Académique Documents
Professionnel Documents
Culture Documents
Objectives:
Describe the methods to produce project duration that minimize project cost Explain the direct and indirect project cost including a description of the basic types of schedules relative to the relationships of project duration and total project costs. Discuss reasons for the need to reduce project duration Examine the time reduction method of expediting or buying time along the critical path Explain time-cost relationships for project activity duration as well as cost slope computations and comparisons
Result of normal or average, time estimates for activity durations Normal time estimates and associated resource allocation result in an efficient schedule but not necessarily the leastcost or least-time Schedule a compromise between cost and time to accomplish the project task.
Least-cost to minimize the total project cost, both direct and indirect costs must be minimized
Increasing the direct cost to shorten one or more activities (i.e. less than the normal duration) may reduce the project duration, and thus the indirect cost sufficiently to reduce the total project cost and provide a least-cost schedule
Indirect costs tend to decrease as project duration decreases, but this may be at the expense of increased direct costs of a faster but less efficient set of resources and sequence of operations
Least Cost Scheduling What is a least cost schedule? - One with an optimum project duration such that to lengthen or shorten it would increase the total cost
Schedule compression The systematic process of arriving at the least cost solution
Schedule compression
for simple compression, when both the direct and overhead costs vary linearly with time, the planner must do the following: 1. Assign each activity a direct cost to complete the activity at the normal duration, which is called the normal cost. 2. Assign, a minimum duration (less than or equal to the normal duration) for every activity, which is called crash duration 3. Assign to each activity a direct cost (greater than the normal cost) to complete the activity at the minimum duration.
Schedule compression
in order to investigate a method of least cost scheduling, the following are the assumptions: 1. The planned duration can be any whole day value between and including the normal and crash durations 2. The direct cost of an activity is linear between the normal and crash direct cost 3. The overhead cost is linear during the entire project. It is simply the number of days times the overhead cost per day.
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Schedule compression
Activity 4
Completely crash the following network schedules using simple compression, and find the optimum time and least cost