Académique Documents
Professionnel Documents
Culture Documents
ERLDC
INTRODUCTION
Stage I
Cost of Transmission clubbed with Generation Tariff
Stage II
Apportioned on the basis of energy drawn (Usage Based)
Stage III
Apportioned on the basis of MW entitlements (Access Based)
Stage IV
Hybrid Methodology
(Usage & Distance/Direction sensitivity based)
Implicit
Upto 1991
19922002
20022011
2011 onwards
3
7/18/2012
7/18/2012
POWERGRID
7/18/2012
GENERATION
TRANSMISSION
DISTRIBUTION
UTILITY (U-1)
SERVICE
UTILITY (U-1)
TRANSMISSION
UTILITY (U-2)
SERVICE
UTILITY (U-n)
SERVICE
UTILITY (U-n)
DISCOMS: COMPLEXITY INCREASED FURTHER (D-1 TO D-N): DISCOMS PAY DIRECTLY TO TSPS
D-1 D-n
U-1
U-2
D-1
D-n
U-3
D-1
D-n
U-4
D-1
D-n
U-n
D-1
D-n
MULTIPLE REGIONS
U-1 D-1
D-n
U-1 D-1
D-n
U-2 D-1
TSP 1 Transmission Assets (T1A 1-n) TSP 2 Transmission Assets (T2A 1-n)
U-2 D-1
D-n
U-3 D-1
D-n
U-4 D-1
U-4 D-1
D-n
U-n D-1
U-n D-1
D-n
REGIONAL GRID -1
REGIONAL GRID -2
Inter-Regional Interconnections
TSP 1 Transmission Assets (T1A 1-n) TSP 2 Transmission Assets (T2A 1-n)
U-1 D-1
D-n
TSP 1 Transmission Assets (T1A 1-n) TSP 2 Transmission Assets (T2A 1-n)
U-2 D-1
D-n
U-2 D-1
D-n
U-3 D-1
D-n
U-3 D-1
D-n
U-4 D-1
D-n
U-4 D-1
D-n
U-n D-1
D-n
U-n D-1
D-n
Inter-Regional Interconnections
Region -1
U-3 U-4
U-n
D-1
D-n
U-1
Region -2
U-n
FOCUS
Economic/Regulatory Objective Operational Efficiency Minimisation of Present Operating Cost Dynamic Efficiency Long-term development of system Allocative Efficiency Equity and fairness in assigning costs
18
Minimize Cross Subsidies Transparency of Procedures Continuity Smooth transition from existing practice
19 POWERGRID
7/18/2012
Paradigm
Rolled in Paradigm
Postage stamp Contract Path Method MW-Mile
Distance based Power flow based (several variant such as MM, DFM, ZCF)
Contract Path Methodology ++ Sensitive to distance -- provides wrong economic signal, based on fictitious path, power flow on parallel path is ignored
22 7/18/2012 POWERGRID
DEFINITIONS
DEFINITIONS
Designated ISTS Customers (DICs) Users of any segments/elements of the ISTS and shall include all generators, STUs, SEBs or load serving entities directly connected to the ISTS including Bulk Consumer and any other entity/person Implementing Agency (IA) The agency designated by the Commission to undertake the estimation of allocation of transmission charges and transmission losses at various nodes/zones for the Application Period along with other functions Approved Injection Injection in MW vetted by IA for the DIC for each representative block of months, peak and other than peak scenarios at the ex-bus of the generator or any other injection point of the Designated ISTS Customer into the ISTS, and determined based on the generation data submitted by the DIC incorporating total injection into the grid, considering the long term and medium term contracts;
DEFINITIONS
Approved Additional Medium Term Injection means the additional injection, as per the MTOA approved by CTU after submission of data to NLDC by the DIC over and above the Approved Injection for the DIC for each representative block of months, peak and off-peak scenarios at the ex-bus of the generator or any other injection point of the DIC into the ISTS Approved Short Term Injection The injection, as per the STOA approved by RLDC /RLDC & including PX Similarly we have Approved Withdrawal (simultaenous withdrawal), Approved additional MT withdrawal & Approved ST withdrawal Deemed Inter State Transmission System (Deemed ISTS) Transmission system which has regulatory approval of the Commission as being used for interstate transmission of power and qualified as ISTS Point of Connection (PoC) transmission charges Nodal / zonal charges determined using the POC method
DEFINITIONS
Yearly Transmission Charge (YTC) Annual Transmission Charges for existing lines determined by the Commission in accordance with the Terms and Conditions of Tariff Regulations or adopted in the case of tariff based competitive bidding in accordance with the Transmission License Regulations and for new lines based on benchmarked capital costs Uniform Charge Charged determined by dividing the YTC of the ISTS Licensees by the sum of the Approved Injection and Approved Withdrawal from the grid(postage stamp charge)
OF
POC
Data Collection Regulation 7(1) DICs, Transmission Licensees to submit Basic Network Data Network Data for Load Flow Analysis Regulation 7(1)(b) Electrical Plant or line upto 132 kV Generators connected at 110 kV Inflow from lower levels generation at that node Outflow towards lower levels Load at that node Dedicated Transmission Lines Regulation 7(1)(c) Owned and Operated by ISTS. Included in Basic Network Owned and Operated by Generator.Excluded
INFORMATION PROCEDURES
Data to be submitted by DICs YTC, Basic Network Details of ISTS, Deemed ISTS, Certified ISTS Lines Demand or Injection Forecast for each season On or Before the end of fourth week of November Data to be submitted by CTU, Owners of Deemed ISTS and DICs Entire Network Data for first year of Implementation Dates and data of commissioning of any new transmission asset for subsequent years
INFORMATION PROCEDURES
Injection and Withdrawal forecast for different blocks of months (Peak and Other than Peak):
Regulation 16(4) April to June (May 15) July to September. (August 31) October to November (October 30) December to February.. (January 15) March (March 15)
In case any of the above fall on a Weekend/Public Holiday, the data shall be submitted for working days immediately after the dates indicated.
7/18/2012
34
Network Parameters
Network Parameters
Implementing Agency
Approved Injection
Approved Withdrawal
Basic Network
Based on Forecast provided by DICs Forecast should be based on Long Term and Medium Term Contracts Forecast Generation to be vetted by IA based on Historic Generation / Demand. Changes in Generation /Demand to be Communicated to DICs In case of conflict validation committee to take final decision IA to perform AC Load flow Regulation 7(1)(h) To obtain LGB & for achieving convergence adjustments may be required to be made on vetted generation/demand Converged Load Flow results to be verified by Validation Committee Regulation 7(1)(i)
VALIDATION COMMITTEE
Nominee from Commission to Chair the Committee Regulation 7(1)(g) Validation Committee Comprises two officials each from:
Implementing Agency National Load Despatch Centre Regional Power Committee Central Transmission Utility Central Electricity Authority Central Electricity Regulatory Commission
7/18/2012
37
NETWORK TRUNCATION
Network Truncation by IA
Regulation 7(1)(k) Upto 400 kV except NER, where it shall be reduced to 132 kV Annexure I, Clause 2.3
Power inflow from Lower voltage Level : Generation Node Annexure I, Clause 2.3 Power outflow from Lower voltage Level : Demand Node Annexure I, Clause 2.3 AC Load Flow on Truncated Network
Annexure I, Clause 2.3
PoC Charges to be computed for 5 blocks of month for peak and other the peak conditions
Average YTC to be apportioned to peak and other than peak based on the no. of hours constituting these periods
Regulation 7(1)(p)
50% recovery through Hybrid Methodology and 50% through Uniform Charge Sharing Mechanism(for first two years )
Regulation 7(1)(q)
ZONING
Criteria for Zoning of nodes: Regulations7(1)(t) Costs within the same range Geographically and electrically proximate Nodes with connectivity to Thermal Generators > 1500 MW or Hydro Generators > 500 MW to be taken as separate zone. Demand zones : Sate Control Area Except NER states where entire region is to be taken as one zone.
Zonal Charges : Weighted Average of Nodal Charges Annexure I, Clause 2.2 Revision of Zones in a financial year Significant Changes in Power System Prior approval from commission Regulations7(1)(t)(vi) Generating stations connected to ISTS network < 400KV would be charged at zonal charges where physically located No transmission charges/losses for solar projects (for the entire useful life) commissioned within next 3 years.
SPECIFIC CHARGES
Charges thus determined to the extent of approved injection/withdrawal for each DIC In the event of a Designated ISTS Customer failing to provide its requisition for demand or injection for an Application Period, the last demand or injection forecast supplied by the DIC and as adjusted by the Implementing Agency for Load Flow Analysis shall be deemed to be Approved Withdrawal or Approved Injection In case the metered MWs (ex-bus) of a power station or the aggregate demand of a Designated ISTS Customer exceeds, in any time block, (a) In case of generators: The Approved Injection + Approved Additional Medium Term Injection + Approved Short Term Injection or; (b) In case of demand customers: The Approved Withdrawal + Approved Additional Medium Term Withdrawal + Approved Short Term Demand, Additional charges would be applicable for deviation
SPECIFIC CHARGES
For deviation > 20% in any time block, the DIC shall be required to pay transmission charges for excess generation @ 25% above the zonal POC charges determined for zone where the Designated ISTS Customer is physically located
Such additional charges would not be applicable in case:: Rescheduling of the planned maintenance program which is beyond the control of the generator Certified by RPC Payment on account of additional charges for deviation by the generator shall not be charged to its long term customer and shall be payable by the generator
SPECIFIC CHARGES
Even if in case of injection / withdrawal < Approved injection/withdrawal allocated transmission charges to be fully paid
After declaration of COD of a generator, charges payable by generators for LT supply shall be billed directly to the LT customers based on capacity share in the generating stations However, before COD, charges to be borne by generators There would be no differentiation between POC charges/losses for LT/MT/ST customers
Regulation 18(1)
Procedures to be prepared by IA
Procedure for Data Collection Procedure for Loss Sharing Procedure for Transmission Charge Computation
TREATMENT OF HVDC
MP Method can not recover its cost directly. HVDC line can be modeled as:
Load at sending end Generator at receiving end
7/18/2012
47
Network Reduction
IA to specify :
Peak and other than Peak conditions for each representative blocks for the next application period.
Approved Demand/Withdrawal to be notified on the website of IA Adjustments in forecasted Injection/withdrawal to be intimated to concerned DIC.
Network Reduction
Reduction upto 400 kV (except NER where the
Software
Computation of Charges
Annual Average YTC to be apportioned to peak and Other than peak conditions
Zoning
As per the regulations Fixed for an application period Zonal Charges / Zonal LAF
Weighted average of all nodes in the zone
Information to RPC
Approved Withdrawal/Injection (MW) for peak and other than peak hours for each season Zonal Point of Connection Charge (Rs/MW/month) for Generation and Demand Zones Approved Additional Medium Term Withdrawal / Injection (MW) Details of Short Term Open Access As per format I and II of the Procedure
Season I
Season II
Season III
Season IV
Season V
From
To
Peak
Peak
Accounting
Regional Power Committee
Regulation 10
Regional Transmission Accounts Working Day of Every Month for the previous Month) (1st
Regional Transmission Deviation Accounts (by 15th Day of Every Month for the previous Month)
7/18/2012
63
Billing (1)
Regulation 11
Generators shall be billed only for deviations. Bill to be raised only on DICs
SEB/STU may recover such charges from DISCOMs, Generators and Bulk Consumers.
7/18/2012 64
Billing (2)
Central Transmission Utility First Part (Based on Approved Injection/Withdrawal and PoC Charge) Second Part (Recovery of Charges for Additional Medium Term Open Access) Third Part (Adjustments Based on FERV,Interest, Rescheduling of Commissioning) Fourth Part (Deviations)
7/18/2012
BILL PART-I
To be raised by 1st working day of the month by CTU Independent of Transmission accounts to be issued by RPCs For Generators [ (PoC Transmission Charge of generation zone in Rs / MW / month for peak hours) (Approved Injection for peak hours) ]
+
[ (PoC Transmission Charge of generation zone in Rs / MW / month for off-peak hours) x (Approved Injection for off-peak hours) ] For Demand [ (PoC Transmission Charge of demand zone in Rs / MW / month for peak hours)x(Approved withdrawal for peak hours) ]
+
[ (PoC Transmission Charge of demand zone in Rs / MW / month for off-peak hours) x (Approved withdrawal for off-peak hours) ]
BILL PART-II
To be simultaneously raised alongwith BILL-PART-I For Generators [ (PoC Transmission Charge of generation zone in Rs / MW / month for peak hours) (Approved Additional MediumTerm Injection for peak hours) ] + [ (PoC Transmission Charge of generation zone in Rs / MW / month for off-peak hours) x (Approved Additional MediumTerm Injection for off-peak hours) ]
For Demand [ (PoC Transmission Charge of demand zone in Rs / MW / month for peak hours)x(Approved Additional MediumTerm withdrawal for peak hours) ] + [ (PoC Transmission Charge of demand zone in Rs / MW / month for off-peak hours) x (Approved Additional MediumTerm withdrawal for off-peak hours) ] Revenue from Additional MTOA alongwith interest to be used for truing up the YTC for next F.Y.(i.e would be adjusted in YTC of the licensee for computation of POC for next F.Y.)
Deviation calculations after considering additional MT & Short Term Open Access for each time block Deviation = [Average MW injected/withdrawn]
[ (Approved injection/withdrawal+Approved additional MT injection/withdrawal+ST injection/withdrawal) ] Charge to be Calculated on Block wise Deviation
Deviations by Generator shall not be charged to Long Term Customers No additional Charge for Deviations in case :
Rescheduling of Maintenance Schedule for reasons beyond control of geenrator OR Certified by RPC
Net Injection
Net Drawl
PoC Charge
1.25 times PoC Charge for the excess deviation > 20%
Net Drawl
Net Injection
PoC Charge
1.25 times PoC Charge for the excess deviation > 20%
Thus additional charges due to deviations = 1.25 x POC transmission charge for demand / withdrawal x Deviations In case a generator withdraws from grid:: Additional charges = 1.25 x POC transmission charge for the demand zone x Average MW withdrawn for the corresponding blocks In case a withdrawing DIC becomes a net injector:: Additional charges = 1.25 x POC transmission charge for the generation zone x Average MW injected for the corresponding blocks Bill for deviations to be raised by CTU within 3 days of issue of Transmission deviation accounts by RPC. This part alongwith interest would be used for truing up the YTC for next F.Y.(i.e would be adjusted in YTC of the licensee for computation of POC for next F.Y.)
BILL PART-III
The 3rd Part of the Bill to be raised bi-annully by CTU on the first working day of September & March for the previous six months The bill shall be used to adjust any variations in interest rates, FERV, rescheduling of commissioning of transmission assets, etc. Recovery/Reimbursement would be on basis of under-recovery/over-recovery, in proportion to average approved injection/withdrawal over previous six months CTU to transfer the 3rd part to respective ISTS licensees for whom the adjustment is required
CTU to collect charges on behalf of ISTS service providers. CTU to disburse in proportion to Monthly Transmission Charges.
CTU to prepare revenue sharing agreement which is to be approved by CERC for disbursal of monthly transmission charges to various ISTS licnesees The impact of any delayed payment/non-payment by any DIC would be shared pro-rata in proportion of YTC by all the ISTS transmission licensees including CTU Users to ensure that existing contracts(e.g. BPTAs) are realigned to these regulations within a period of 60 days from the date of notification of the TSA
PART
Commission would notify detailed procedures prepared by IA, NLDC & CTU as a part of transition mechanism
Regulation 17
Approved Basic Network Data and Assumptions, if any Zonal or nodal transmission charges for each block of month Zonal or Nodal Transmission losses data Schedule of Charges payable by each constituent after undertaking necessary true up costs Underlying network information & base load flows
Introduction
Hybrid Method : Based on Load Flow (Offline Studies) Average participation for slack bus identification Marginal Participation for usage identification Recovery of Charges
50% by Uniform Charge Method 50% by PoC Charge Method
Results of offline line studies highly dependent upon the input to the model Inconsistent data may not make solution Converged May lead to modifications in Approved Demand / Injection
Approved Injection / Withdrawal Data to be submitted on or before 4th Week of November for next F.Y. The information may be sought by the IA at times other than those if necessary
Flow Chart
Input Network Parameters Load & Generation Data
Network Reduction
Reduced Network
Software for PoC Charge & Loss Computation Output PoC Charges and LAF
Formats would be available on the website of IA and all RLDCs after getting permission from the Commission
www.nldc.in www.nldcindia.in
Submission of data shall be only in electronic spreadsheet formats (MS Excel). For all communication puposes
emailid of IA : implementingagency@powergridindia.com
Network Parameters
Network Data upto 132 kV except where generators are connected to Grid at 110KV Injection below 132 kV : Generation Withdrawal below 132 kV : Load Also include states generation.
Type of Data
Transmission Licensees DICs
Network Data
Bus Data
Generator Data
AC Line Data
DC Line Data
Transformer Data
Bus Data
Bus Type
Susceptance
Reactive Component of Shunt admittance to ground In Mvar at one per unit Should not include reactive impedance load , line charging and line connected shunts
Sign Convention
+ Voltage in kV
Generator Data
Bus Name Generator Real Power Ouput
Ex Bus Output in MW
RT, XT
Step up Transformer Impedance in per unit on MVA Base
GTAP
Step up Transformer off-nominal turns ratio (in pu)
Load Data
Bus Name Real & Reactive Power Component
Constant MVA Load Constant Current Load Constant Admittance Load
AC Line Data
From Bus Name (I) To Bus Name (J)
Circuit Number
For D/C line one line will have 1 in this data and 2 for other line
Rate A
Operating limit considering the compensations and length of line Minimum of Thermal, Voltage and Stability limits.
Transformer Data
From Bus To Bus
Circuit Number
Resistance and Reactance in per unit Phase shift angle Nominal Tap Ratio
Desired Voltage Upper & Lower Limit Ni : Number of steps for block I Bi : Admittance increment for each Ni steps in block i
Forecast of MW
On the basis of MW entitlements
Forecast required for 5 blocks of month For Generators forecast should be equal to the rated capacity Forecast = max(G1) + max(G1) +.
Commercial Data
Line wise YTC of each ISTS Line Breakup of total YTC among different Voltage Levels.
Introduction
The procedure aims to keep computation:
Simple Non-Recursive
7/18/2012
108
New Methodology
Point of Connection Losses
Independent of Contract Path
Moderation of Losses
Based on Actual Regional Losses of last week and Losses based on studies
7/18/2012 109
7/18/2012
110
Zonal Loss : Weighted Average of losses at each node Moderation of Zonal Losses
One PoC Loss for each entity per day
Weighted average of peak and other than peak
7/18/2012 111
7/18/2012
112
7/18/2012
113
where A is Total MW losses of a region GNG = Total Injection in a region IIR = Inter Regional Exchange
7/18/2012 114
115
B
B
92.15 MW 100 MW
7/18/2012
116
3 5
92.15 MW
A
97 MW
100 MW
7/18/2012
117
92.15 MW
97 MW
A
97 MW
100 MW
7/18/2012
118
THANK YOU!