Académique Documents
Professionnel Documents
Culture Documents
SAIEA
Figure 2: Illustration of cables and increasing levels of armouring each end of the cable. A typical lightweight cable has a 17 mm outer diameter and comprises a welded steel tube housing multiple fibre pairs in a stress-free environment. In order to protect the cable, depending on the level of risk, the number and diameter of armour wires surrounding the cable is increased, with a high strength double armoured cable having an outer diameter of approximately 45 mm (Figure 2).
Figure 1: Route of the proposed EASSy cable down the east coast of Africa.
SAIEA 2009
SAIEA 2009
SAIEA 2009
Scoping Phase public participation From the outset, the client was concerned that appeals or legal disputes from the trawling industry would either delay environmental authorisation or project implementation. The process was therefore designed to ensure that the trawling industry was provided with maximum opportunity to comment and participate, and that off-shore cable route alternatives could be considered. In order to ensure that the best cable route alternative could be selected, the environmental consultant ensured that the process of stakeholder consultation would align with the programme of the international cable route team who were planning the routes and the marine survey. The consultant was well aware that once the marine survey was undertaken, no other offshore alignments would be considered due to the technical planning requirements and costs associated with a marine survey.
Specialist study The Oceanographic Research Institute was appointed to undertake a specialist study focusing on the impacts of different cable routes upon the trawling grounds and industry. The data used was the most accurate data available and consisted of 19,943 trawl deployments and catches between 2000-2006. This data had been recorded by the trawlers as per the requirements of their licences. The specialist study focussed on the potential loss of trawling grounds on both the Thukela Banks and offshore grounds for the original proposed
SAIEA 2009
SAIEA 2009
The importance of the inshore Thukela Banks fishing grounds relative to the rest of the fishing grounds, and the influence of the closure of the St Lucia estuary mouth on catches on these grounds. The influence of cheaper imports of the same prawn species on fishing effort on the Thukela Banks. The licensed trawling periods on the Thukela Banks had been reduced over the period for which data was available, from 12 months to only six months of the year. This influenced the relative contribution of the catches from
After careful consideration of the findings it was apparent that if trawlers continued to operate over and around the initial cable route proposed, as had occurred with the SAFE cable, there would be little impact upon the industry or the economic viability of the trawling grounds. However, when applying a applying a risk-averse and cautious approach from both technical and environmental perspectives, it was preferable that trawling did not occur over the cable and that the cable route selected should minimize its impact on the trawling grounds. Yet, a range of other factors still needed to be taken into account such as the findings of the final bathymetric survey, cable protection and length, feasible cable angles and turnsetc. which influence the cost and risks of different cable routes. These factors would influence the final
SAIEA 2009
SAIEA 2009
Lessons learnt
For an Environmental Impact Assessment to add value to a project, the key environmental issues, impacts and risks need to be identified and investigated in time so that they can influence technical planning and decisions. If projects are not timed and coordinated correctly, the technical planning process may proceed without environmental input, reducing the EIA to just another administrative requirement that the client must obtain. The more contentious and difficult an issue is to assess, the more careful the consideration of all factors must be, and the more stakeholder participation is required. An Impact Assessment Report should explain how the findings were interpreted, what assumptions were made, what uncertainties were identified, and how the final recommendation was influenced by these factors. This allows the thinking and interpretation behind the assessment to be understood by stakeholders.
www.saiea.com
SAIEA 2009