Vous êtes sur la page 1sur 19

Construction Disputes and their Settlement

BUILDING TECHNOLOGY AND MANAGEMENT

Development of Disputes
Natural phenomenon!

Interpretation of contract clauses


Difference in opinion regarding the execution of the work Unforeseen problems

Types of Construction Disputes


Claim: Demand for something considered ones due
Claims of Contractor against Owner/Client Claims of Owner/Client against Contractor Sub-contractors claims

Claims of Contractor against Owner/Client


Claims to recover damages caused by breach of

conditions by the owner


Claims to recover loss or damage caused by an unjust termination of the contract by the owner Claims to recover damages upon rescinding of the contract due to frustration

Claim Generating Circumstances


1. Delay in the supply of drawings and clarifications 2. Defects in the specifications furnished 3. Delay/manufacturing defects in materials/equipment supplied by the owner 4. Changes in law, regulations or codes subsequent to the award of the contract 5. Changed or differing site conditions 6. Delay due to other contractors work 7. Acceleration in work demanded by the owner 8. Defects in the contract agreement 9. Inordinate delay in the release of payments 10.Unjustified termination of the contractor by the 5 owner

11. Substantial delay in handing over the site 12. Owners failure in his implied duties 13. Unreasonable rejection of acceptable work 14. Delay in clearances 15. Suspension of work by the owner for his own convenience 16. Rescheduling/prolonging work for financial and other reasons 17. Work arising during maintenance period, which is not covered by the contractors obligations 18. Owners delay in decision over amendments/change orders 19. Quantity variations, for which provision is not made in the contract
6

20. Failure by sub-contractors nominated by the


owner 21. Stipulations of near-impossibilities for compliance or incorporation into the contract work 22. Natural calamities

23. Force Majeure

Claims of Owner/Client against Contractor


Claims for defective work done by the contractor

Claims for delay caused by the contractor


Counter-claim as a defense Claim against professionals Claims following termination and breach Claims for expenditure incurred in completing the

work left incomplete or abandoned by the


contractor Claims for liquidated damages
8

Owners Claim Procedure


Engineers Comments Consultants Comments Claims Committees Recommendation Top Managements Approval Claim Initiation by the Client/Owner Excusable Delays

Modes of Settlement of Disputes


By direct negotiations between the client and the

contractor
Settlement by arbitration Through civil courts

10

Direct Negotiations
Easiest and least expensive

Majority of the disputes are settled through


negotiations Arbitration is sought after, only if direct negotiations fail

11

Settlement Through Courts


Last resort

Attempted only if direct negotiation and


arbitration fails Time consuming, to the tune of several years Expensive

12

Settlement Through Arbitration


a dispute by an impartial referee selected by the parties concerned. Arbitrator is a person chosen by the concerned parties to pronounce judgment on the dispute.

Arbitration is the hearing and determination of

Sole Arbitrator Joint Arbitrators

13

Advantages of Arbitration over Litigation


1. Cost 2. Speed 3. Convenience 4. Technical knowledge

5. Informality
6. Proceedings in private premises

7. Finality of award

14

Indian Arbitration Act 1940


Provides for arbitration in the following three cases:

Arbitration without intervention of a court


Arbitration with intervention of a court Arbitration in lawsuits

15

The Act:
does not dictate the form of arbitration to be adopted

does not prescribe the procedure for arbitration


does not interfere with the award given by the

arbitrator
does not require the arbitrator to state reasons in support of his ruling

16

Arbitration Clause
1. All disputes will be settled through arbitration in accordance with the Indian Arbitration Act, 1940 2. The parties may appoint a single arbitrator or each party may nominate an arbitrator and the

two nominated arbitrators may mutually select an


umpire 3. The parties will mutually agree regarding the sharing of arbitration fees and expenses
17

The arbitration proceedings will be conducted by


the arbitrator(s) in accordance with laid down procedures, at mutually convenient places and dates

If difference in opinion arises between the two

arbitrators, the decision of the umpire will be


final 6 The arbitration award will be final and binding

upon both parties

18

Reference
o Joy, PK, Handbook of Construction Management, MacMillan India o Patil, BS, Civil Engineering Contracts and

Estimates, Universities Press


o Gahlot, PS and BM Dhir, Construction Planning and

Management, New Age International


o Gupta, BL and A Gupta, Construction Management

and Machinery, Standard Publishers


19

Vous aimerez peut-être aussi