DEFENCE HEAD QUARTERS COMPLEX AT AKUREGODA

MASTER PROGRAMME FOR MAIN BUILDING - 29.05.2012


Activity ID

Activity Name

MAIN BUILDING - 29.05.2012


PROJECT MILESTONES

Original
Duration

Remaining
Duration

Start

Finish

1683d
1609d

1607d

14-Feb-12 A

30-Sep-16

30-Sep-16

1564d

27-Apr-12 A

30-Sep-16

30-Sep-16

27-Apr-12 A

A21060

COMMENCEMENT DAT E OF CONST RUCTION

0d

0d

A21040

Issuance of Piling Tender for Block 4 Building

0d

0d

11-Jun-12*

A21030

Acquire Land for Dumping Excavated Material

0d

0d

30-Jun-12*

A21050

Approval & Award of Piling Tender for Block 4 Building after


recommendation

0d

0d

24-Jul-12

A26750

Issuance of Piling Tender for Block 3 Building

0d

0d

26-Jul-12

A26760

Approval & Award of Piling Tender for Block 3 Building after


recommendation

0d

0d

07-Sep-12

A26770

PROJECT COMPLETION DATE

0d

0d

30-Sep-16*

1095d

BLOCK 6 (SLA 1) FOR SRI LANKA ARMY


RAFT FOUNDATION

1019d

14-Feb-12 A

18-Feb-15

169d
26d

93d
0d

14-Feb-12 A
14-Feb-12 A

31-Jul-12
02-Apr-12 A

A1000

Bulk Excavation of Soil up to +8.0 (m) MSL

A1010

Setting out of Block 6 (SLA 1)

1d

0d

03-Apr-12 A

03-Apr-12 A

A1020

Excavation for Raft from +8.0 (m) MSL to +6. 5 (m) MSL (1.5m
depth)

7d

0d

03-Apr-12 A

09-Apr-12 A

A1030

Excavation of Final 300mm Height

31d

0d

26-Apr-12 A

27-Apr-12 A

A1040

Lay 1000G Polythene and Screed Concrete

31d

31d

27-Apr-12 A

06-Jun-12

A1050

Application of Membrane Type Wat er P roofing

32d

32d

15-May-12

21-Jun-12

A1060

Protection Screed for Water Proofing Membrane

32d

32d

19-May-12

26-Jun-12

A1070

Reinforcement work to Raft

40d

40d

22-May-12 A

07-Jul-12

A1080

Formwork to Raft

40d

40d

26-May-12 A

19-Jul-12

A1090

Concreting to Raft Foundation

40d

40d

29-May-12 A

24-Jul-12

A1100

Curing to Raft Foundation

45d

45d

09-Jun-12

31-Jul-12

963d
671d
249d
50d
48d

963d
671d
249d
50d
48d

25-Jun-12
25-Jun-12
25-Jun-12
25-Jun-12
06-Jul-12

18-Feb-15
30-Apr-14
02-Mar-13
13-Aug-12
22-Aug-12

MAIN STRUCTURE
LOWER LEVEL 3 (LL3) +8.50 MSL
STRUCTURAL WORKS
COLUMNS RAFT TO P TO LOWER LEVEL 2
SHEAR WALLS & LIFT WALLS FROM RAFT TOP TO LL2

Remaining Level of Effort

% Complete

Page 1 / 9

Actual Work

Summary

Remaining Work

Milestone

Critical Remaining Work

2012
2013
2014
2015
2016
F M A M J J A S ON D J F MA M J J A S O ND J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N

18-Feb-15
31-Jul-12

18-Feb-15
30-Apr-14
02-Mar-13
13-Aug-12
22-Aug-12
Date
29-May-12

Revision
DRAFT - TO BE REVIEWED BY RELEVANT DISCIPLINES
ACTIVITY DURATIONS MAY CHANGE WITH DETAILED DESIGN DRAWINGS

Checked

Approved

Activity ID

Activity Name

Original
Duration

BEAMS & SLAB - LOWER LEVEL 2 (LL 2)


FACADE (OUTER CONCRETE WALL) CONSTRUCTIO N
INTERNAL FINISHES

Remaining
Duration

Start

Finish

A9820

Block work

23d
36d
547d
20d

A9830

Internal Wall Plast ering

25d

25d

10-Apr-13

11-May-13

A9840

Floor Finishes

30d

30d

16-May-13

19-Jun-13

A9850

Internal Wall Paint ing - 1st coat

12d

12d

20-Jun-13

03-Jul-13

A9930

Wall Tiling in Toilets

21d

21d

20-Jun-13

10-Jul-13

A9920

Internal Wall Paint ing - Final Coat

12d

12d

19-Mar-14

30-Mar-14

67d
0d

67d
0d

11-Jan-14
11-Jan-14*

18-Mar-14

SPECIALIST CONTRACTOR WORK

23d
36d
547d
20d

04-Jul-12
26-Jan-13
26-Sep-12
26-Sep-12

26-Jul-12
02-Mar-13
30-Mar-14
18-Oct-12

A10130

Commencement of Specialist Contactors' Works after


Approval & Award of Tenders

A9970

Installation of Ceiling Framing System

28d

28d

13-Jan-14

13-Feb-14

A10070

Fabrication & Fixing of Door & Window Frames

28d

28d

13-Jan-14

13-Feb-14

A10080

Fabrication & Fixing of Door & Window sashes

28d

28d

14-Feb-14

18-Mar-14

A10090

Installation of Ceiling Panels

21d

21d

14-Feb-14

10-Mar-14

392d
0d

392d
0d

02-Apr-13
02-Apr-13*

30-Apr-14

313d
365d
349d
392d
671d
670d
670d
671d
670d
672d
673d
670d
667d
544d
90d

313d
365d
349d
392d
671d
670d
670d
671d
670d
672d
673d
670d
667d
544d
90d

02-Apr-13
02-Apr-13
02-Apr-13
02-Apr-13
28-Jul-12
30-Aug-12
02-Oct-12
03-Nov-12
06-Dec-12
08-Jan-13
09-Feb-13
14-Mar-13
19-Apr-13
30-Jun-13
30-Jun-13

10-Feb-14
03-Apr-14
18-Mar-14
30-Apr-14
02-Jun-14
04-Jul-14
06-Aug-14
08-Sep-14
10-Oct-14
12-Nov-14
15-Dec-14
16-Jan-15
18-Feb-15
29-Dec-14
27-Sep-13

MEP WORKS

A9960

Commencement of MEP Works after A pproval & Award of


MEP Tenders

MECHANICAL WORKS
ELECTRICAL WORKS
PLUMBING WORKS
ICT WORKS

LOWER LEVEL 2 (LL2) +13.05 MSL


LOWER LEVEL 1 (LL1) +17.6 MSL
GROUND FLOOR (GR. FL.) +23.55 MSL
1ST FLOOR (1ST. FL.) +28.45 MSL
2ND FLOOR (2ND. FL.) +33.35 MSL
3RD FLOOR (3RD. FL.) +38.25 MSL
4TH FLOOR (4TH. FL.) +43.15 MSL
5TH FLOOR (5TH. FL.) +48.05 MSL
6TH FLOOR (6TH. FL.) +52.95 MSL
EXTERNAL WORKS & FINISHES

A15310

Roof Construction

A10260

Installation of Rain Water Harvesting System & Rain Water


Overhead Tank

120d

120d

28-Sep-13

27-Jan-14

A15320

External Wall Plastering

90d

90d

28-Sep-13

28-Dec-13

A10320

Installation of City Water Overhead Tank

90d

90d

28-Jan-14

27-Apr-14

A15330

External Wall Painting

52d

52d

06-Nov-14

29-Dec-14

Remaining Level of Effort

% Complete

Page 2 / 9

Actual Work

Summary

Remaining Work

Milestone

Critical Remaining Work

2012
2013
2014
2015
2016
F M A M J J A S ON D J F MA M J J A S O ND J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N

26-Jul-12
02-Mar-13
30-Mar-14

18-Mar-14

30-Apr-14

10-Feb-14
03-Apr-14
18-Mar-14
30-Apr-14
02-Jun-14
04-Jul-14
06-Aug-14
08-Sep-14
10-Oct-14
12-Nov-14
15-Dec-14
16-Jan-15
18-Feb-15
29-Dec-14

Date
29-May-12

Revision
DRAFT - TO BE REVIEWED BY RELEVANT DISCIPLINES
ACTIVITY DURATIONS MAY CHANGE WITH DETAILED DESIGN DRAWINGS

Checked

Approved

Activity ID

Activity Name

Original
Duration

BLOCK 7 (SLA 2) FOR SRI LANKA ARMY


RAFT FOUNDATION

Remaining
Duration

Start

Finish

1126d

1126d

02-Jul-12

07-Aug-15

141d
30d

141d
30d

02-Jul-12
02-Jul-12

19-Nov-12
04-Aug-12

A15340

Bulk Excavation of Soil up to +8.0 (m) MSL

A15350

Setting out of Block 7 (SLA 2)

1d

1d

06-Aug-12

06-Aug-12

A15360

Excavation for Raft from +8.0 (m) MSL to +6. 5 (m) MSL (1.5m
depth)

8d

8d

07-Aug-12

15-Aug-12

A15440

Excavation of Final 300mm Height

40d

40d

16-Aug-12

01-Oct-12

A15370

Lay 1000G Polythene and Screed Concrete

40d

40d

17-Aug-12

02-Oct-12

A15380

Application of Membrane Type Wat er P roofing

40d

40d

20-Aug-12

04-Oct-12

A15390

Protection Screed for Water Proofing Membrane

40d

40d

22-Aug-12

06-Oct-12

A15400

Reinforcement work to Raft

56d

56d

24-Aug-12

27-Oct-12

A15410

Formwork to Raft

56d

56d

30-Aug-12

02-Nov-12

A15420

Concreting to Raft Foundation

60d

60d

04-Sep-12

12-Nov-12

A15430

Curing to Raft Foundation

65d

65d

05-Sep-12

19-Nov-12

991d
615d
616d
615d
614d
607d
606d
605d
603d
602d
601d
374d
1258d

991d
615d
616d
615d
614d
607d
606d
605d
603d
602d
601d
374d
1258d

14-Nov-12
14-Nov-12
27-Dec-12
08-Feb-13
23-Mar-13
09-May-13
21-Jun-13
03-Aug-13
16-Sep-13
29-Oct-13
11-Dec-13
04-Mar-14
02-Jul-12

07-Aug-15
25-Jul-14
05-Sep-14
17-Oct-14
28-Nov-14
09-Jan-15
20-Feb-15
03-Apr-15
15-May-15
26-Jun-15
07-Aug-15
14-Mar-15
17-Dec-15

MAIN STRUCTURE
LOWER LEVEL 3 (LL3) +8.50 MSL
LOWER LEVEL 2 (LL2) +13.05 MSL
LOWER LEVEL 1 (LL1) +17.6 MSL
GROUND FLOOR (GR. FL.) +23.55 MSL
1ST FLOOR (1ST. FL.) +28.45 MSL
2ND FLOOR (2ND. FL.) +33.35 MSL
3RD FLOOR (3RD. FL.) +38.25 MSL
4TH FLOOR (4TH. FL.) +43.15 MSL
5TH FLOOR (5TH. FL.) +48.05 MSL
6TH FLOOR (6TH. FL.) +52.95 MSL
EXTERNAL WORKS & FINISHES

BLOCK 4 FOR SRI LANKA AIR FORCE


PILE FOUNDATION

A1570

Bulk Excavation of Soil up to +8.0 (m) MSL

209d
26d

209d
26d

02-Jul-12
02-Jul-12

28-Jan-13
31-Jul-12

A1580

Piling Work (90 Nos .)

45d

45d

01-Aug-12

21-Sep-12

A1600

Excavation for Pile Caps & Tie beams

28d

28d

14-Sep-12

16-Oct-12

A1590

Pile hacking & Pile Testing

28d

28d

17-Sep-12

18-Oct-12

A1610

Lay 1000G Polythene and Screed Concrete

32d

32d

01-Oct-12

06-Nov-12

A1680

Application of Membrane Type Wat er P roofing

32d

32d

04-Oct-12

09-Nov-12

Remaining Level of Effort

% Complete

Page 3 / 9

Actual Work

Summary

Remaining Work

Milestone

Critical Remaining Work

2012
2013
2014
2015
2016
F M A M J J A S ON D J F MA M J J A S O ND J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N

07-Aug-15
19-Nov-12

07-Aug-15
25-Jul-14
05-Sep-14
17-Oct-14
28-Nov-14
09-Jan-15
20-Feb-15
03-Apr-15
15-May-15
26-Jun-15
07-Aug-15
14-Mar-15
17-Dec-15
28-Jan-13

Date
29-May-12

Revision
DRAFT - TO BE REVIEWED BY RELEVANT DISCIPLINES
ACTIVITY DURATIONS MAY CHANGE WITH DETAILED DESIGN DRAWINGS

Checked

Approved

Activity ID

Activity Name

Original
Duration

Remaining
Duration

Start

Finish

A1620

Protection Screed for Water Proofing Membrane

32d

32d

08-Oct-12

13-Nov-12

A1630

Reinforcement work to Pile caps & Tie Beams

37d

37d

11-Oct-12

22-Nov-12

A1640

Formwork to Pile caps & tie beams

35d

35d

19-Oct-12

28-Nov-12

A1650

Concreting Pile caps & Tie beams

39d

39d

23-Oct-12

06-Dec-12

A1660

Curing to Pile caps & tie beams

45d

45d

24-Oct-12

14-Dec-12

A1720

Basement Slab Construction

45d

45d

07-Dec-12

28-Jan-13

1049d
771d
770d
767d
761d
759d
756d
754d
752d
751d
752d
629d
90d

1049d
771d
770d
767d
761d
759d
756d
754d
752d
751d
752d
629d
90d

29-Jan-13
29-Jan-13
02-Mar-13
04-Apr-13
10-May-13
12-Jun-13
15-Jul-13
16-Aug-13
18-Sep-13
21-Oct-13
22-Nov-13
02-Feb-14
02-Feb-14

17-Dec-15
14-Mar-15
14-Apr-15
14-May-15
13-Jun-15
14-Jul-15
13-Aug-15
12-Sep-15
13-Oct-15
14-Nov-15
17-Dec-15
25-Oct-15
02-May-14

MAIN STRUCTURE
LOWER LEVEL 3 (LL3) +8.50 MSL
LOWER LEVEL 2 (LL2) +13.05 MSL
LOWER LEVEL 1 (LL1) +17.6 MSL
GROUND FLOOR (GR. FL.) +23.55 MSL
1ST FLOOR (1ST. FL.) +28.45 MSL
2ND FLOOR (2ND. FL.) +33.35 MSL
3RD FLOOR (3RD. FL.) +38.25 MSL
4TH FLOOR (4TH. FL.) +43.15 MSL
5TH FLOOR (5TH. FL.) +48.05 MSL
6TH FLOOR (6TH. FL.) +52.95 MSL
EXTERNAL WORKS & FINISHES

A26720

Roof Construction

A26700

Installation of Rain Water Harvesting System & Rain Water


Overhead Tank

120d

120d

03-May-14

30-Aug-14

A26730

External Wall Plastering

90d

90d

03-May-14

31-Jul-14

A26710

Installation of City Water Overhead Tank

90d

90d

31-Aug-14

28-Nov-14

A26740

External Wall Painting

52d

52d

04-Sep-15

25-Oct-15

1374d

1374d

01-Aug-12

13-May-16

BLOCK 3 FOR SRI LANKA NAVY


PILE FOUNDATION

A32440

Bulk Excavation of Soil up to +8.0 (m) MSL

265d
28d

265d
28d

01-Aug-12
01-Aug-12

24-Apr-13
01-Sep-12

A32450

Piling Work (134 Nos.)

67d

67d

22-Sep-12

08-Dec-12

A32470

Excavation for Pile Caps & Tie beams

28d

28d

01-Dec-12

02-Jan-13

A32460

Pile hacking & Pile Testing

28d

28d

04-Dec-12

04-Jan-13

A32480

Lay 1000G Polythene and Screed Concrete

32d

32d

10-Dec-12

15-Jan-13

A32540

Application of Membrane Type Wat er P roofing

32d

32d

13-Dec-12

18-Jan-13

A32490

Protection Screed for Water Proofing Membrane

32d

32d

17-Dec-12

22-Jan-13

Remaining Level of Effort

% Complete

Page 4 / 9

Actual Work

Summary

Remaining Work

Milestone

Critical Remaining Work

2012
2013
2014
2015
2016
F M A M J J A S ON D J F MA M J J A S O ND J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N

17-Dec-15
14-Mar-15
14-Apr-15
14-May-15
13-Jun-15
14-Jul-15
13-Aug-15
12-Sep-15
13-Oct-15
14-Nov-15
17-Dec-15
25-Oct-15

13-May-16
24-Apr-13

Date
29-May-12

Revision
DRAFT - TO BE REVIEWED BY RELEVANT DISCIPLINES
ACTIVITY DURATIONS MAY CHANGE WITH DETAILED DESIGN DRAWINGS

Checked

Approved

Activity ID

Activity Name

Original
Duration

Remaining
Duration

Start

Finish

A32500

Reinforcement work to Pile caps & Tie Beams

37d

37d

20-Dec-12

31-Jan-13

A32510

Formwork to Pile caps & tie beams

45d

45d

28-Dec-12

18-Feb-13

A32520

Concreting Pile caps & Tie beams

45d

45d

01-Jan-13

21-Feb-13

A32530

Curing to Pile caps & tie beams

45d

45d

02-Jan-13

22-Feb-13

A32550

Basement Slab Construction

50d

50d

22-Feb-13

24-Apr-13

1109d
876d
826d
813d
799d
787d
772d
761d
749d
736d
719d
482d
120d

1109d
876d
826d
813d
799d
787d
772d
761d
749d
736d
719d
482d
120d

25-Apr-13
25-Apr-13
07-Jun-13
20-Jul-13
02-Sep-13
15-Oct-13
27-Nov-13
09-Jan-14
21-Feb-14
05-Apr-14
22-May-14
13-Aug-14
13-Aug-14

13-May-16
21-Sep-15
14-Sep-15
14-Oct-15
13-Nov-15
14-Dec-15
13-Jan-16
12-Feb-16
14-Mar-16
13-Apr-16
13-May-16
09-Dec-15
10-Dec-14

MAIN STRUCTURE
LOWER LEVEL 3 (LL3) +8.50 MSL
LOWER LEVEL 2 (LL2) +13.05 MSL
LOWER LEVEL 1 (LL1) +17.6 MSL
GROUND FLOOR (GR. FL.) +23.55 MSL
1ST FLOOR (1ST. FL.) +28.45 MSL
2ND FLOOR (2ND. FL.) +33.35 MSL
3RD FLOOR (3RD. FL.) +38.25 MSL
4TH FLOOR (4TH. FL.) +43.15 MSL
5TH FLOOR (5TH. FL.) +48.05 MSL
6TH FLOOR (6TH. FL.) +52.95 MSL
EXTERNAL WORKS & FINISHES

A32410

Roof Construction

A32390

Installation of Rain Water Harvesting System & Rain Water


Overhead Tank

120d

120d

11-Dec-14

11-Apr-15

A32420

External Wall Plastering

90d

90d

11-Dec-14

12-Mar-15

A32400

Installation of City Water Overhead Tank

90d

90d

12-Apr-15

10-Jul-15

A32430

External Wall Painting

52d

52d

19-Oct-15

09-Dec-15

1306d

1306d

03-Sep-12

08-Apr-16

102d
28d

102d
28d

03-Sep-12
03-Sep-12

13-Dec-12
04-Oct-12

BLOCK 8 FOR OCDS


RAFT FOUNDATION

A38240

Bulk Excavation of Soil

A38250

Setting out

1d

1d

05-Oct-12

05-Oct-12

A38260

Excavation for Raft

4d

4d

06-Oct-12

10-Oct-12

A38340

Excavation of Final 300mm Height

20d

20d

11-Oct-12

02-Nov-12

A38270

Lay 1000G Polythene and Screed Concrete

20d

20d

12-Oct-12

03-Nov-12

A38280

Application of Membrane Type Wat er P roofing

20d

20d

15-Oct-12

06-Nov-12

A38290

Protection Screed for Water Proofing Membrane

20d

20d

17-Oct-12

08-Nov-12

A38300

Reinforcement work to Raft

20d

20d

29-Oct-12

20-Nov-12

Remaining Level of Effort

% Complete

Page 5 / 9

Actual Work

Summary

Remaining Work

Milestone

Critical Remaining Work

2012
2013
2014
2015
2016
F M A M J J A S ON D J F MA M J J A S O ND J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N

13-May-16
21-Sep-15
14-Sep-15
14-Oct-15
13-Nov-15
14-Dec-15
13-Jan-16
12-Feb-16
14-Mar-16
13-Apr-16
13-May-16
09-Dec-15

08-Apr-16
13-Dec-12

Date
29-May-12

Revision
DRAFT - TO BE REVIEWED BY RELEVANT DISCIPLINES
ACTIVITY DURATIONS MAY CHANGE WITH DETAILED DESIGN DRAWINGS

Checked

Approved

Activity ID

Activity Name

Original
Duration

Remaining
Duration

Start

Finish

A38310

Formwork to Raft

20d

20d

06-Nov-12

28-Nov-12

A38320

Concreting to Raft Foundation

20d

20d

13-Nov-12

05-Dec-12

A38330

Curing to Raft Foundation

30d

30d

14-Nov-12

13-Dec-12

1212d
1163d
984d
994d
1007d
1018d
1027d
1040d
1047d
1059d
300d
1396d

1212d
1163d
984d
994d
1007d
1018d
1027d
1040d
1047d
1059d
300d
1396d

06-Dec-12
06-Dec-12
26-Dec-12
15-Jan-13
02-Feb-13
21-Feb-13
12-Mar-13
30-Mar-13
22-Apr-13
10-May-13
02-Jul-14
05-Oct-12

08-Apr-16
19-Feb-16
09-Sep-15
09-Oct-15
09-Nov-15
09-Dec-15
08-Jan-16
08-Feb-16
09-Mar-16
08-Apr-16
29-Apr-15
08-Aug-16

MAIN STRUCTURE
LOWER LEVEL 2 (LL2) +13.05 MSL
LOWER LEVEL 1 (LL1) +17.6 MSL
GROUND FLOOR (GR. FL.) +23.55 MSL
1ST FLOOR (1ST. FL.) +28.45 MSL
2ND FLOOR (2ND. FL.) +33.35 MSL
3RD FLOOR (3RD. FL.) +38.25 MSL
4TH FLOOR (4TH. FL.) +43.15 MSL
5TH FLOOR (5TH. FL.) +48.05 MSL
6TH FLOOR (6TH. FL.) +52.95 MSL
EXTERNAL WORKS & FINISHES

BLOCK 2 FOR MOD


PILE FOUNDATION

A44360

Bulk Excavation of Soil

221d
28d

221d
28d

05-Oct-12
05-Oct-12

15-May-13
06-Nov-12

A44370

Piling Work (75 Nos .)

38d

38d

10-Dec-12

22-Jan-13

A44390

Excavation for Pile Caps & Tie beams

28d

28d

15-Jan-13

15-Feb-13

A44380

Pile hacking & Pile Testing

28d

28d

17-Jan-13

18-Feb-13

A44400

Lay 1000G Polythene and Screed Concrete

32d

32d

23-Jan-13

28-Feb-13

A44460

Application of Membrane Type Wat er P roofing

32d

32d

26-Jan-13

04-Mar-13

A44410

Protection Screed for Water Proofing Membrane

32d

32d

30-Jan-13

07-Mar-13

A44420

Reinforcement work to Pile caps & Tie Beams

37d

37d

02-Feb-13

16-Mar-13

A44430

Formwork to Pile caps & tie beams

45d

45d

11-Feb-13

03-Apr-13

A44440

Concreting Pile caps & Tie beams

45d

45d

14-Feb-13

06-Apr-13

A44450

Curing to Pile caps & tie beams

50d

50d

15-Feb-13

17-Apr-13

A44470

Basement Slab Construction

30d

30d

08-Apr-13

15-May-13

1162d
1143d
929d
940d
952d
963d
975d
987d
998d

29-May-13
29-May-13
18-Jun-13
08-Jul-13
26-Jul-13
14-Aug-13
02-Sep-13
20-Sep-13
09-Oct-13

08-Aug-16
20-Jul-16
08-Jan-16
08-Feb-16
09-Mar-16
08-Apr-16
09-May-16
08-Jun-16
08-Jul-16

MAIN STRUCTURE

1162d
1143d
929d
940d
952d
963d
975d
987d
998d

LOWER LEVEL 2 (LL2) +13.05 MSL


LOWER LEVEL 1 (LL1) +17.6 MSL
GROUND FLOOR (GR. FL.) +23.55 MSL
1ST FLOOR (1ST. FL.) +28.45 MSL
2ND FLOOR (2ND. FL.) +33.35 MSL
3RD FLOOR (3RD. FL.) +38.25 MSL
4TH FLOOR (4TH. FL.) +43.15 MSL
5TH FLOOR (5TH. FL.) +48.05 MSL

Remaining Level of Effort

% Complete

Page 6 / 9

Actual Work

Summary

Remaining Work

Milestone

Critical Remaining Work

2012
2013
2014
2015
2016
F M A M J J A S ON D J F MA M J J A S O ND J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N

08-Apr-16
19-Feb-16
09-Sep-15
09-Oct-15
09-Nov-15
09-Dec-15
08-Jan-16
08-Feb-16
09-Mar-16
08-Apr-16
29-Apr-15
08-Aug-16
15-May-13

08-Aug-16
20-Jul-16
08-Jan-16
08-Feb-16
09-Mar-16
08-Apr-16
09-May-16
08-Jun-16
08-Jul-16
Date
29-May-12

Revision
DRAFT - TO BE REVIEWED BY RELEVANT DISCIPLINES
ACTIVITY DURATIONS MAY CHANGE WITH DETAILED DESIGN DRAWINGS

Checked

Approved

Activity ID

Activity Name

6TH FLOOR (6TH. FL.) +52.95 MSL


EXTERNAL WORKS & FINISHES

Original
Duration

Remaining
Duration

Start

Finish

1010d
300d
90d

1010d
300d
90d

28-Oct-13
30-Sep-14
30-Sep-14

08-Aug-16
28-Jul-15
30-Dec-14

A43330

Roof Construction

A43310

Installation of Rain Water Harvesting System & Rain Water


Overhead Tank

120d

120d

31-Dec-14

29-Apr-15

A43340

External Wall Plastering

90d

90d

31-Dec-14

30-Mar-15

A43350

External Wall Painting

52d

52d

31-Mar-15

21-May-15

A43320

Installation of City Water Overhead Tank

90d

90d

30-Apr-15

28-Jul-15

1178d

16-May-13

11-Aug-16

1178d

BLOCK 5 - AUDITORIUM
RAFT FOUNDATION

A48600

Bulk Excavation of Soil

99d
28d

99d
28d

16-May-13
16-May-13

22-Aug-13
17-Jun-13

A48610

Setting out

1d

1d

18-Jun-13

18-Jun-13

A48620

Excavation for Raft

4d

4d

19-Jun-13

22-Jun-13

A48700

Excavation of Final 300mm Height

20d

20d

24-Jun-13

16-Jul-13

A48630

Lay 1000G Polythene and Screed Concrete

20d

20d

25-Jun-13

17-Jul-13

A48640

Application of Membrane Type Wat er P roofing

20d

20d

27-Jun-13

19-Jul-13

A48650

Protection Screed for Water Proofing Membrane

20d

20d

29-Jun-13

22-Jul-13

A48660

Reinforcement work to Raft

20d

20d

08-Jul-13

30-Jul-13

A48670

Formwork to Raft

20d

20d

16-Jul-13

07-Aug-13

A48680

Concreting to Raft Foundation

20d

20d

23-Jul-13

14-Aug-13

A48690

Curing to Raft Foundation

30d

30d

24-Jul-13

22-Aug-13

1087d
419d
500d
510d
521d
1006d
300d
90d

1087d
419d
500d
510d
521d
1006d
300d
90d

15-Aug-13
15-Aug-13
06-Sep-13
26-Sep-13
16-Oct-13
04-Nov-13
10-Aug-14
10-Aug-14

11-Aug-16
09-Oct-14
22-Jan-15
21-Feb-15
24-Mar-15
11-Aug-16
07-Jun-15
07-Nov-14

MAIN STRUCTURE
LOWER LEVEL 3 (LL3) +8.50 MSL
LOWER LEVEL 2 (LL2) +13.05 MSL
LOWER LEVEL 1 (LL1) +17.6 MSL
GROUND FLOOR (GR. FL.) +23.55 MSL
1ST FLOOR (1ST. FL.) +28.45 MSL
EXTERNAL WORKS & FINISHES

A48570

Roof Construction

A48550

Installation of Rain Water Harvesting System & Rain Water


Overhead Tank

120d

120d

08-Nov-14

09-Mar-15

A48580

External Wall Plastering

90d

90d

08-Nov-14

07-Feb-15

A48590

External Wall Painting

52d

52d

08-Feb-15

31-Mar-15

Remaining Level of Effort

% Complete

Page 7 / 9

Actual Work

Summary

Remaining Work

Milestone

Critical Remaining Work

2012
2013
2014
2015
2016
F M A M J J A S ON D J F MA M J J A S O ND J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N

08-Aug-16
28-Jul-15

11-Aug-16
22-Aug-13

11-Aug-16
09-Oct-14
22-Jan-15
21-Feb-15
24-Mar-15
11-Aug-16
07-Jun-15

Date
29-May-12

Revision
DRAFT - TO BE REVIEWED BY RELEVANT DISCIPLINES
ACTIVITY DURATIONS MAY CHANGE WITH DETAILED DESIGN DRAWINGS

Checked

Approved

Activity ID

Activity Name

A48560

Original
Duration

Installation of City Water Overhead Tank

COMMUNICATION BUILDING
RAFT FOUNDATION

Remaining
Duration

Start

Finish

90d

90d

10-Mar-15

07-Jun-15

500d

500d

22-Nov-13

09-Apr-15

A52090

Bulk Excavation of Soil

97d
28d

97d
28d

22-Nov-13
22-Nov-13

28-Feb-14
24-Dec-13

A52100

Setting out

1d

1d

25-Dec-13

25-Dec-13

A52110

Excavation for Raft

4d

4d

26-Dec-13

30-Dec-13

A52190

Excavation of Final 300mm Height

20d

20d

31-Dec-13

22-Jan-14

A52120

Lay 1000G Polythene and Screed Concrete

20d

20d

01-Jan-14

23-Jan-14

A52130

Application of Membrane Type Wat er P roofing

20d

20d

03-Jan-14

25-Jan-14

A52140

Protection Screed for Water Proofing Membrane

20d

20d

06-Jan-14

28-Jan-14

A52150

Reinforcement work to Raft

20d

20d

14-Jan-14

05-Feb-14

A52160

Formwork to Raft

20d

20d

22-Jan-14

13-Feb-14

A52170

Concreting to Raft Foundation

20d

20d

29-Jan-14

20-Feb-14

A52180

Curing to Raft Foundation

30d

30d

30-Jan-14

28-Feb-14

361d
238d
235d
250d
277d
300d
90d

361d
238d
235d
250d
277d
300d
90d

21-Feb-14
21-Feb-14
20-Mar-14
19-Apr-14
16-May-14
12-Jun-14
12-Jun-14

18-Feb-15
16-Oct-14
09-Nov-14
26-Dec-14
18-Feb-15
09-Apr-15
09-Sep-14

MAIN STRUCTURE
BASEMENT FLOOR +8.0 MSL
GROUND FLOOR +13.2 MSL
1ST FLOOR +17.2 MSL
2ND FLOOR +21.2 MSL
EXTERNAL WORKS & FINISHES

A52060

Roof Construction

A52040

Installation of Rain Water Harvesting System & Rain Water


Overhead Tank

120d

120d

10-Sep-14

09-Jan-15

A52070

External Wall Plastering

90d

90d

10-Sep-14

08-Dec-14

A52080

External Wall Painting

52d

52d

09-Dec-14

31-Jan-15

A52050

Installation of City Water Overhead Tank

90d

90d

10-Jan-15

09-Apr-15

502d

502d

10-Apr-15

25-Aug-16

99d
28d

10-Apr-15
10-Apr-15

17-Jul-15
12-May-15

SECURITY BUILDING
RAFT FOUNDATION

A53830

Bulk Excavation of Soil

99d
28d

A53840

Setting out

1d

1d

13-May-15

13-May-15

A53850

Excavation for Raft

4d

4d

14-May-15

18-May-15

Remaining Level of Effort

% Complete

Page 8 / 9

Actual Work

Summary

Remaining Work

Milestone

Critical Remaining Work

2012
2013
2014
2015
2016
F M A M J J A S ON D J F MA M J J A S O ND J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N

09-Apr-15
28-Feb-14

18-Feb-15
16-Oct-14
09-Nov-14
26-Dec-14
18-Feb-15
09-Apr-15

25-Aug-16
17-Jul-15

Date
29-May-12

Revision
DRAFT - TO BE REVIEWED BY RELEVANT DISCIPLINES
ACTIVITY DURATIONS MAY CHANGE WITH DETAILED DESIGN DRAWINGS

Checked

Approved

Activity ID

Activity Name

Original
Duration

Remaining
Duration

Start

Finish

A53930

Excavation of Final 300mm Height

20d

20d

19-May-15

10-Jun-15

A53860

Lay 1000G Polythene and Screed Concrete

20d

20d

20-May-15

11-Jun-15

A53870

Application of Membrane Type Wat er P roofing

20d

20d

22-May-15

13-Jun-15

A53880

Protection Screed for Water Proofing Membrane

20d

20d

25-May-15

16-Jun-15

A53890

Reinforcement work to Raft

20d

20d

02-Jun-15

24-Jun-15

A53900

Formwork to Raft

20d

20d

10-Jun-15

02-Jul-15

A53910

Concreting to Raft Foundation

20d

20d

17-Jun-15

09-Jul-15

A53920

Curing to Raft Foundation

30d

30d

18-Jun-15

17-Jul-15

305d
229d
229d
251d
300d
90d

305d
229d
229d
251d
300d
90d

10-Jul-15
10-Jul-15
06-Aug-15
02-Sep-15
29-Oct-15
29-Oct-15

11-May-16
25-Feb-16
23-Mar-16
11-May-16
25-Aug-16
28-Jan-16

MAIN STRUCTURE
GROUND FLOOR +8.5 MSL
1ST FLOOR +12.5 MSL
2ND FLOOR +16.5 MSL
EXTERNAL WORKS & FINISHES

A53800

Roof Construction

A53780

Installation of Rain Water Harvesting System & Rain Water


Overhead Tank

120d

120d

29-Jan-16

27-May-16

A53810

External Wall Plastering

90d

90d

29-Jan-16

27-Apr-16

A53820

External Wall Painting

52d

52d

28-Apr-16

18-Jun-16

A53790

Installation of City Water Overhead Tank

90d

90d

28-May-16

25-Aug-16

348d

348d

01-Sep-15

15-Aug-16

300d

300d

01-Sep-15*

15-Aug-16

140d

140d

14-May-16

30-Sep-16

140d

140d

14-May-16

30-Sep-16

BLOCK 1 - BUILDING
A50160

Construction of Block 1 Building (DRAWINGS TO BE


RECEIVED FOR DETAILING)

TESTING, COMMISSIONING & HANDING OVER


A54740

Testing, Commissioning & Handing over of Buidings

Remaining Level of Effort

% Complete

Page 9 / 9

Actual Work

Summary

Remaining Work

Milestone

Critical Remaining Work

2012
2013
2014
2015
2016
F M A M J J A S ON D J F MA M J J A S O ND J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N

11-May-16
25-Feb-16
23-Mar-16
11-May-16
25-Aug-16

15-Aug-16

30-Sep-16

Date
29-May-12

Revision
DRAFT - TO BE REVIEWED BY RELEVANT DISCIPLINES
ACTIVITY DURATIONS MAY CHANGE WITH DETAILED DESIGN DRAWINGS

Checked

Approved