INTRODUCTION

Industry of construction is one of sector that has a high risk in working. A lot of damage could be happen in death, money, and production delay. So, we need implementation of Safety and Health Environment (SHE) system to prevent this kind of problem.

DEFINITION SHE Is an activity begin with planning, implementation, and controlling to prevent risk in safety and health of work GENERAL PURPOSES Avoid Risk Prevent accident at work Decrease consequences because accident

SPECIAL PURPOSES In order to ensure that PT. Total BangunPersada policies about Safety and Healthy in Construction can be implemented in Central Park project well. FUNDAMENTAL LAW

SHE MANAGEMENT SYSTEM-CENTRAL PARK

Page 1

A. PT. Total Bangun Persada SHE Prosedure B. PT. Total Bangun Persada SHE standard C. PT. Total Bangun Persada cleanliness and tidiness standard D. Minister Regulation No.01/Men/1980, about SHE in Building construction E. Joint decision of PU Ministry & Labor minister number :KEP.174/MEN/1986 & No 104/KPTS/1986 F. PT.Total Bangun Persada SHE pocket book G. Regulation of Labor Minister No.PER.05/MEN/1996 H. Decision of Indonesian Health Minister Number 1405/MENKES/SK/XI/2002 about Health requirements for office work environments and industries I. Occupational Health and safety Assessment Series-OHSAS 180001:1999

PROJECT OVERVIEW

PROJECT DATA
Project Name Various Owner Area Building Area of work Access of time Time remaining Job Progress : : : : : : : Central Park Project Mixed (Mall-Apartment-Office-Hotel)

PT Tiara Metropolitan Jaya 86,000 m2 652,000 m2 SAME (Mall) + Structure (Tower)\ : : 25 months (01 August 07 31 August 09) 9,5 months

34% (Progress Oct 08)\

SHE MANAGEMENT SYSTEM-CENTRAL PARK

Page 2

MAIN CONTRACTORS PERSADA CONCEPT ARCHITECTS LEAD ARCHITECTS NASIONAL CIVIL & STRUCTURAL ENGINEER

: PT TOTAL BANGUN

: DP ARCHITECTS PTE LTD : PT ARKIPURI INTRA

: PT GISTAMA INTI SEMESTA : PT SKEMANUSA

MECHANICAL & ELECTRICAL CONSULTANT KONSULTAMA TEKNIK GEOTECHNICAL ENGINEERS SITE SURVEYORS SOIL INVESTIGATION QUANTITY SURVEYORS TRAFFIC CONSULTANT

: PT PRATAMA WIDYA : PT MARMOYA BARUNA PERSADA : PT PRATAMA WIDYA : PT WILDE & WOOLARD : PT PAMINTORI CIPTA

SHE MANAGEMENT SYSTEM-CENTRAL PARK

Page 3

Writer limited this explanation in Safety only.

SHE MANAGEMENT SYSTEM-CENTRAL PARK

Page 4

ORGANIZATION CHART

SCOPE OF SHE PLANNING Include provisions for administrative and managerial control as well as deal with safety and environmental health projects working at the Central Park area of Jakarta, assigned to all employees and workers who work the Central Park project, or guests as well as representatives / workers and other companies working in the Central Park project. SAFETY PROGRAM 1. TRAINING

SHE MANAGEMENT SYSTEM-CENTRAL PARK

Page 5

Head of safety must meet the competency of personnel safety and emergency response team planned and implemented in coordination with the HRD (training center level). The training is tailored to the specific needs of the project. 2. SAFETY INDUCTION Done to give directions to workers and every guest who comes. Can be made in writing on a board shown on each worker, workers should be given induction has signed a statement following the induction. 3. SAFETY TALK Briefing in groups according to the work area or job discipline. Conducted in the morning before work began (for about
10-15 minutes). Briefing materials: - Potential dangers of the job that day & precautions - Order - Information events that often occur in the field - Material handling to prevent accidents on the condition that

must be observed.
4. Safety inspection Aims to maintain consistency in the application of SHE and covers the entire project area. Safety managers must make inspection reports and discrepancy SHE reports, at least 60 minutes after the inspection is completed. 5. Safety Patrol Conducted by safety supervisors, covering all areas of work and the areas where there is work that has identified a potential accident.
No . ACTIVITY PARTICIPANT/PLACE SCHEDULE PIC

SAFETY INDUCTION 1 Safety Induction Staff, workers & visitors Early in the project As needed Safety officer

Tool Box Meeting

Staff & workers

Safety officer

SHE MANAGEMENT SYSTEM-CENTRAL PARK

Page 6

3 4

Safety Talks Safety Coordination Meeting

All safety staff TBP staff & subcon

Min. 1x/ week Min 1 x/ month

Safety officer Safety officer

INSPECTION 1 Safety Patrol Safety officer& Safety supervisor PM, SM, Safety (TBP& subcontractor) everyday Safety officer

Safety inspection

Min. 1 x/month

Project Manager

Monthly Reports

Safety Manager must make a monthly report. This report was sent to safety managers at headquarters, 05th date after the end of the month. And also be equipped with the information that cases are still in progress (if any)
ACTIVITY PARTICIPANT/ PLACE SCHEDULE PIC

N O REPORTS 1 Daily reports

everyday

Safety officer Safety officer Safety officer Safety officer

SHE inspection reports

From the results of inspection SHE (1x week) If there is a discrepancy or an accident Every 5th of every month

Report mismatches of SHE, Near miss (near misses) & accident reports Monthly reports

HEALTH WORK 1 Employment medical examination of the Social Security 1 x year or as scheduled GA

HIRARC (Hazard Identification, Risk Assesment and risk control)


HIRARC include: All activities

SHE MANAGEMENT SYSTEM-CENTRAL PARK

Page 7

Prevention action plan to identify potential hazards are to be zero or becomes dangerous levels down as low as possible.

N O 1

SELF PROTECTION EQUIPMENT

TYPE OF JOB/ USE All the people on the project site, including subcontractors

SPECIFICATION MSA, JSW

Safety helm

2 3

Safety shoes
Rubber Shoes / Work Shoes

TBP staff Workers in site

Protective steel in the front end (safety toe)


Closed at the front end, at least a high ankle

Dust mask

Used in a dusty work environment Works with the risk of eye injury (grinding, workers who use the cutting wheel), etc.

May contain dangerous dust particles / smoke


help spark small debris & dust fine to the eye

Protective goggles

Ear Plugs

People who work in areas that high noise levels above 85 db, such as grinding, ramset, generators work in the area, erection
People who work at a height of 2 m / more, working in the elevator

Decrease noise levels which is more than 85 desibel

Safety Belt/ Full Body Harness

Able to withstand the load in accordance specification, no


Page 8

SHE MANAGEMENT SYSTEM-CENTRAL PARK

shaft, the gondola and being around the building or void parameter

defects (a reasonable use condition)

Masker Fume

People who work with chemicals, such as painters, etc.

withstand chemical particles (such as chemical particles paints etc.)

Gloves

A blacksmith, carpenter, rigger, etc. Workers who work with chemicals, such as fogging workers, working with electricity
welding & cutting and cutting torch

Made of fabric (kind of polka-dot) (made of rubber / latex, isolator material

10

Rubber gloves

11

Protective clothing Welding apron Welding gloves Welding shields

Can protect users from the dangers of a spark, to gloves made of leather, for welding shield can protect the eyes & face from sparks

SHE MANAGEMENT SYSTEM-CENTRAL PARK

Page 9

Conclusion: Central park is a huge project. PT Total Bangun Persada, as Main Contractor, give their best to reach construction goal. Succeed in Cost, Quality, Time, and Safety and Heath in work. To achieve Safety in work, PT. Total Bangun Persada have their own policies such as in safety regulation, safety planning, safety program, safety control, etc. These kinds of policies should be done by all people in construction site, worker, and visitor.