,666

$0.0871
$0.000
8,000,000
$696,850

$0.0915
$0.000
8,000,000
$731,692

$0.0960
$0.000
8,000,000
$768,277

$0.1008
$0.000
8,000,000
$806,691

$0.1059
$0.000
8,000,000
$847,025

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$1,074,900

$1,100,758

$1,127,916

$1,156,439

$1,186,396

$1,217,857

$1,250,899

$1,285,600

$1,322,043

$1,360,315

$1,400,508

3%
$30,900

3%
$31,827

3%
$32,782

3%
$33,765

3%
$34,778

3%
$35,822

3%
$36,896

3%
$38,003

3%
$39,143

3%
$40,317

6%
6%
6%
6%
3%
3%
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
14
13
12
12
11
10
$449,957
$435,649
$421,795
$408,382
$395,395
$382,822

3%

3%

3%

10
$370,648

9
$358,862

9
$347,450

0%
$30,000
16

6%

Overhead Costs
Corporate Allocation
50% allocation of direct costs
CM Profit 8%
Total annual OH costs

16
$480,000

15
$464,736

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$177,450

$177,379

$177,308

$177,237

$177,166

$177,095

$177,025

$176,954

$176,883

$176,812

$176,741

$124,392
$1,301,842

$125,240
$1,302,619

$126,230
$1,303,538

$127,367
$1,304,604

$128,655
$1,305,822

$130,099
$1,307,195

$131,704
$1,308,728

$133,474
$1,310,427

$135,415
$1,312,298

$137,534
$1,314,346

$139,837
$1,316,578

$8,000,000
$460,000

0.03
$8,240,000
$460,000

$8,487,200
$460,000

$8,741,816
$460,000

$9,004,070
$460,000

$9,274,193
$460,000

$9,552,418
$460,000

$9,838,991
$460,000

$10,134,161
$460,000

$10,438,185
$460,000

$10,751,331
$460,000

$10,241,842

$10,467,355

$10,700,695

$10,942,069

$11,191,687

$11,449,769

$11,716,542

$11,992,240

$12,277,107

$12,571,393

$12,875,359

$300,000
$1,000,000
$250,000
$200,000
$400,000
$6,000,000

$300,000
$0
$262,500
$210,000
$0

$300,000
$0
$275,625
$220,500
$0

$300,000
$0
$289,406
$231,525
$0

$300,000
$0
$303,877
$243,101
$0

$300,000
$0
$319,070
$255,256
$400,000

$300,000
$0
$335,024
$268,019
$0

$300,000
$0
$351,775
$281,420
$0

$300,000
$0
$369,364
$295,491
$0

$300,000
$0
$387,832
$310,266
$0

$300,000
$0
$407,224
$325,779
$400,000

$8,150,000

$772,500

$796,125

$820,931

$846,978

$1,274,327

$903,043

$933,195

$964,855

$998,098

$1,433,003

$19,466,742

$12,340,613

$12,624,736

$12,919,439

$13,225,061

$13,941,953

$13,870,484

$14,211,035

$14,564,005

$14,929,806

$15,708,870

1.00
$19,466,742

0.8696
$10,730,967

0.7561
$9,546,115

0.6575
$8,494,741

0.5718
$7,561,471

0.4972
$6,931,615

0.4323
$5,996,593

0.3759
$5,342,454

0.3269
$4,760,999

0.2843
$4,243,983

0.2472
$3,882,992
$86,958,673

Freight Rate %
Freight
Safety Stock
TOTAL SG&A COSTS
INVESTMENTS
Annual Capital Outlays
Start Up Costs
Additional Scott People To Manage CM
Additional Scott Travel
Molds
Buyback Lease Option

Discount Rate @ 15%


NPV

5%
$0

$30,000

Number of salaried managers


Total annual management labor cost

Total Costs

5%
$0

Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
$0.91
0%
2%
2%
2%
2%
2%
2%
$0.91
$0.93
$0.95
$0.97
$0.99
$1.00
$1.02
195
2%
2%
2%
2%
2%
2%
(Productivity assumed to increase at 2% annually.)
195
191
187
184
180
176
173
$354,900
$354,758
$354,616
$354,474
$354,333
$354,191
$354,049
(Assuming a 5 day work week, 8 hours/day and a 50 week year)
5.00% <--annual growth rate
$0.0650
$0.0683
$0.000
$0.000
8,000,000
8,000,000
$520,000
$546,000

Lease

TOTAL INVESTMENTS

5%
$0

10 YR NPV

Figure 4 NPV Calculations for Temecula with Transportation Cost Annual Increase of 9.4%
Year:

10

PRODUCTION COSTS
Raw Materials
Current savings from use of regrind

($100,000)

Annual increase in savings due to regrind usage


Cost savings from use of regrind
Hourly Labor Costs

($100,000)

5%

5%

5%

5%

5%

5%

5%

5%

5%

5%

($105,000)

($110,250)

($115,763)

($121,551)

($127,628)

($134,010)

($140,710)

($147,746)

($155,133)

($162,889)

Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
$16.25

Current Avg. hourly rate


Annual increase %
Avg. hourly labor rate

$16.25

Current no. of workers

3%

3%

3%

3%

3%

3%

3%

3%

3%

3%

$16.74

$17.24

$17.76

$18.29

$18.84

$19.40

$19.99

$20.59

$21.20

$21.84

6%

6%

6%

6%

3%

3%

3%

3%

3%

(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
172
162
152
143
139
135

131

127

123

$5,377,374

$5,372,534

$5,367,699

195

Annual productivity increase

6%

Number of hourly workers


Total annual hourly labor cost

195

183

$6,337,500

$6,135,968

$5,940,844

$5,751,925

$5,569,014

$5,391,919

$5,387,066

$5,382,218

(Assuming a 5 day work week, 8 hours/day and a 50 week year)


Electricity Costs

4.00% <--annual growth rate


$0.1664

Avg. KwH rate

$0.1600

Surcharge (per KwH)


Annual power usage (KwH)
Total annual electricity cost

TOTAL PRODUCTION COSTS

$0.1800

$0.1872

$0.1947

$0.2025

$0.2105

$0.2190

$0.2277

$0.2368

$0.025

$0.025

$0.000

$0.000

$0.000

$0.000

$0.000

$0.000

$0.000

$0.000

7,840,000
$1,500,576

7,683,200
$1,521,704

7,529,536
$1,355,153

7,378,945
$1,381,172

7,231,366
$1,407,690

7,086,739
$1,434,718

6,945,004
$1,462,264

6,806,104
$1,490,340

6,669,982
$1,518,954

6,536,582
$1,548,118

$1,480,000

Lease

$0.1731

$0.025
8,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$10,717,500

$10,531,544

$10,352,298

$9,991,315

$9,828,635

$9,671,981

$9,687,774

$9,703,772

$9,719,968

$9,736,356

$9,752,928

SG&A COSTS
Management Costs
Current Average annual rate

$125,000

Annual increase %
Avg. annual pay labor rate
Current no. of workers

0%

3%

3%

3%

3%

3%

3%

3%

3%

3%

3%

$125,000

$128,750

$132,613

$136,591

$140,689

$144,909

$149,257

$153,734

$158,346

$163,097

$167,990

6%

6%

6%

6%

3%

3%

3%

3%

3%

16

Annual productivity increase

6%

Number of salaried managers


Total annual management labor cost

16

15

$2,000,000

$1,936,400

(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
14
13
12
12
11
10
$1,874,822

$1,815,203

$1,757,480

$1,701,592

$1,647,481

$1,595,091

10

$1,544,367

$1,495,257

$1,447,707

Overhead Costs
Corporate Allocation
30% allocation of direct costs
CM Profit
Total annual OH costs

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$2,345,250

$2,290,963

$2,238,764

$2,132,123

$2,085,056

$2,039,883

$2,046,535

$2,053,345

$2,060,314

$2,067,447

$2,074,745

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$3,345,250

$3,290,963

$3,238,764

$3,132,123

$3,085,056

$3,039,883

$3,046,535

$3,053,345

$3,060,314

$3,067,447

$3,074,745

$1,000,000

$1,094,000

$1,196,836

$1,309,339

$1,432,416

$1,567,064

$1,714,368

$1,875,518

$2,051,817

$2,244,688

$2,455,688

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$6,345,250

$6,321,363

$6,310,423

$6,256,665

$6,274,952

$6,308,538

$6,408,384

$6,523,954

$6,656,498

$6,807,391

$6,978,141

$500,000

Freight Rate %
Freight
Safety Stock
TOTAL SG&A COSTS

0.03

INVESTMENTS
Annual Capital Outlays

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Additional Scott People To Manage CM

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Additional Scott Travel

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Molds

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$17,562,750

$17,352,907

$17,162,720

$16,747,980

$16,603,586

$16,480,519

$16,596,158

$16,727,726

$16,876,466

$17,043,746

$17,231,069

1.0

0.8696

0.7561

0.6575

0.5718

0.4972

0.4323

0.3759

0.3269

0.2843

Start Up Costs

TOTAL INVESTMENTS
Total Costs
Discout Factor @ 15%
NPV

$17,562,750

$15,089,484

$12,977,482

$11,012,069

$9,493,154

$8,193,731

$7,174,977

$6,288,572

$5,516,947

$4,844,896
10 YR NPV

0.2472

$4,259,257
$102,413,319

Figure 5 NPV Calculations for China with Transportation Cost Annual Increase of 9.4%
Year:

10

PRODUCTION COSTS
Raw Materials
Current savings from use of regrind

$0

Annual increase in savings due to regrind usage


Cost savings from use of regrind

$0

Hourly Labor Costs


Current Avg. hourly rate
Annual increase %
Avg. hourly labor rate
Current no. of workers
Annual productivity increase
Number of hourly workers
Total annual hourly labor cost

Electricity Costs
Avg. KwH rate
Surcharge (per KwH)
Annual power usage (KwH)
Total annual electricity cost

TOTAL PRODUCTION COSTS


SG&A COSTS
Management Costs
Current Average annual rate
Annual increase %
Avg. annual pay labor rate
Current no. of workers
Annual productivity increase

5%
$0

5%
$0

5%
$0

$0.0717
$0.000
8,000,000
$573,300

$0.0752
$0.000
8,000,000
$601,965

$0.0790
$0.000
8,000,000
$632,063

$0.0830
$0.000
8,000,000
$663,666

$0.0871
$0.000
8,000,000
$696,850

5%
$0

5%
$0

5%
$0

5%
$0

2%
$1.05

2%
$1.07

2%
$1.09

2%
$1.11

2%

2%

2%

2%

169
$353,907

166
$353,766

163
$353,624

159
$353,483

$0.0915
$0.000
8,000,000
$731,692

$0.0960
$0.000
8,000,000
$768,277

$0.1008
$0.000
8,000,000
$806,691

$0.1059
$0.000
8,000,000
$847,025

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$1,074,900

$1,100,758

$1,127,916

$1,156,439

$1,186,396

$1,217,857

$1,250,899

$1,285,600

$1,322,043

$1,360,315

$1,400,508

3%
$30,900

3%
$31,827

3%
$32,782

3%
$33,765

3%
$34,778

3%
$35,822

3%
$36,896

3%
$38,003

3%
$39,143

3%
$40,317

6%
6%
6%
6%
3%
3%
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
14
13
12
12
11
10
$449,957
$435,649
$421,795
$408,382
$395,395
$382,822

3%

3%

3%

10
$370,648

9
$358,862

9
$347,450

0%
$30,000
16

6%

Overhead Costs
Corporate Allocation
50% allocation of direct costs
CM Profit 8%
Total annual OH costs

16
$480,000

15
$464,736

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$177,450

$177,379

$177,308

$177,237

$177,166

$177,095

$177,025

$176,954

$176,883

$176,812

$176,741

$124,392
$1,301,842

$125,240
$1,302,619

$126,230
$1,303,538

$127,367
$1,304,604

$128,655
$1,305,822

$130,099
$1,307,195

$131,704
$1,308,728

$133,474
$1,310,427

$135,415
$1,312,298

$137,534
$1,314,346

$139,837
$1,316,578

$8,000,000

0.03
$8,752,000

$9,574,688

$10,474,709

$11,459,331

$12,536,508

$13,714,940

$15,004,145

$16,414,534

$17,957,500

$19,645,505

$460,000

$460,000

$460,000

$460,000

$460,000

$460,000

$460,000

$460,000

$460,000

$460,000

$460,000

$10,241,842

$10,979,355

$11,788,183

$12,674,962

$13,646,948

$14,712,085

$15,879,064

$17,157,394

$18,557,481

$20,090,708

$21,769,533

$300,000
$1,000,000
$250,000
$200,000
$400,000
$6,000,000

$300,000
$0
$262,500
$210,000
$0

$300,000
$0
$275,625
$220,500
$0

$300,000
$0
$289,406
$231,525
$0

$300,000
$0
$303,877
$243,101
$0

$300,000
$0
$319,070
$255,256
$400,000

$300,000
$0
$335,024
$268,019
$0

$300,000
$0
$351,775
$281,420
$0

$300,000
$0
$369,364
$295,491
$0

$300,000
$0
$387,832
$310,266
$0

$300,000
$0
$407,224
$325,779
$400,000

$8,150,000

$772,500

$796,125

$820,931

$846,978

$1,274,327

$903,043

$933,195

$964,855

$998,098

$1,433,003

$19,466,742

$12,852,613

$13,712,224

$14,652,332

$15,680,321

$17,204,269

$18,033,006

$19,376,189

$20,844,378

$22,449,121

$24,603,044

1.00
$19,466,742

0.8696
$11,176,185

0.7561
$10,368,412

0.6575
$9,634,146

0.5718
$8,965,275

0.4972
$8,553,562

0.4323
$7,796,166

0.3759
$7,284,227

0.3269
$6,814,064

0.2843
$6,381,441

0.2472
$6,081,496
$102,521,717

Freight Rate %
Freight
Safety Stock
TOTAL SG&A COSTS
INVESTMENTS
Annual Capital Outlays
Start Up Costs
Additional Scott People To Manage CM
Additional Scott Travel
Molds
Buyback Lease Option

Discount Rate @ 15%


NPV

5%
$0

$30,000

Number of salaried managers


Total annual management labor cost

Total Costs

5%
$0

Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
$0.91
0%
2%
2%
2%
2%
2%
2%
$0.91
$0.93
$0.95
$0.97
$0.99
$1.00
$1.02
195
2%
2%
2%
2%
2%
2%
(Productivity assumed to increase at 2% annually.)
195
191
187
184
180
176
173
$354,900
$354,758
$354,616
$354,474
$354,333
$354,191
$354,049
(Assuming a 5 day work week, 8 hours/day and a 50 week year)
5.00% <--annual growth rate
$0.0650
$0.0683
$0.000
$0.000
8,000,000
8,000,000
$520,000
$546,000

Lease

TOTAL INVESTMENTS

5%
$0

10 YR NPV

Figure 6 Transportation Costs Sensitivity (Graph)

10 YR NPV

Freight Cost Change (%)


-5%
-4%
-3%
-2%
-1%
0%
1%
2%
3%
4%
5%
6%
7%
8%
9%
10%
11%
12%
13%
14%
15%

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

TEMECULA
98,782,957
98,958,251
99,142,553
99,336,371
99,540,239
99,754,719
99,980,407
100,217,927
100,467,939
100,731,137
101,008,253
101,300,058
101,607,360
101,931,015
102,271,918
102,631,014
103,009,296
103,407,805
103,827,640
104,269,952
104,735,951

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

$140,000,000

CHINA
73,478,821
74,881,169
76,355,588
77,906,131
79,537,073
81,252,918
83,058,417
84,958,577
86,958,673
89,064,260
91,281,190
93,615,625
96,074,048
98,663,283
101,390,510
104,263,279
107,289,529
110,477,607
113,836,284
117,374,778
121,102,769

Transportation Cost Sensitivity Analysis

$120,000,000

$100,000,000

$80,000,000

9.4% Freight increase per year

10 YR NPV TEMECULA

10 YR NPV CHINA
$60,000,000

$40,000,000

$20,000,000

10 YR NPV
$-5% -4% -3% -2% -1% 0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12% 13% 14% 15%
Freight Cost Change

Figure 7 NPV Calculations for Temecula with Productivity Annual Increase of 16.2%
Year:

10

PRODUCTION COSTS
Raw Materials
Current savings from use of regrind

($100,000)

Annual increase in savings due to regrind usage


Cost savings from use of regrind
Hourly Labor Costs

($100,000)

5%

5%

5%

5%

5%

5%

5%

5%

5%

5%

($105,000)

($110,250)

($115,763)

($121,551)

($127,628)

($134,010)

($140,710)

($147,746)

($155,133)

($162,889)

Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
$16.25

Current Avg. hourly rate


Annual increase %
Avg. hourly labor rate

$16.25

Current no. of workers

3%

3%

3%

3%

3%

3%

3%

3%

3%

3%

$16.74

$17.24

$17.76

$18.29

$18.84

$19.40

$19.99

$20.59

$21.20

$21.84

16.2%

16.2%

16.2%

16.2%

16.2%

16.2%

16.2%

16.2%

16.2%

195

Annual productivity increase

16.2%

Number of hourly workers


Total annual hourly labor cost

195

163

$6,337,500

$5,470,150

(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
137
115
96
81
68
57
47
$4,721,505

$4,075,320

$3,517,572

$3,036,157

$2,620,628

$2,261,969

40

33

$1,952,396

$1,685,191

$1,454,556

$0.2368

(Assuming a 5 day work week, 8 hours/day and a 50 week year)


Electricity Costs

4.00% <--annual growth rate


$0.1600
$0.1664
$0.1731

Avg. KwH rate


Surcharge (per KwH)
Annual power usage (KwH)

$0.1800

$0.1872

$0.1947

$0.2025

$0.2105

$0.2190

$0.2277

$0.025

$0.025

$0.025

$0.000

$0.000

$0.000

$0.000

$0.000

$0.000

$0.000

$0.000

8,000,000

7,683,200
$1,521,704

7,529,536
$1,355,153

7,378,945
$1,381,172

7,231,366
$1,407,690

7,086,739
$1,434,718

6,945,004
$1,462,264

6,806,104
$1,490,340

6,669,982
$1,518,954

6,536,582
$1,548,118

Total annual electricity cost

$1,480,000

7,840,000
$1,500,576

Lease

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$3,000,000

$10,717,500

$9,865,726

$9,132,959

$8,314,710

$7,777,193

$7,316,219

$6,921,336

$6,583,523

$6,294,990

$6,049,013

$5,839,785

TOTAL PRODUCTION COSTS


SG&A COSTS
Management Costs
Current Average annual rate

$125,000

Annual increase %
Avg. annual pay labor rate
Current no. of workers

0%

3%

3%

3%

3%

3%

3%

3%

3%

3%

3%

$125,000

$128,750

$132,613

$136,591

$140,689

$144,909

$149,257

$153,734

$158,346

$163,097

$167,990

6%

6%

6%

6%

3%

3%

3%

3%

3%

(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
14
13
12
12
11
10
10

$1,544,367

$1,495,257

$1,447,707

16

Annual productivity increase


Number of salaried managers
Total annual management labor cost

6%
16

15

$2,000,000

$1,936,400

$1,874,822

$1,815,203

$1,757,480

$1,701,592

$1,647,481

$1,595,091

Overhead Costs
Corporate Allocation
30% allocation of direct costs
CM Profit

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$2,345,250

$2,091,218

$1,872,963

$1,629,142

$1,469,623

$1,333,154

$1,216,604

$1,117,270

$1,032,821

$961,244

$900,802

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$3,345,250

$3,091,218

$2,872,963

$2,629,142

$2,469,623

$2,333,154

$2,216,604

$2,117,270

$2,032,821

$1,961,244

$1,900,802

$1,000,000

$1,030,000

$1,060,900

$1,092,727

$1,125,509

$1,159,274

$1,194,052

$1,229,874

$1,266,770

$1,304,773

$1,343,916

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$6,345,250

$6,057,618

$5,808,685

$5,537,072

$5,352,611

$5,194,020

$5,058,137

$4,942,235

$4,843,958

$4,761,273

$4,692,426

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Additional Scott People To Manage CM

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Additional Scott Travel

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Molds

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$500,000

$17,562,750

$16,423,343

$15,441,644

$14,351,782

$13,629,804

$13,010,239

$12,479,474

$12,025,759

$11,638,948

$11,310,286

$11,032,211

1.0

0.8696

0.7561

0.6575

0.5718

0.4972

0.4323

0.3759

0.3269

0.2843

Total annual OH costs


Freight Rate %
Freight
Safety Stock
TOTAL SG&A COSTS

0.03

INVESTMENTS
Annual Capital Outlays
Start Up Costs

TOTAL INVESTMENTS
Total Costs
Discout Factor @ 15%
NPV

$17,562,750

$14,281,168

$11,676,101

$9,436,530

$7,792,885

$6,468,388

$5,395,221

$4,520,928

$3,804,793

$3,215,089
10 YR NPV

0.2472

$2,726,994
$86,880,847

10

Figure 8 Temecula Productivity Sensitivity (Graph)


Temecula Annual Productivity Change (%)
0%
1%
2%
3%
4%
5%
6%
7%
8%
9%
10%
11%
12%
13%
14%
15%
16%
17%
18%
19%
20%

10 YR NPV
TEMECULA
CHINA
$ 110,721,881 $ 86,958,673
$ 108,601,919 $ 86,958,673
$ 106,590,968 $ 86,958,673
$ 104,683,104 $ 86,958,673
$ 102,872,716 $ 86,958,673
$ 101,154,487 $ 86,958,673
$ 99,523,383 $ 86,958,673
$ 97,974,636 $ 86,958,673
$ 96,503,733 $ 86,958,673
$ 95,106,404 $ 86,958,673
$ 93,778,607 $ 86,958,673
$ 92,516,520 $ 86,958,673
$ 91,316,530 $ 86,958,673
$ 90,175,219 $ 86,958,673
$ 89,089,357 $ 86,958,673
$ 88,055,891 $ 86,958,673
$ 87,071,938 $ 86,958,673
$ 86,134,774 $ 86,958,673
$ 85,241,827 $ 86,958,673
$ 84,390,667 $ 86,958,673
$ 83,579,002 $ 86,958,673

$120,000,000

Temecula Productivity Sensitivity Analysis

$100,000,000

$80,000,000

16.2% Productivity increase per year


$60,000,000

10 YR NPV TEMECULA
10 YR NPV CHINA
$40,000,000

$20,000,000

10 YR NPV
$0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12% 13% 14% 15% 16% 17% 18% 19% 20%
Temecula Productivity Change

11

Figure 9 NPV Calculations for China with Hourly Labor Cost Annual Increase of 39.5%
Year:

10

PRODUCTION COSTS
Raw Materials

Current savings from use of regrind

$0

Annual increase in savings due to regrind usage


Cost savings from use of regrind

$0

Hourly Labor Costs


Current Avg. hourly rate
Annual increase %
Avg. hourly labor rate
Current no. of workers
Annual productivity increase
Number of hourly workers
Total annual hourly labor cost

Electricity Costs
Avg. KwH rate
Surcharge (per KwH)
Annual power usage (KwH)
Total annual electricity cost

TOTAL PRODUCTION COSTS


SG&A COSTS
Management Costs
Current Average annual rate
Annual increase %
Avg. annual pay labor rate
Current no. of workers
Annual productivity increase

5%
$0

5%
$0

5%
$0

$0.0717
$0.000
8,000,000
$573,300

$0.0752
$0.000
8,000,000
$601,965

$0.0790
$0.000
8,000,000
$632,063

$0.0830
$0.000
8,000,000
$663,666

$0.0871
$0.000
8,000,000
$696,850

5%
$0

5%
$0

5%
$0

5%
$0

39.5%
$9.36

39.5%
$13.05

39.5%
$18.21

39.5%
$25.40

2%

2%

2%

2%

169
$3,167,437

166
$4,330,203

163
$5,919,821

159
$8,092,987

$0.0915
$0.000
8,000,000
$731,692

$0.0960
$0.000
8,000,000
$768,277

$0.1008
$0.000
8,000,000
$806,691

$0.1059
$0.000
8,000,000
$847,025

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$200,000

$1,074,900

$1,231,184

$1,436,595

$1,708,755

$2,071,736

$2,558,423

$3,213,752

$4,099,129

$5,298,480

$6,926,511

$9,140,012

3%
$30,900

3%
$31,827

3%
$32,782

3%
$33,765

3%
$34,778

3%
$35,822

3%
$36,896

3%
$38,003

3%
$39,143

3%
$40,317

6%
6%
6%
6%
3%
3%
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
14
13
12
12
11
10
$449,957
$435,649
$421,795
$408,382
$395,395
$382,822

3%

3%

3%

10
$370,648

9
$358,862

9
$347,450

0%
$30,000
16

6%

Overhead Costs
Corporate Allocation
50% allocation of direct costs
CM Profit 8%
Total annual OH costs

16
$480,000

15
$464,736

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$1,000,000

$177,450

$242,592

$331,647

$453,395

$619,836

$847,378

$1,158,451

$1,583,718

$2,165,102

$2,959,910

$4,046,493

$124,392
$1,301,842

$135,674
$1,378,265

$150,924
$1,482,572

$171,552
$1,624,947

$199,483
$1,819,319

$237,344
$2,084,723

$288,732
$2,447,183

$358,556
$2,942,275

$453,530
$3,618,632

$582,830
$4,542,740

$758,997
$5,805,490

$8,000,000
$460,000

0.03
$8,240,000
$460,000

$8,487,200
$460,000

$8,741,816
$460,000

$9,004,070
$460,000

$9,274,193
$460,000

$9,552,418
$460,000

$9,838,991
$460,000

$10,134,161
$460,000

$10,438,185
$460,000

$10,751,331
$460,000

$10,241,842

$10,543,001

$10,879,729

$11,262,412

$11,705,185

$12,227,298

$12,854,997

$13,624,087

$14,583,441

$15,799,787

$17,364,271

$300,000
$1,000,000
$250,000
$200,000
$400,000
$6,000,000

$300,000
$0
$262,500
$210,000
$0

$300,000
$0
$275,625
$220,500
$0

$300,000
$0
$289,406
$231,525
$0

$300,000
$0
$303,877
$243,101
$0

$300,000
$0
$319,070
$255,256
$400,000

$300,000
$0
$335,024
$268,019
$0

$300,000
$0
$351,775
$281,420
$0

$300,000
$0
$369,364
$295,491
$0

$300,000
$0
$387,832
$310,266
$0

$300,000
$0
$407,224
$325,779
$400,000

Freight Rate %
Freight
Safety Stock
TOTAL SG&A COSTS
INVESTMENTS
Annual Capital Outlays
Start Up Costs
Additional Scott People To Manage CM
Additional Scott Travel
Molds
Buyback Lease Option

Discount Rate @ 15%


NPV

5%
$0

$30,000

Number of salaried managers


Total annual management labor cost

TOTAL INVESTMENTS

5%
$0

Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
$0.91
0%
39.5%
39.5%
39.5%
39.5%
39.5%
39.5%
$0.91
$1.27
$1.77
$2.47
$3.45
$4.81
$6.71
195
2%
2%
2%
2%
2%
2%
(Productivity assumed to increase at 2% annually.)
195
191
187
184
180
176
173
$354,900
$485,184
$663,295
$906,790
$1,239,673
$1,694,757
$2,316,902
(Assuming a 5 day work week, 8 hours/day and a 50 week year)
5.00% <--annual growth rate
$0.0650
$0.0683
$0.000
$0.000
8,000,000
8,000,000
$520,000
$546,000

Lease

Total Costs

5%
$0

$8,150,000

$772,500

$796,125

$820,931

$846,978

$1,274,327

$903,043

$933,195

$964,855

$998,098

$1,433,003

$19,466,742

$12,546,685

$13,112,449

$13,792,099

$14,623,899

$16,060,048

$16,971,792

$18,656,412

$20,846,775

$23,724,396

$27,937,286

1.00
$19,466,742

0.8696
$10,910,161

0.7561
$9,914,895

0.6575
$9,068,529

0.5718
$8,361,262

0.4972
$7,984,682

0.4323
$7,337,374

0.3759
$7,013,636

0.3269
$6,814,848

0.2843
$6,743,954

0.2472
$6,905,670
$100,521,752

10 YR NPV

12

Figure 10 China Hourly Labor Cost Sensitivity (Graph)

China Hourly Labor Cost Change (%)


0%
3%
6%
9%
12%
15%
18%
21%
24%
27%
30%
33%
36%
39%
42%
45%
48%
51%

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$

10 YR NPV
TEMECULA
CHINA
100,467,939 $
86,729,016
100,467,939 $
87,082,378
100,467,939 $
87,493,006
100,467,939 $
87,970,776
100,467,939 $
88,527,175
100,467,939 $
89,175,540
100,467,939 $
89,931,321
100,467,939 $
90,812,373
100,467,939 $
91,839,289
100,467,939 $
93,035,768
100,467,939 $
94,429,021
100,467,939 $
96,050,229
100,467,939 $
97,935,046
100,467,939 $
100,124,153
100,467,939 $
102,663,878
100,467,939 $
105,606,869
100,467,939 $
109,012,846
100,467,939 $
112,949,412

$120,000,000

China Labor Cost Sensitivity Analysis

$100,000,000

$80,000,000

39.5% Labor cost increase per year

$60,000,000
10 YR NPV TEMECULA
10 YR NPV CHINA
$40,000,000

$20,000,000

10 YR NPV
$0% 3% 6% 9% 12% 15% 18% 21% 24% 27% 30% 33% 36% 39% 42% 45% 48% 51%
China Hourly Labor Cost Change

13

Vous aimerez peut-être aussi