Académique Documents
Professionnel Documents
Culture Documents
BACKGROUND CAMBODIA
Country: Area 181,035 sq km, water 2.5%. Population 13.4 million. Pop growth rate 1.54% (NIS, 2008) GDP growth rate 6.4% (2011) GDP/capita $830 (NIS, 2010)
Hydro power potential about 10,000 MW, at present the capacity < 3% used
ENERGY POLICY
To provide an adequate supply of energy throughout Cambodia at reasonable and affordable price,
To ensure a reliable and secured electricity supply at reasons price, which facilitates investment in Cambodia and development of national economy, To encourage exploration and environmentally and socially acceptable development of energy resources needed for supply to all sectors of Cambodia economy, To encourage the efficient use of energy and to minimize the detrimental environmental affects resulted from energy supply and consumption.
In 2011 the national electrification increased to 35%, while the household in urban areas were almost 100% electrified and only 14% of the total household in rural areas.
Beside domestic supply, Cambodia imported
electricity from Loas, Thailand and Vietnam with total capacity about 285MW in 2011. It increased about 22% from 2010. Cambodia has a good potential of hydropower about 10,000 MW. At present, about 10% to the potential under construction.
In 2011 the total electricity supply increased to 2,674.38 GWh within install capacity about 635.5MW. While, the importing electiricity accounted for 45%.
Since last decade till 2008, Cambodia heavily relied on DO/HFO to generate electricity. DO/HFO accounted about 90%. However, in recent year, the importing electricity from neighboring countries are accounted more than 40%.
By concerning on electricity supply security and to reduce the vulnerability in the power sector as well as the electricity price that effected by the high oil price in the market, Cambodia tend to import more electricity.
Interm of increasing the total install capacity and importing electricity to meet the growing demand, as result for a decade, we see that the electricity per capita was increasing steadly. At the same time, the national electrification also increased.
A-Development of Generation
C-Rural Electrification
Increasing diversify of power supply such as Hydro, Coal power, Importing electricity, biomass and others renewable energies to meet the electricity demand and reduce fuel oil for power generation.
Development the national transmission line, GMS & ASEAN power grid, maximize mini-grid to rural areas, upgrading the HV, MV & LV.
- Grid Expansion - Cross-border supply from Neighboring countries - Mini grids Dev.mt - Renewable Energy Dev.mt
A- Development of Generation
A1- Project Existing
No.
1
Power-Project
Kirirom I
Install Capa.MW
12
IA/PPA/LA
BOT
Company
CETIC
Country
China
COD
2001
Achiev ement
100%
2
3 4
Ochum
Coal plant Kamchay Hydro
1
10 194.1
BOO BOT
EDC
CIIDG Sinohydro
Cambodia
China China
2002
2010 2011
100%
100% 100%
Power-Project
Kirirom III Coal Power Plant Atay Hydro
Install Capa.MW
18 100 120
IA/PPA/LA
BOT BOO BOT
Company
CETIC CEL CHD
Country
China Malaysia China
COD
2012 2013 2013
Achiev ement
95% 20% 49%
4
5 6 7
270
338 246 270
BOO
BOT BOT BOO
CIIDG
China Huadian Sinohydro CIIDG
China
China China China
2014
2014 2015 2016
10%
40% 40% -
1
2 3
400
2600 375
PFS
F/S F/S
----
Vietnam
China Korea
4
5 6 7 8 9 10 11 12 13
330
235 24 36 75 17 64 64 40 900
F/S
F/S F/S F/S F/S F/S F/S F/S F/S F/S
-----------
China
China Korea Korea China China Korea Korea Korea Vietnam
Fuel Type
Hydro Hydro Hydro Coal Hydro Hydro Coal Coal Coal Coal Hydro Coal Hydro Coal Coal Hydro Coal/Natural Gas Hydro
Install Capa.MW
194.1 18 120 100 246 338 270 100 100 135 400 100 108 100 200 450/2600 400 900 4,279.1 (6,429.1)
COD
2011 2012 2013 2013 2013-2014 2013 2014 2016 2017 2016 2016 2018 2017 2019 2020 2019 2020 2020
Base on PDP, by 2020, Cambodia intent to develop more domestic hydropower to contribute in the electricity supply which share more than 50%.
72%
1%
27%
16
1
2 3 4 5 6 7 8 9 10
230 kV, Takeo - Kampot, (construct substation in Kampot), 230 kV, Steung Treng - Loa PDR, (construct substation in Steung Treng), 110 kV, Kampong Cham - Viet Nam, (construct 3 substations: Kampong Cham, - Soung, - Pongnearkreak ),
230 kV, Kampot - Sihanouk Ville 230 kV, Phnom Penh - Kampong Chhnang - Pursat - Battambong, (construct 3 substations: - Kampong Chhnang, - Pursat, Battambong), 230 kV, Pursat - Osom, (construct 1 substation in Osom Commune), 230 kV, Kampong Cham Kratie, 230 kV, Kratie Stung Treng, 230 kV, Phnom Penh Kampong Cham, 220 kV, Phnom Penh Sihanoukville, along national road 4, (construct 1 substation in Sre Ambil) 115 kV, East Phnom Penh Neakleung Svay Rieng, (construct 2 substations: - Neakleung, - Svay Rieng)
87
56 68 82 310 175 110 126 110 220
KFW
WB WB ADB & JBIC CYC CYC CUPL INDIA CUPL CHMC
2011
2014 2010 2013 2012 2012 2013 2015 2012 2013
11
120
2014
No. 12 13 14 15 16 17
Transmission Expansion Plan 230 kV, Stung Tatay Hydro Osom substation, 115 kV, West Phnom Penh East Phnom Penh ( construct substation GS4 at South Phnom Penh) 230 kV, Stung Chay Areng Hydro North Phnom Penh (NPP) substation 230 kV, Stung Chay Areng - Osom substation 230 kV, Kampong Cham - Kampong Thom - Siem Reap, (construct 1 substation in Kampong Thom) 500 kV, Loa PDR (Ban Sok)- Steung Treng Vietnam (Tay Ninh), (construct substation in Steung Treng) Total Transmission Line
C- Rural Electrification
In 2011 the national electrification increased to 35%, while the household in urban areas were almost 100% electrified and only 14% of the total household in rural areas. Mainly mni grids in rural areas based on diesel for their generations and supplies with high tariff between US$ 0.65-US$1.00; There are a number of biomas gassifiers (approx.50) supply power in rural areas with their tariff US$0.60US$0.90; Few micro-hydropwers in rural areas as pilot /grant by donors, JICA,
Investment in constructing sub-transmissions from sub-stations to rural areas to replace high cost of power generation
It requires huge investment cost to achieve the target setted ( US$M 50/year from now to 2030).
Level- up Plan of Village Elect rificat ion Rat io (including Bat t ery Light ing)
Diesel Mini-Grid
Electrification Strategies ES1 to ES3
70%
60.0%
50.0%
47%
40.0% Diesel Mini-Grid Biomass Mini-Grid 20.0%
Electrification Strategies ES1 to ES3 Short-term Policy Measures SP1 to SP3 Mid-term Policy Measures MP1 to MP3
30.0%
10.0%
2020
2030
New BCS Existing BCS Hydro Biomass New diesel Existing diesel Grid
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29 20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
Ye ars
20
30
25
kar)a:n;sanTunvinieyaK
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Grid extension
Year
Year
26
Thanks!
28