Académique Documents
Professionnel Documents
Culture Documents
layout. In general sense , the term assembly line refers to progressive assembly linked by some material handling devices .
The classic example is Henry Fords auto chassis line.
Before the moving assembly line was introduced in 1913, each
chassis was assembled by one worker and required 12.5 hours. Once the new technology was installed, this time was reduced to 93 minutes
Key Concept
The most common assembly line is a moving conveyer that passes a series of workstations in a uniform time interval called the cycle time (which is also the time between successive units coming off the end of the line). The work performed at each station is made up of many bits of work , termed task, elements or work units.
Contd.
The total work to be performed at a workstation at a workstation is equal to the sum of the tasks assigned to workstations. The assembly line balancing problem is one of assigning all tasks to a series of workstations so that each workstations has no more than can be done in their cycle time. The unassigned time (idle) across all workstations is minimised .The problem is complicated by the relationships among tasks imposed by product design and process technologies . This is called PRECEDENCE RELATIONSHIP which specifies the order in which the tasks must be performed in the assembly process.
3.
4.
Draw the precedence diagram Determine the required cycle time (c) C=(Production time/day) /Output per day (in units) Determine the theoretical no of work stations Nt = Sum of the task times/cycle time Select a rule which tasks are to be assigned to work stations and a secondary rule to break the ties.
5. 6.
Efficiency = Sum of the tasks times/[ actual no of workstations x Cycle time ] Balance delay =1-Efficiency
Precedence Diagram
Figure 6.10
a c
0.7 min.
b d
0.5 min.
e
0.2 min.
workstations.
Use a cycle time of 1.0 minute Assign tasks in order of the most number of followers
Example 1 Solution
Revised Time Remaining
0.9 0.2
Workstation
1
Time Remaining
1.0 0.9 0.2 1.0 1.0 0.5 0.3
Eligible
a, c c none b d e -
Assign Task
a c b d e -
0.2
0.0 0.5 0.3 0.0 0.3 0.5
2 3
Line Balancing
available work time Cycle time demand
number of theoretical workstations, N T task times / cycle time
12
Precedence Diagram
B E A C
13
Calculations
cycle time = 450/75 = 6 minutes/part NT = 20/6 = 3.33 = 4 stations
Task Assignment
Time Station Avail. 1 6.0 3.8 0.4 2 6.0 1.9 0.2 Elig. Tasks A C,D C,D C E Will Task Idle Fit? Assign. Time A B -D C -0.2 0.4 -C,D C --
B,C,D B,C
Station 4 G
Efficiency
efficiency = 20/(4*6) = 83.3%
2 3 4 5 6 7 8 9 10 11
A B A,C A B A,C G H I J
0.020 0.020 0.040 0.020 0.020 0.040 0.050 0.008 0.040 0.098