Vous êtes sur la page 1sur 15

Estimation and costing by dutta 25 Revised Edition fourth reprint 2003 page 486 item no.

5 Cement concrete 1:5:10 in Foundation or Floor with Brick Ballast 40mm(1.5") Thick gauge - unit 1 Cu.M. Take - 10 Cu.M. Particulars Materials Brick Ballast 1st class 40mm gauge Sand (Local) Cement (28.5 Bags) Labour, etc . Mistri(Head Mason) Mason Mazdoor(Beldar) Boy or Woman Coolie Bhishti(Including Curing) Sundries, T, and P., etc. Quantity or Nos.

9.50 Cu.M 4.75 Cu. M. 0.95 Cu.M.

0.5 no. 1.5 no. 12 nos. 18 nos. 4 nos. Lump Sum

Add 1.5% Water Charges Add 10% Contractor's Profit Rate per Cu.M =Rs 110009.95/10=Rs 1101.00

6. Cement Concrete 1:2:4 - unit 1 Cu.M. Take - 10 Cu.M. Materials Stone Ballast 40mm gauge Sand (Coarse) Cement (66 Bags) Labour Mistri (Head Mason) Mason Mazdoor ( Beldar) Boy or Woman Coolie Bhishti ( Including Curing ) Forms etc.(according to requirement) Sundries, T. and P., etc.

8.80 Cu.M. 4.40 Cu.M. 2.20 Cu.M.

0.33 no. 2 nos. 12 nos. 20 nos. 6 nos. Lump Sum Lump Sum Total of Material and Labour = Add 1.5% Water Charges = Add 10% Contractor's Profit = Rate per Cu.M. = Rs 20509.70/10 = 2059.00

Page 487 Item no.7 RCC work in Beams,Slabs, etc. 1:2:4 - unit 1 Cu.M. Take - 10 Cu.M. Materials Stone Ballast 20mm gauge 8.80 Cu.M. Sand (Coarse) 4.40 Cu.M. Cement (66 Bags) 2.20 Cu.M. Steel,Mild Steel bars @ 1% = .1Cu.M.@78.5q/Cu.M. 7.85 q Binding Wire 1.50 Kg Labour Mistri (Head Mason) Mason Mazdoor ( Beldar) Boy or Woman Coolie Bhishti ( Including Curing ) Sundries, T. and P., etc. Bending, cranking and binding Steel bars in position Blacksmith(II Class) Mazdoor ( Beldar) T. and P.

0.5 no. 3 nos. 12 nos. 20 nos. 6 nos. Lump Sum

8 nos. 8 nos. Lump Sum

Centering and Shuttering (both erection and dismantling) Timber Planks and ballies Carpenter (II Class) Mazdoor (Beldar) Nails T. and P.

Lump Sum 10 nos. 10 nos. Lump Sum Lump Sum Total of Material and Labour = Add 1.5% Water Charges = Add 10% Contractor's Profit = Rate per Cu.M. = 38427.95/10 =3843.00

40mm(1.5") Thick gauge - unit 1 Cu.M. Take - 10 Cu.M. Rate Rs Cost Rs

P 2850 712.5 4189.5 7752 75 187.5 720 900 200 40 2122.5 9874.5 148 987.45 11009.95

300.00 per Cu.M. 150.00 Per Cu.M. 4410.00 Per Cu.M. Total 150.00 per day 125.00 per day 60.00 per day 50.00 per day 50.00 per day 40.00 L.S. Total Total of Material and Labour

Grand Total r Cu.M =Rs 110009.95/10=Rs 1101.00

for Cu.M.

400.00 per Cu.M. 550.00 per Cu.M. 4410.00 Cu.M. Total

3520 2420 9702 15642 50 250 720 1000 300 450 55 2825 18467 277 1846.7 20509.7 for 10 Cu.M.

150.00 per Day 125.00 per Day 60.00 Per Day 50.00 Per Day 50.00 Per Day 450.00 L.S. 55.00 L.S. Total Material and Labour =

% Contractor's Profit = Grand Total = r Cu.M. = Rs 20509.70/10 = 2059.00

u.M. Take - 10 Cu.M. 500.00 per Cu.M. 550.00 per Cu.M. 4410.00 Cu.M. 1550 per q 20.00Kg Total 150.00 per Day 125.00 per Day 60.00 Per Day 50.00 Per Day 50.00 Per Day 45.00 L.S. Total 4440 2420 9702 12167.5 30 28759.5 75 375 720 1000 300 45 2215

100.00 per Day 60.00 Per Day 20.00 L.S. Total

800 480 20 1300

500.00 L.S. 100.00 per Day 60.00 per Day 70.00 L.S. 20.00 L.S. Total Material and Labour =

% Contractor's Profit = Grand Total = r Cu.M. = 38427.95/10 =3843.00

500 1000 600 70 20 2190 34464.5 517 3446.45 38427.95 for 10 cu.M.

page 486 item no. 5 Cement concrete 1:5:10 in Foundation or Floor with Brick Ballast 40mm(1.5") Thick gauge - unit 1 Cu.M. Take - 10 Cu.M. Particulars Materials Brick Ballast 1st class 40mm gauge in Cu.M. Sand (Local) in Cu.M. Cement (28.5 Bags) in cu.M. Labour, etc . Mistri(Head Mason) in no. Mason in no. Mazdoor(Beldar) in no. Boy or Woman Coolie in no. Bhishti(Including Curing) in no. Sundries, T, and P., etc. In L.S. Quantity or Nos.

9.5 4.75 0.95

0.5 1.5 12 18 4 1

Add 1.5% Water Charges Add 10% Contractor's Profit Rate per Cu.M =Rs 110010.07/10=Rs 1101.01

6. Cement Concrete 1:2:4 - unit 1 Cu.M. Take - 10 Cu.M. Materials Stone Ballast 40mm gauge in Cu.M. Sand (Coarse) in Cu.M. Cement (66 Bags) in Cu.M. Labour Mistri (Head Mason) in no.(per Day) Mason in no. (per Day) Mazdoor ( Beldar) in no. (per day) Boy or Woman Coolie in no. (per day) Bhishti ( Including Curing ) in no. (per Day) Forms etc.(according to requirement) in Lump Sum Sundries, T. and P., etc. in Lump Sum

8.8 4.4 2.2

0.33 2 12 20 6 1 1 Total of Material and Labour = Add 1.5% Water Charges = Add 10% Contractor's Profit = Rate per Cu.M. = Rs 20509.70/10 = 2059.70

Page 487 Item no.7 RCC work in Beams,Slabs, etc. 1:2:4 - unit 1 Cu.M. Take - 10 Cu.M. Materials Stone Ballast 20mm gauge 8.8 Sand (Coarse) 4.4 Cement (66 Bags) 2.2 Steel,Mild Steel bars @ 1% = .1Cu.M.@78.5q/Cu.M. 7.85 Binding Wire 1.5 Labour Mistri (Head Mason) Mason Mazdoor ( Beldar) Boy or Woman Coolie Bhishti ( Including Curing ) Sundries, T. and P., etc. Bending, cranking and binding Steel bars in position Blacksmith(II Class) Mazdoor ( Beldar) T. and P.

0.5 3 12 20 6 1

8 8 1

Centering and Shuttering (both erection and dismantling) Timber Planks and ballies Carpenter (II Class) Mazdoor (Beldar) Nails T. and P.

1 10 10 1 1 Total of Material and Labour = Add 1.5% Water Charges = Add 10% Contractor's Profit =

40mm(1.5") Thick gauge - unit 1 Cu.M. Take - 10 Cu.M. Rate per unit Rs Cost Rs 300 150 4410 Total 150 125 60 50 50 40 Total Total of Material and Labour

P 2850 712.5 4189.5 7752 75 187.5 720 900 200 40 2122.5 9874.5 148.12 987.45 11010.07 1101.01 per Cu.M.

Grand Total Rate per Cu.M =Rs 110010.07/10=Rs 1101.01

400 550 4410 Total 150 125 60 50 50 450 55

3520 2420 9702 15642 49.5 250 720 1000 300 450 55 2824.5 18466.5 276.9975 282.45 20509.7 for 10 Cu.M. 2050.97 for 1 Cu.M.

Total Total of Material and Labour = Add 1.5% Water Charges = Add 10% Contractor's Profit = Grand Total = Rate per Cu.M. = Rs 20509.70/10 = 2059.70

.M. Take - 10 Cu.M. 500 550 4410 1550 20 Total 150 125 60 50 50 45 Total 4440 2420 9702 12167.5 30 28759.5 75 375 720 1000 300 45 2215

100 60 20 Total

800 480 20 1300

500 100 60 70 20

Total Total of Material and Labour = Add 1.5% Water Charges = Add 10% Contractor's Profit = Grand Total =

500 1000 600 70 20 2190 34464.5 517 3446.45 38427.95

As on 25-06-2012 Quantity or Nos. Rate per unit Rs 9.5 4.75 0.95 Total 0.5 1.5 12 18 4 1 Total Total of Material and Labour 550 500 400 350 300 400 Cost Rs 3158 1412.4 8700

P 30001 6708.9 8265 44974.9 275 750 4800 6300 1200 400 13725 58699.9 880.50 5869.99 65450.39 6545.04 per Cu.M.

Grand Total Rate per Cu.M =Rs 63,540.11/10=Rs 6354.01

8.8 4.4 2.2 Total 0.33 2 12 20 6 1 1 Total Total of Material and Labour = Add 1.5% Water Charges = Add 10% Contractor's Profit = Grand Total = Rate per Cu.M. = Rs 51820.39/10 = 5182.04

988.68 1412.4 8700

8700.384 6214.56 19140 34054.944 181.5 1000 4800 6000 2400 900 100 15381.5 49436.444 741.55 1538.15 51716.14 for 10 Cu.M. 5171.61 for 1 Cu.M.

550 500 400 300 400 900 100

8.8 4.4 2.2 7.85 1.5 Total 0.5 3 12 20 6 1 Total

1129.92 1412.4 8700 4820 48.2

9943.30 6214.56 19140 37837 72.3 73207.16 275 1500 4800 6000 2400 90 15065

550 500 400 300 400 90

8 8 1 Total

550 400 50

4400 3200 50 7650

1 10 10 1 1 Total Total of Material and Labour = Add 1.5% Water Charges = Add 10% Contractor's Profit = Grand Total = Rate per Cu.M.

1000 500 400 150 50

1000 5000 4000 150 50 10200 106122.16 1591.83 10200 117913.99 for 10 Cu.M. 11791.40 for 1 Cu.M.

The construction materials are available in the following rates* and it has been displayed for your guidance.(from website www.anytimeproperty.com) Material Cement Per 50kg bag Steel Non ISI TMT 8MM dia TMT 10-25 MM dia RMS (Ready made steel) STIRRUPS " VSP / SAIL BRICKS 3000 NOS RIVER SAND BLUE METAL (Material not Freely avaliable) 20 MM 40 MM BITUMEN AT I.O.C Grade 80/100 Grade 60/70 MASON LABOUR Men Women PAINTER/PLUMBER CARPENTER Last Week Rs. 290 Rs. 47,800 Rs. 48,700 Rs. 47,100 Rs. 52,500 Rs. 53,500 Rs. 52,000 Rs. 18,000 Rs.40/-per cft

Rs.28 to Rs.30/-cft Rs.28/-cft Rs.41,365/-MT Rs.42,326/-MT Rs.500 to Rs.550 Rs.350 to Rs.400 Rs.250 to Rs.300 Rs.450 to Rs.500 Rs.500 to Rs.550

played for your guidance.(from website

This Week Rs. 290 Rs. 48,360 Rs. 49,000 Rs. 48,200 Rs. 52,500 Rs. 53,500 Rs. 52,000 Rs. 18,000 Rs.40/-per cft

Rs.30 to Rs.32/-cft Rs.28/-cft Rs.41,977/-MT Rs.42,938/-MT Rs.500 to Rs.550 Rs.350 to Rs.400 Rs.250 to Rs.300 Rs.450 to Rs.500 Rs.500 to Rs.550

Price quotes from www.maaproperties.com/pages/products

Material Construction Materials River Sand Manufactured Sand Steel Ready Mix Concrete Premium brand cement (50 Kg. bag) Bricks Mud Bricks Mud Bricks (Light Weight) Fly Ash / Hallow Bricks Accessories Tiles: Ceramic tiles Tiles: Shabad stone Tiles: Markapur Marbles - tiles Marbles - Slabs Granite - tiles Granite - Slabs Bthroom accessories etc. Wood & Panel(per cubic foot) Panel Boards Teak Wood - Burma Teak Wood - African Teak Wood - India Teak Wood- Medium Beeja Sal Neem Mango Babool Electrical Accessories

PRODUCT AND MATERIAL PRICES IN HYDERABAD Price Range Construction Materials Rs. 550 - 650 per tonne & 5,000/lorry load Rs. 450 - 500 per tonne Rs. 35 - 37,000 per tonne Variable Rs. 230 - 240 per bag 18,000/lorry load Rs. 1.50 - 1.75 per piece Rs. 2.50 - 2.75 per tonne Rs. 3.25 + per piece Accessories Rs. 10 - 30 per tile Rs. 5 - 10 per tile Rs. 4 - 8 per tile Rs. 14 onwards per sft. Rs. 20 onwards per sft. Rs. 20 onwards per sft. Rs. 45 onwards per sft. Various ranges Wood & Panel(per cubic foot)

Rs. 3,000/cft Rs. 2,400/cft Rs. 2,800/cft Rs. 1,450/cft Rs. 900/cft Rs. 350 to 500 Rs. 150 to 250 Rs. 350 to 400 Various

Availability / Details

Materials Types: River & Filtered. Loads of 5-6, 13-14, 20-21 tons Stone curshed into sand, various manufacturers Available in various gauzes and loads Variable Manufacturers Various Manufacturers and different grades Price depends on thickness and finish Various qualities depends on manufacturer Standard sizes and finishing depends on manufacturer

ies Various Various Various Price depends on whiteness and design Price depends on whiteness and design Price and quality depends on brand Price depends on finishing Brand and quality determine the price

r cubic foot) Various Manufacturers Supply and demand determine the price Supply and demand determine the price Various timber suppliers Various Various Various Various Competitive pricing because of heavy supply

Vous aimerez peut-être aussi