WHY QUALIFICATION?
Objective:
The tender evaluation is a very important and critical exercise. The objective of this exercise is to ensure that the tenders are received in proper format, they are scrutinized, evaluated, negotiated and decided by the competent authority in accordance with manual provisions, govt. instructions and delegated financial power prescribed by the department from time to time.
TENDERING PROCESS
Type of Organization Years in Business Equipment strength Technical staff Architectural work Salvancy certificates Work executed
CASE STUDY
Main structures Inaugural and Performance stage VIP lounge and Sitting area Food stalls Temporary toilet blocks Entrance gates. Infrastructures Pathways and ramps Parking area Ambience. Services Miscellaneous work
Sr. No. 1 a
Requirement Strength of Organisation Type of Company (Form C1) Public Ltd. Pvt. Ltd. Partnership Sole Propriety Firm Joint Venture Year of incorporation (Form C1) 1997 or before 1997-2002 After 2002 Event specific organisational structure (Form C2) Organisation Chart at HO level Organisation Chart at field level Methodology and work plan Quality policy, ISO (Form C4) Environment Policy, ISO (Form C5) Safety Policy (Form C6) Awards, Certificate of Merit
d e f g
Rating 30 8 8 6 4 2 8 5 5 3 2 9 3 3 3 2 2 2 2
2 a
Financial Status Annual turn Over 175 to 200 lacs 200 to 250 lacs
10 10
3 a
Personnel & Asset Available Man Power (Form C2) Event Manager Architect Designer Civil Engineer Electrical Engineer Works Manager+10 years Proposed Deployment of Manpower (Form P2) Event Manager Principal Architect+10 years Principal Designer+10 years Works Manager+10 years Civil Engineer Available TEP (Form C3) Portals Cranes Generators Other Proposed TEP (Form P3) Portals/Frames Cranes Generators Other
30 6 1 1 1 1 1 1 10 2 2 2 2 2 6 2 1 2 1 8 2 1 2 3
(4) a
Experience Overall Experience Cost of works executed from 20 to 40% of Estimated Cost, 5 marks/work from 40 to 60% of Estimated Cost, 10 marks/work from 60 to 80% of Estimated Cost, 15 marks/work from 80% to 100 % of Estimated Cost More than 100 % of Estimated Cost Similar Experience 120 to 145 Lacs Above 145 Lacs Electrical works Experience 10-20 Lacs 20-40 Lacs 40 Lacs & above Total
120 40
10 20 30 35 40 50 25 50 30 10 20 30 300
MARKS ALLOTED
1/5 Sr. No. Requirement Weighta ge A 2/5 B 3/5 C 4/5 D 5/5 E
(1) Strength of Organisation a b c d e f g Type of company Year of incorporation Event specific organisational structure Documented Quality policy, ISO Documented Environment Policy, ISO Documented Safety Policy Awards, Certificate of Merit
30 8 5 9 2 2 2 2
19 6 5 6 0 0 2 0
24 4 5 9 2 1 1 2
16 2 5 9 0 0 0 0
27 8 5 6 2 2 2 2
12 6 3 3 0 0 0 0
2/5
3/5
4/5
5/5
120 100 20
110 100 10
110 90 20
120 100 20
120 100 20
110 100 10
Sr. No.`
Requirement
Weight age
1/5 A
2/5 B
3/5 C
4/5 D
5/5 E
(3) Personnel and Assets a b c d Available Man Power Proposed Deployment Manpower Available TEP Proposed TEP of
30 6 10 6 8
26 5 10 3 8
24 6 10 3 5
15 3 6 3 3
18 5 10 3 0
15 6 9 0 0
1/5
Sr. No. Requirement Weigh tage
2/5
3/5
4/5
5/5
120 40 50 30
100 40 50 10
110 40 50 20
120 40 50 30
120 40 50 30
130 40 50 40
2/5
B
3/5
C
4/5
D
5/5
E
300
255 YES
268 YES
271 YES
285 YES
267 YES
Conclusion :
All the contractors are eligible for presentation as total marks obtained by them is more than 70% of the total.
THANK YOU