Académique Documents
Professionnel Documents
Culture Documents
Description
20.00 9.50
A-Sub -Structure 1-Excavation and earth work 1.1-site clearance L=18+2=20m W=7.5+2=9.5m 2 190.00 m 2 190.00 m NET TOTAL 1.3 Bulk excavation
4 0.00 1.3Trench excavation Avg Depth = 0.62+0.55+0.64+0.74+0.70 5 = 0.65m m3 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m 4 m3 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m 4 m3 m3 NET TOTAL 1.4 Back fill Avg D = 0.60+0.56+0.55+0.30 = 0.5 m 4 m3 Avg D = 0.28+0.20+0.00+0.0.20 = 0.17m 4 1
11.7
9.62
1.48 22.80
Foundn_ Ditto as item no1.3 Avg Depth = 0.62+0.55+0.64+0.74+0.70= 0.65 5 m3 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m 4 3 m Avg D = 0.60+0.78+0.87+0.70 = 0.74 m 4 m3 m3 NET TOTAL
11.23
9.24
1.42 21.89
18.00 0.30 0.50 18.00 0.33 0.50 6.50 0.35 0.50 4.00 0.35 0.50
6.00 6.50 0.50 6.00 6.50 0.17 4.00 3.00 0.30 6.00 6.50 4.00 3.00
19.5
2.2-Ditto as item2.1 but ANGL (Average Height =50cm) Avg D = 0.60+0.40+0.20+0.00 = 0.3 m 4 3 2.7 m Avg D = 0.55+0.30+0.28+0.20 = 0.33m 4 3 2.97 m Avg D = 0.60+0.56+0.55+0.20+0.20+0.00 4 = 0.35m 3 4.55 m Avg D = 0.35m
3 0.7 m NET TOTAL 10.92
6.63 Avg D = 0.28+0.20+0.40+0.30 = 0.3m 4 3 7.2 m 3 33.33 m NET TOTAL 1.5Hard coring 2 78 m
2 24 m 2 102 m NET TOTAL 1.6Cart away
2 2
0.00 0.20 DITTO AS ITEM 1.1 BUT MELTI- BY 0.00 0.20 CM 0.00 DITTO AS ITEM 1.3 trench excavtion 3 0.00 m NET TOTAL
Take-off No_____________
contractor_________________
supervisor_________________
3 3.60 m
4 3.60 m
3
3 2.60 m
1 2.60 m
3
0.50 0.20
B.In 6cm thick reinforcement concrete window sills. Here price includes form work & 8mm deformed bars c/c 20cm both ways
3 0.40 m 3 6.60 m NET TOTAL 3.3 Steel reinforcement (a)Q6mm #REF! Kg
0 0
1.60 1.15
0.00 0.00
#REF!
#REF! 18.00 0.20 7.50 0.20 6.50 0.20 6.00 0.20 3.00 0.20 4.00 0.20
2 2
2 2 4 4 4 4
7.20 3.00 Internal 5.20 4 4.80 4 2.40 4 3.20 ` 2 25.80 m NET TOTAL 3.5.concrete ancillaries expantion joint 0.00 0.00 0.00 0.00 0.00 M NET TOTAL 4
0.00 m NET TOTAL 4.2 Steel reinforcement (a)Q6mm #REF! Kg b)Q12mm #REF! Kg 4.3 -form work 18.00 External 0.20 7.20 7.50 0.20 3.00 6.50 Internal 0.20 5.20 6.00 0.20 4.80 3.00 0.20 2.40 4.00 0.20 3.20 2 25.80 m NET TOTAL
0 0 0 0
Take-off No_____________
contractor_________________
supervisor_________________
contractor_________________
supervisor_________________
3 36.40 m
3 5.60 m Dedaction (To be checked again) Doors 3 5.60 m W2 3 8.28 m W1 3 1.92 m 3 76.6 m NET TOTAL
contractor_________________
supervisor_________________
3.25 0.65
2.95 0.7375 1.2 0.3 2.01 0.5025 0.68 0.17 1.33 0.3325
2.11 0.351667
1.18 0.295
contractor_________________
supervisor_________________
Contractor:-Tekle K/mariam B.C. construction Type;-Natural Stone Building;-Childhood Development Center(ECD) Location;-Enderta sites
Site name ;-Aragure Quantity No 1 1.1 1.2 1.3 1.4 1.5 1.6 2 2.1 2.2 3 3.1 3.2 3.3 Description A-SUB STRUCTURE Excavation &Earth Work Site clerance Bulk Excavation Trench excavation Fill under hard core borrowed Hard cring 25cm thick Cart away Sub total(1) Masonry work 50cm thick masoneryBNGL Dittoas2.1butANGL Sub total(2) .Concrete work 10cm Thick RC floor slab Unit Contrat m2 3 m 3 m 3 m 2 m 3 m m3 m3 m2 m3 kg kg kg m2 m Excuted Unit Price Total Price
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -
RC for 50*20cmgrade beam Steel reinforcement (a)Q6mm plain bars b)12mmDeformed bars 12mmDeformed bars 3.4 Form work for grade beam 3.5 concrete ancillaries expansion joint Sub total (3) B. Super Structure 4. Concrete work 4.1 Reinforced concrete class C-20,320kg a)In 50x20cm upper tie beam b)In 6cm thick reinforced concrete window sills. Here price includes form work & 8cm deformed bars c/c 20cm both ways. Steel reinforcement for upper T. beam cut bent & 4.2 placed in position unit price includes cutting bending placing in position & tying bars. a) 6mm plain bars b) 12mm deformed bars Provide cut and fix in position sawn pine wood or 4.3 equivalent formwork for upper tie beam. Sub total 4 5.1 5.2 50cm thick dressed masonery Ditto5.1 above top tie beam Sub total(5) 6. Roofing 6.1 G-30 galvanized corrugated iron sheet roofing fixed Sub total 6
m3 m
0.00
0.00
m3 m3
m2
Contractor:-Tekle K/mariam B.C. construction Type;-Natural Stone Building;-Childhood Development Center(ECD) Location;-Enderta sites
Site name ;-Aragure
_________________________ CONTRACTOR
_________________________ SUPERVISOR
No Description 7.Carpentry and joinery All timber & eucalptus structural members shall be a) 10-12cm eucalyptus lower/upper b) 8-10cm eucalyptus bracing and internal c)5x7cm treated pinewood purlins c/c 90cm. Supply and fix 25x2.5cm carraro or equivalent Sub total 7 Metal work metal windows &doors LTZ Type D1,size 100*280cm Type W1, size 115*180 TypeW2, size 160*60 wire mesh Security grill LtZ size 115*180cm Sub total(8) 9.PLASTERING AND POINTING Apply three coats of cement mortar plaster 1:3 to all internal walls including above top tie beam.and beam surfaces All external stone masonry foundation wall above NGL shall be raked out to a depth of 25mm and pointed in cement mortar 1:3 Unit Contrat
Quantity Excuted
Unit Price
Total Price
7.1
M M M M
13 12 40 60
4 10 4 9
0 0 0 0
9.1
259 30
50 20 500
9.2
m2 m2
9.3 Ditto as 9.2 above but external wall above grade beam Sub total 9 .5CM thick 10.PAVING AND FLOORINGscreed in smooth floor finished cement 10.1 cementwide & 10cm thick mass concrete 100cm mortar 1:3 10.2 pavement, concrete quality C-15,290 KG 10.3 Ditto as 10.3 above but 80cm wide to gable sides Sub total 10
26.4
m2 m2 m2
107 36 19
0 #REF! #REF!
50 180 180
Grand Total
#REF! #REF!
_________________________ CONTRACTOR
_________________________ SUPERVISOR
Contractor:-Tekle K/mariam B.C. construction Type;-Natural Stone Building;-Childhood Development Center(ECD) Location;-Enderta sites
Site name ;-Aragure
No
Discription A-sub structure 1 Excavation &Earth work 2 Masonry work 3 Concrete work
B-SUPER_STRUCTURE
4 5 6 7 8 9 10 11 12
Concrete work Walling Roofing Carpenrty&joinery Metal work Plastering&pointing Paving &Flooring Glazing Paainting
Total for class Room Building At Hawatsu
0.00
0.00
_________________________ CONTRACTOR
_________________________ SUPERVISOR
Site-Hawatsu Description No A-SUB STRUCTURE 1 1.1 1.2 1.3 1.4 1.5 1.6 2 2.1 2.2 3 3.1 3.2 3.3 Excavation &Earth Work Site clerance Bulk Excavation Trench excavation Fill under hard core borrowed Hard cring 25cm thick Cart away Sub total(1) Masonry work 50cm thick masoneryBNGL Dittoas2.1butANGL Sub total(2) .Concrete work 10cm Thick RC floor slab RC for 50*20cmgrade beam Steel reinforcement (a)Q6mm plain bars b)12mmDeformed bars 12mmDeformed bars Form work for grade beam concrete ancillaries expansion joint Sub total (3) B. Super Structure 4. Concrete work Reinforced concrete class C-20,320kg a)In 50x20cm upper tie beam b)In 6cm thick reinforced concrete window sills. Steel reinforcement for upper T. beam cut bent & a) 6mm plain bars b) 12mm deformed bars Provide cut and fix in position sawn pine wood or equivalent formwork for upper tie beam. Sub total 4 50cm thick dressed masonery Ditto5.1 above top tie beam Sub total(5) 6. Roofing G-30 galvanized corrugated iron sheet roofing fixed Sub total 6 m m3 m3 m3 2 m m3
2
Unit Price
Total Price
#REF! 0.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.00 #REF! #REF! #REF! #REF! #REF! #REF!
m3 3 m
2 3
45 25
#REF! #REF!
300.00 400.00
m m
3.4 3.5
kg kg kg m2 m
4.1
m3 m kg kg m2
#REF! #REF! 0.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.2
m3 m3 m2
6.1
190
#REF!
210
_________________________ CONTRACTOR
_________________________ SUPERVISOR
Site-Hawatsu No
Description
Unit Price
Total Price
7.1
7.Carpentry and joinery All timber & eucalptus structural members shall be a) 10-12cm eucalyptus lower/upper b) 8-10cm eucalyptus bracing and internal c)5x7cm treated pinewood purlins c/c 90cm. Supply and fix 25x2.5cm carraro or equivalent Sub total 7 Metal work metal windows &doors LTZ Type D1,size 100*280cm Type W1, size 115*180 TypeW2, size 160*60 wire mesh Security grill LtZ size 115*180cm Sub total(8) 9.PLASTERING AND POINTING Apply three coats of cement mortar plaster 1:3 to all internal walls including above top tiewall above All external stone masonry foundation beam.and NGL shall beabove but external wall above grade Ditto as 9.2 raked out to a depth of 25mm and beam Sub total 9 .5CM thick 10.PAVING AND FLOORINGscreed in smooth floor finished cement cementwide & 10cm thick mass concrete 100cm mortar 1:3 pavement, concrete quality C-15,290 KG Ditto as 10.3 above but 80cm wide to gable sides
M M M M
13 12 40 60
4 10 4 9
m2 m2 2 m
259 30 26.4
50 20 500
m m2 m2
107 36 19
#REF! #REF!
50 50 180
Sub total 10
Grand Total
#REF! #REF!
_________________________ CONTRACTOR
_________________________ SUPERVISOR
Q8
Q 12 75.12 73.92
62.40 60.00
C/c 20cm
C/c 20cm
0.395
Reinforcement bar Schedule Contractor:-Tekle K/mariam B.C. Building;-Childhood Development Center(ECD) Site- Aragure BAR SCHEDULE FOR TOP TIE BEAM
Location Shape Dia(m Length(mete No.Bars m) r) No.of Bars Elem Tot.No SUB TOTAL Dia.6 Dia.8 Dia.10 Dia.12
C/C 20
12 12 6 12 12 6.5 12 12 6
2 2 2 4 4 4 1 1 1
4 4 182 8 8 136 2 2 21
C/c 20cm
C/c 20cm
0.395
0.617
__________________________ CONTRACTOR
______________________-__ SUPERVISOR
__________________________ CONTRACTOR
______________________-__ SUPERVISOR
1-Excavation & Earth work 1.1.Clear the site and remove top soil at an average depth of 20cm L= 3.5 + 2 *2=7.5 m 45.00 W= 2+2*2= 6 m 2 45.00 m 1.3 Excavation in ordinery soil for the dry laterine pit up to a depth of 5.2 and for foundation trenches
7.5 6.00
2.58
1.68
1 2
2 1.79 3 34.99 m NET TOTAL 1.4 Excavation in rock formation for the dry laterine pit up to a depth of 5.2 and for foundation trenches
19.34
2.40 3.20 1.20 9.22 1.5 Selected Excavated fill under Hard core
1.00 1.00
3 1.00 m NET TOTAL 1.6 25cm thick basaltic or equivalent stone hard core well roled ..
0.25 3.00
0.00
1.5 Cart away surples excavated 0.00 materials 0.00 3 0.00 m NET TOTAL
1 1
3.17 13.05
0.48
1 a) 10mm deformed bars 52.28 KG NET TOTAL b) 12mm deformed bars 138.28 KG NET TOTAL
0.36 16.34
4.CONCRETE WORK 4.1.Reinforced concrete class c20 A.in 20*20 cm elevation col 0.20 0.20 2.80 5.30 0.20 0.20 1.93 0.20 0.20 1.94 0.20 0.15 1.20 0.15 0.20
5.60 0.25 5.40 0.25 2.33 0.25 1.93 0.25 0.60 0.20 0.75 0.15 1.00 0.20
2.80
3 0.67 m 3 0.67 m NET TOTAL b.in 20*20 cm upper tie beam 3 0.42 m
5.40
1.17
8
3 0.08 m
3.86
2
3 0.12 m
0.24
4 0.14 3 0.66 m NET TOTAL C.In 6cm thick reinforcement concrete window sills. Here price includes form work & 8mm deformed bars c/c 20cm both ways 2
2 4
0.89 2.80
1.78 11.20 12.98 ml NET TOTAL 4.2.STEEL REINFORCEMENT FOR UPPER TIE BEAM a) 6mm plain bars 29.68 KG NET TOTAL b) 12mm deformed bars 138.28 KG NET TOTAL
5.HOLLOW CONCRETE BLOCK WALL 5.1.20*20*40cm class "B" hallow concrete block 4.70 3.15 3.60 2 2 3.60 0.5 4.70 0.75
2 25.92 m Above Top Tie Beam
2 29.61 m
6 3
3.85 5.3
3 3
3.00 5.00
1.00 2.58
2 4
2.23 1.0
m2
2 53.90 m NET TOTAL
2.00
9.52 2
2 8.82 m 2 18.34 m NET TOTAL 6.ROOFING 6.1. G-30 galvanazed C.I.S
29.61
2 2
25.92
3.53
5.16 53.90
4.76
0.36
14. Painting 14.1Apply three coats of approved plastic paint to all internal walls & plastered beam surfaces a)To external wall
53.90 Ditto But as item No. 9.1,a 53.90 M2 otal
1.00 2 0.20 0.77 4 0.15 2.15 0.15 2.38 0.20 0.60 0.20 0.46 0.40
1.29
0.95
1.20 0.89 1.93 1.00 2.33 0.15 0.75 0.15 1.00 0.20
2.35
9.3. Ditto as 9.2 above but external wall above grade beam
9.68
4 2
6.20 1.00
12.40 12.40
2
2 2.24 m
2.50 0.80
4.00 4.00
A=5.3*0.9*0.5=2.39
2 4.78 m
deduction m2 1.07 2
2 2
7.20 2.33
1.00 2.38
68.00
Take-off No_____________
B.C.
Description 2.MASONRY WORK 2.1. Basaltic or equivalent 50 CM thick stone masonry foundation trench, wall thickness varries acccorrding to the drawing
m3
m3
M3 Total M3 Total
Take-off No_____________
B.C.
Description 3.4 Provide cut and fix in position sawn pine wood or equivalent form work for sides of Floor slab P=(2.33+5.6)*2=15.86M m2 m2 for slab
Take-off No_____________
B.C.
Description 4.3.provide cut & fix in position swan pine wood form work for upper tie beam
m2 external
m2 internal
m2 soffit of windows
m2 soffit of doors
m2 NET TOTAL
Take-off No_____________
B.C.
Description
7. Carpentry and Joinery 7.1.all timber & ecuallyptus structure members shall be well seasoned A.F 10-12cm eucalyptus lower/upper members(trusses)
ML NET TOTAL B.F 8-10cm eucalyptus internal members(trusses) L=(0.22+0.56)*2+0.9=2.46 L=(1.15+1.35)*2=5.00 ML NET TOTAL C.5*7 cm purlins c/c 90cm ML NET TOTAL 7.2,Supply & fix 25*2.5cm facia board
ML NET TOTAL 7.3,Supply & fix 50mm PVC vent pipe PC 7.4 40x50 cm zigba or equivalent lids (as shown on the drawing to cover the dry latrine pit holes) PC 8.METAL WORK all metal windows and doors shall be fabricated of locally manufactured frame LTZ profile 8.1.Type D2 size .80*2.80cm pcs 9.PLASTERING AND POINTING 9.1.Apply three coats of cement mortar plaster 1:3 to all internal walls including above top tie beam.and beam surfaces m2
Take-off No_____________
B.C.
m2
soffit of doors
sied of doors
sied of window
Take-off No_____________
B.C.
Description
10.PAVING AND FLOORING 10.1.5CM thick smooth floor finished cement screed in cement mortar 1:3 m2
m2 DOORS m2 m2
m2 NET TOTAL 10.2. 100cm wide & 10cm thick mass concrete pavement, concrete quality C15,290 KG cement/m3 of concrete, m2 m2 NET TOTAL 10.3. Ditto as 10.3 above but 80cm wide to gable sides
m2 NET TOTAL
11. Apply three coats of approved plastic paint to all internal walls & plastered beam surfaces
Ditto But as item No. 9.1 m2 NET TOTAL
Summary Of Projects
Sno Project Type 1 ECD 2 Dry Latrine Location Aragure Egri Hariba Contract Executed #REF! 0.00
Total
#REF!
Contractor
Supervisor
yKF MSK
First paym
Aragure ECD and Egri hariba Dry Latrine Enderta Woreda in Tigray Region
As per the attached measurements the Value of work executed and/or materials supplied to-date is 20418 hundred four thousand one hundred eighty sex Birr and 38/100 cents)
qN Date
DMR
TOTAL
ypDM KF BR Amount of Advance Taken (birr) XSk ytmls ypDM KF BR Amount of Advance Repaid to-date (birr)
MRm __________________________________________________________________________________
trUG**L Certified
_______________________________ kN Date
__________________ kN Date
W WL Main Contract w/o VAT tq{ WL Supplementary Contract ylW_ | T:C Variation orders VAT 15% .-Q DMR Total sum with VAT
tq>
DEDUCTIONS
2. Q> Rebate 3. m 4. Contract amount after rebate 5. Value add tax 15% 6. Total amount with 15% VAT Retention 5% 7. mq Penalty 8. kQD KF % 15%
Deduction for Advance payment Recovery (20%) 9. l@ Others DMR yt lt+ ykfL gNzB Net Sum due to the Contractor l| t+ BR 189612.58 l!kfL ml#N XrUGlN:: We certify that the contractor is now entitled to the sum of Birr 189612.58 (Two hundred eight nine hundred twelve Birr and 58/100 cents) TOTAL
___________________________________________
_________________________________________ T4 T5 T6
__________________ kN Date
204,186.38
0.00
ctor
__________________ kN Date