Project Management Process

Source: PMBOK

Initiation

Planning

Execution

Controls

Closeout

Project Implementation

Break Timer

Implementation Model
Step 1 Perform Tasks

Step 4 Update the Plan

Resolve Issues

Step 2 Track Progress

Step 3 Manage Change


Break Timer

R o a d m a p t o P r o je c t M a n a g e m e n t S u c c e s s
S ta te m e n t o f W o rk F o rm P r o je c t Tea m
P u rp o s e P r o je c t B a c k g ro u n d P r o j e c t D e l iv e r a b l e s S

W o rk B re a k d o w n S tr u c tu re

R e s p o n s ib ility M a trix
R A S R A

N e tw o rk

G a n tt

P e rfo rm Tasks
ME
ET

R e s o u rc e P la n

B udget

T IM E

PLAN
O
PRO JE CT
N
O K EBO T
P e rfo rm Tasks

IN

GS

C onduct C lo s e - O u t M e e tin g

L E A D E R S H IP

S h a re Lessons L e a rn e d

E v a lu a t e Success

IM

SO LES EOS CL

UT

LE

AR NED

LE P

RE

EN

PO

RT S

C O M M U N I C A T IO N

Tra c k P ro g re s s

U p d a te P la n

R e s o lv e Is s u e s

M anage C hange

Break Timer

Collect Project Data


Team Member Status Reports

Team Member Status Review Meetings

Project Manager

Automated Information Systems

Supplier Status Reports/ Meetings

Break Timer

Reporting Activity Progress


Estimate

to complete (ETC)

Break Timer

Percent Completion Reporting


Period 1 2 3 4 5 6 7 8

Planned

20

40

60

90

100

Actual

20

40

60

90

94

96

97

97.5

Everything looks fine until you reach 90%!


Break Timer

Reporting Project Progress


Progress

review meeting Project reports

Break Timer

Project Progress Data


Audience Level of Detail Presented Senior management Project sponsor Customer Program manager Summary data: Summary activities Decision matrix Major risks Serious Issues

Project manager Team members Cross-functional groups

Detail data: All activities Detail Gantt charts All milestones All risks and issues

Break Timer

Project Progress Review Meetings


Review of action items from last meeting Update on activities and schedule Problem identification and corrective action planned Review of issues (closed, open, new) Change request status Risk status Plan for next period

Break Timer

P P A

r o j e c t T i t l e P r o je c t T i t l e

P P R R OO J J E E C C T T P P R R OO GG R R E E S S S S D a t e S u b m it t e d
D R R e e a p p t e o o r t r t S P P u b e m i t t e d r i o d e r i o d

R R E E P P OO R R T T

r o j e c t M a n a g e r : P r o je c t M a n a g e r : u A u S u

t h o r i z a t i o n R e f e r e n c e ( P u r c h a s e C O o n d t re a r c, t . . C. ) h a r g e r : N u m b e r u t h o r i z a t i o n R e f e r e n c e ( P u r c h a s e C O o n d t re a r c, t . . C. ) h a r g e r : N u m b e r m m m m a a r y o f P r o g r e s s D u r in g P e r i o d r y o f P r o g r e s s D u r in g P e r i o d

O O

p p

e e

n n

I s s u e s : I s s u e s :

R R

e e

s p o n s ib il i t y : s p o n s ib i l i t y :

C C

o o

m m

p p

l e le

t i o n D a t e : t i o n D a t e :

R R

e e

p p

o o

r t s / C o r r e s p o n d e n c e I s s u e d D u r in g P e r i o d : r t s / C o r r e s p o n d e n c e I s s u e d D u r i n g P e r i o d :

M M

e e

e e

t i n g s A t t e n d e d D u r i n g P e r io d : t i n g s A t t e n d e d D u r i n g P e r i o d :

W W

o o

r k P la n n e d f o r N e x t P e r i o d : r k P la n n e d f o r N e x t P e r i o d :

B B P P

u u

d d

g g

e e

t t

A p p r o v e d B u d g E e xt p e n d e d D u r i n g x P p e e r ni o d d e d E t oR D ma t a e i n i n g e a t E n d o f P e r io d A p p r o v e d B u d g E e xt p e n d e d D u r i n g x P p e e r ni o d d e d E t oR D ma t a e i n i n g e a t E n d o f P e r i o d t a t u s S t a t u s P P r o j e c t D i r e c t o r r o j e c t D i r e c t o r

Break Timer

r o j e c t M a n a g e r r o je c t M a n a g e r

R o a d m a p t o P r o je c t M a n a g e m e n t S u c c e s s
S ta te m e n t o f W o rk F o rm P r o je c t Tea m
P u rp o s e P r o je c t B a c k g ro u n d P r o j e c t D e l iv e r a b l e s S

W o rk B re a k d o w n S tr u c tu re

R e s p o n s ib ility M a trix
R A S R A

N e tw o rk

G a n tt

R e s o u rc e P la n

B udget

T IM E

PLAN
O K EBO OT

ME
ET
IN

T ra c k P ro g re s s

PRO JE CT

P e rfo rm Tasks

GS

C onduct C lo s e - O u t M e e tin g

L E A D E R S H IP

S h a re Lessons L e a rn e d

E v a lu a t e Success

IM

SO LES EOS CL

UT

LE

AR NED

LE P

RE

EN

PO

RT S

C O M M U N I C A T IO N

Tra c k P ro g re s s

U p d a te P la n

R e s o lv e Is s u e s

M anage C hange

Break Timer

Project Tracking and Control


Step 1 Perform Tasks

Step 4 Update the Plan

Resolve Issues

Step 2 Track Progress

Step 3 Manage Change


Break Timer

Compare Progress to Plan


Quality

reviews Gantt schedule performance charts Cost performance charts Earned value techniques

Break Timer

Quality Reviews
Product

design Specifications Manuals Parts Computer program code

Break Timer

Schedule Performance Charts


Gantt

charts Cost Performance

Break Timer

Gantt Chart

Break Timer

Cost Performance
Week 1 2 3 4 5 6 7 8 9 10
Break Timer

Planned Value $3,000 $6,000 $18,000 $30,000 $44,000 $54,000 $64,000 $80,000 $83,000 $89,000

Actual Costs $8,000 $16,000 $30,000 $48,000 $66,000

Cost Performance Chart


$100 $90

Total Costs (X1000)

$80 $70 $60 $50 $40 $30 $20 $10 $0


PV AC 1 3 8 2 6 16 3 18 30 4 30 48 5 44 66 6 54 7 64 8 80 9 83 10 89

Weeks

Break Timer

R o a d m a p t o P r o je c t M a n a g e m e n t S u c c e s s
S ta te m e n t o f W o rk F o rm P r o je c t Tea m
P u rp o s e P r o je c t B a c k g ro u n d P r o j e c t D e l iv e r a b l e s S

W o rk B re a k d o w n S tr u c tu re

R e s p o n s ib ility M a trix
R A S R A

N e tw o rk

G a n tt

R e s o u rc e P la n

B udget

T IM E

PLAN
O
PRO JE CT
N
O K EBO T

ME
ET
IN
P e rfo rm Tasks

GS

C onduct C lo s e - O u t M e e tin g

L E A D E R S H IP

S h a re Lessons L e a rn e d

E v a lu a t e Success

UT

IM

LE

AR NED

LE P

RE

EN

PO

RT S

C O M M U N I C A T IO N

M anage C hange

SO LES EOS CL

Tra c k P ro g re s s

U p d a te P la n

R e s o lv e Is s u e s

M anage C hange

Break Timer

Managing Project Change


Step 1 Perform Tasks

Step 4 Update the Plan

Resolve Issues

Step 2 Track Progress

Step 3 Manage Change


Break Timer

Categories of Change
Customer
Typically

requested
the largest source of change

All

others
Changes

Internal

company requests Government regulation Team members

Break Timer

Customer submits a formal change request

Change Request Form

Analyze the request for changes to:

Project Plan

Project team analyzes the request.

SCOPE COST SCHEDULE QUALITY

Change Request Process


Change Request Form

Approved?

No

Notify customer of review results

Yes Update the project plan to reflect change in scope, cost, schedule and requirements.

Project Plan

Incorporate change as requested.

Change Request Form

Formal plan for controllin g change.

Project Plan
Break Timer

Update the plan and close the change request

Addressing Project Changes


Call a team meeting. Explain what the change is. Obtain feedback from team members. Identify alternative corrective options. Prepare a decision matrix. Select a recommended option(s). Present information to upper management/customer. Implement the approved course of action.

Break Timer

R o a d m a p t o P r o je c t M a n a g e m e n t S u c c e s s
S ta te m e n t o f W o rk F o rm P r o je c t Tea m
P u rp o s e P r o je c t B a c k g ro u n d P r o j e c t D e l iv e r a b l e s S

W o rk B re a k d o w n S tr u c tu re

R e s p o n s ib ility M a trix
R A S R A

N e tw o rk

G a n tt

R e s o u rc e P la n

Budge 4-5-1t

T IM E

PLAN
O
PRO JE CT
N
O K EBO T

ME
ET

C onduct C lo s e - O u t M e e tin g

L E A D E R S H IP C O M M U N I C A T IO N

R e s o lv e Is s u e s
GS

P e rfo rm Tasks

IN

S h a re Lessons L e a rn e d

E v a lu a t e Success

IM

SO LES EOS CL

UT

LE

AR NED

LE P

RE

EN

PO

RT S

Tra c k P ro g re s s

U p d a te P la n

R e s o lv e Is s u e s

M anage C hange

Break Timer

Issue Resolution
Disagreements
Documented Assigned Scheduled Tracked Escalated Resolved

that should be

Break Timer

R o a d m a p t o P r o je c t M a n a g e m e n t S u c c e s s
S ta te m e n t o f W o rk F o rm P r o je c t Tea m
P u rp o s e P r o je c t B a c k g ro u n d P r o j e c t D e l iv e r a b l e s S

W o rk B re a k d o w n S tr u c tu re

R e s p o n s ib ility M a trix
R A S R A

N e tw o rk

G a n tt

R e s o u rc e P la n

Budge 4-6-1t

T IM E

PLAN
O
PRO JE CT
N
O K EBO T

ME
ET
IN

C onduct C lo s e - O u t M e e tin g

L E A D E R S H IP

U p d a te P la n

P e rfo rm Tasks

GS

S h a re Lessons L e a rn e d

E v a lu a t e Success

IM

SO LES EOS CL

UT

LE

AR NED

LE P

RE

EN

PO

RT S

C O M M U N I C A T IO N

Tra c k P ro g re s s

U p d a te P la n

M anage C hange

Break Timer

Plan Updates
Step 1 Perform Tasks

Step 4 Update the Plan

Resolve Issues

Step 2 Track Progress

Step 3 Manage Change


Break Timer