Académique Documents
Professionnel Documents
Culture Documents
Tony Farrow
Trett Consulting
www.trett.com
AGENDA
Background (Contracts, Delays,
entitlement
Hence Delay Analysis Methodology has developed
Estimate or Model Methods (investigate the EVENT and its potential impact)
Actual Methods (identify the DELAY period and investigate what caused it)
As-Planned vs As-Built
Windows / Snap-Shot
Estimate of Delay
Why Delay?
Activity
Dur
10 11
A B C D
PLANNED PROGRAMME
Original Overall Duration 7 Weeks Critical Path runs through activities A and B
Activity
Dur
10 11
A B C D
AS-BUILT PROGRAMME
As-Built Overall Duration 10 Weeks Critical Path ran through activities C, D and B
Activity
Dur
10 11
A B C D
8 wks 1 wk
VO
d2
d4
Late Info
5 wks 4 wks
d1
Lack of Resources
d3
DELAYING EVENTS
Events d1, d2 and d4 Owner Delays Event d3 Contractor Delay
Activity
Dur
10 11
A B C D
AS-PLANNED IMPACTED
Uses planned programme
Activity
Dur
10 11
A B C D
AS-PLANNED IMPACTED
Add in first delay to occur (d1)
Activity
Dur
10 11
A B C D
AS-PLANNED IMPACTED
Add in first delay to occur (d1)
Activity
Dur
10 11
A B C D
6 wks 1 wk
VO
2 wks 2 wks
d1
AS-PLANNED IMPACTED
Add in first delay to occur (d1) - 1 Week Critical Delay
Activity
Dur
10 11
A B C D
6 wks 1 wk
VO
d2
2 wks 2 wks
d1
AS-PLANNED IMPACTED
Add in first delay to occur (d1) Add in 2nd delay to occur (d2) - 1 Week Critical Delay - No Critical Delay
Activity
Dur
10 11
A B C D
6 wks 1 wk
VO
d2
2 wks 2 wks
d1
AS-PLANNED IMPACTED
Add in first delay to occur (d1) Add in 2nd delay to occur (d2) Add in 3rd delay to occur (d3) - 1 Week Critical Delay - No Critical Delay
Activity
Dur
10 11
A B C D
6 wks 1 wk
VO
d2
2 wks 2 wks
d1
Lack of Resources
d3
AS-PLANNED IMPACTED
Add in first delay to occur (d1) Add in 2nd delay to occur (d2) Add in 3rd delay to occur (d3) - 1 Week Critical Delay - No Critical Delay - 2 Weeks Critical Delay
Activity
Dur
10 11
A B C D
6 wks 1 wk
VO
d2
d4
Late Info
2 wks 2 wks
d1
Lack of Resources
d3
AS-PLANNED IMPACTED
Add in first delay to occur (d1) Add in 2nd delay to occur (d2) Add in 3rd delay to occur (d3) Add in 4th delay to occur (d4) - 1 Week Critical Delay - No Critical Delay - 2 Weeks Critical Delay - No Critical Delay
Activity
Dur
10 11
A B C D
8 wks 1 wk
VO
d2
d4
Late Info
5 wks 4 wks
d1
Lack of Resources
d3
COLLAPSED AS-BUILT
Uses as-built programme logic linked
Activity
Dur
10 11
A B C D
8 wks 1 wk
VO
d2
d4
Late Info
5 wks 4 wks
d1
Lack of Resources
d3
COLLAPSED AS-BUILT
Critical Path Identified and first employer delay removed
Activity
Dur
10 11
A B C D
8 wks 1 wk 2 wks
d2
d4
Late Info
LackLackResources of of Resources LackLackResources of Resources LackLackResources Resources LackResources of Resources of of of of of of Resources of of of of of of Resources LackResources LackResources LackResources LackResources LackResources LackResources Lack Lack Lack
4 wks
dddddddddddddddd3 333333333333333
COLLAPSED AS-BUILT
Critical Path Identified and first employer delay removed
Activity
Dur
10 11
A B C D
8 wks 1 wk 2 wks
d2
d4
Late Info
Lack of Resources
4 wks
d3
COLLAPSED AS-BUILT
Critical Path Identified and first employer delay removed 1 Weeks Critical Delay Allocated to d1
Activity
Dur
10 11
A B C D
8 wks 1 wk 2 wks
d2
d4
Late Info
Lack of Resources
4 wks
d3
COLLAPSED AS-BUILT
Critical Path Identified and next employer delay removed 1 Weeks Critical Delay Allocated to d1
Activity
Dur
10 11
A B C D
7 wks 1 wk 2 wks
d2
Lack of Resources
4 wks
d3
COLLAPSED AS-BUILT
Critical Path Identified and next employer delay removed 1 Weeks Critical Delay Allocated to d1 1 Weeks Critical Delay Allocated to d4
Activity
Dur
10 11
A B C D
7 wks 1 wk 2 wks
d2
Lack of Resources
4 wks
d3
COLLAPSED AS-BUILT
Critical Path Identified and next employer delay removed 1 Weeks Critical Delay Allocated to d1 1 Weeks Critical Delay Allocated to d4
Activity
Dur
10 11
A B C D
6 wks 1 wk 2 wks
Lack of Resources
4 wks
d3
COLLAPSED AS-BUILT
Critical Path Identified and next employer delay removed 1 Weeks Critical Delay Allocated to d1 1 Weeks Critical Delay Allocated to d4 1 Weeks Critical Delay Allocated to d2
As-Planned Impact
1 week critical delay
Collapsed As-Built
1 week critical delay
d2 (bad weather)
no critical delay
1 week delay
d3 (lack resources)
no critical delay
d4 (late info)
no critical delay
Activity
Dur
10 11
A B C D
AS-PLANNED vs AS-BUILT
As-Built Overall Duration 10 Weeks Critical Path ran through activities C, D and B
Activity
Dur
10 11
A B C D
Activity
Dur
10 11
A B C D
Activity
Dur
10 11
A B C D
Activity
Dur
10 11
A B C D
Ground Works
Floor 3
Delays occurring within the first snap-shot period are added and the programme is re-analysed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Planned Finish Date
Ground Works
Floor 3
Ground Works
Floor 3
The planned programme is updated to reflect the actual progress within the snapshot period and then re-analysed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Planned Finish Date
Ground Works
Floor 3
Ground Works
Floor 3
Delays occurring within the 2nd snap-shot period are added and the programme is re-analysed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
End Date as at end of 1st snapshot period
Ground Works
Floor 3
Ground Works
Floor 3
The planned programme is updated to reflect the actual progress within the snapshot period and then re-analysed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
End Date as at end of 1st snapshot period
Ground Works
Floor 3
Programme Float
10 days
TERMINAL FLOAT
10 days
15 days
TOTAL FLOAT
10 days
TERMINAL FLOAT
10 days
10 days
TERMINAL FLOAT
EMPLOYER DELAY
10 days
10 days
TERMINAL FLOAT
EMPLOYER DELAY
10 days 15 days
CONTRACTOR DELAY
10 days
TERMINAL FLOAT
EMPLOYER DELAY
10 days 15 days
CONCURRENCY
Bad Weather
4 weeks
Bad Weather
4 weeks
Structure
M&E
Finishings
Delay B 3 weeks
4 weeks
Completion
4 weeks
Completion
4 weeks
Completion
1 Week EOT
4 weeks
Completion
4 weeks
Completion
2 Weeks EoT
Actual
4 weeks
Completion
4 weeks
Completion
APPENDICES
A. Definitions B. Model Specification Clause (Programmes) C. Model Specification Clause (Records) D. Illustrations
CORE PRINCIPLES
Good Programme Systems and Management Good Record Systems and Management
GUIDANCE NOTES - S1
Definitions (Appendix A) Extension of Time principles
Float
Concurrency Mitigation (best endeavours)
Variations
Global Claims Overheads
Profit
Acceleration (does not address Constructive Acceleration)
GUIDANCE NOTES S2
Form of Programme (Appendix B)
Method Statement Timetables for issue (Initial and Agreed) Updates and Revisions Software
GUIDANCE NOTES S3
Extensions of Time during the Project (Prospective) Time Impact Analysis Updated Programmes Revised Programmes
GUIDANCE NOTES S4
Extensions of Time after the Project (Retrospective)
Four Methods
Updated/Revised Programmes Balance taken re time/costs Consider the terms of the Contract Factual analysis or Entitlement driven? Placing oneself back at the time of the delay
THE PROTOCOL -AIMS Not intended as a contract document Offers specification terms for programme management and record keeping Offers guidance in the management of delay and disruption that is, in the management of change Extensions of Time should be dealt with at the time Time Impact Analysis is the recommended method
THE PROTOCOL -ACHIEVEMENTS Hoped that Contracting Parties would adopt its recommendations Prospective X Hoped/Attempted to have industry contracting bodies adopt it Prospective X Attempted to have the Courts adopt it Retrospective X Delay Analysts adopt it
THE PROTOCOL -CHALLENGES Needs to deal more practically with constructive acceleration Should advance a debate on the fairness of condition precedent clauses Does it amend the basis upon which damage is normally assessed?
1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
10
11
12
13
14
Planned Completion
1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
10
11
12
13
14
Planned Completion
1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
10
11
12
13
14
Planned Completion
Delay 2 Notified Late Switchgear Delivery Delay 3 Inherent Design Fault Discovered
Approved Programme
As-Built
Projected
1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
10
11
12
13
14
Planned Completion
Delay 2 Notified Late Switchgear Delivery Delay 3 Inherent Design Fault Discovered
Approved Programme
As-Built
Projected
1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
10
11
12
13
14
Planned Completion
Delay 2 Notified Late Switchgear Delivery Delay 3 Inherent Design Fault Discovered
1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
10
11
12
13
14
Planned Completion
Delay 2 Notified Late Switchgear Delivery Delay 3 Inherent Design Fault Discovered
1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
10
11
12
13
14
Planned Completion
Actual Completion
Delay 2 Notified Late Switchgear Delivery Delay 3 Inherent Design Fault Discovered
1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
10
11
12
13
14
Slow Progress
Planned Completion
Actual Completion
Crane Delay
REVIEW
10
11
12
13
14
Slow Progress
10
11
12
13
14
Slow Progress
10
11
12
13
14
Slow Progress
Slow Progress
Slow Progress
10
11
12
13
14
Slow Progress
10
11
12
13
14
Slow Progress
10
11
12
13
14
Planned Completion
Approved Programme
Planned Completion
Planned Completion
Answer 1 Month 11 - Subcontractor A Month 12 - Main Contractor Month 13 - Subcontractor B Answer 2 Month 11 - Subcontractor A Month 12 - Subcontractor B Month 13 - Subcontractor B Answer 3 Month 11 - Subcontractor B Month 12 - Subcontractor B Month 13 - Subcontractor B Answer 4 Month 11 - Employer's Liability Month 12 - Subcontractor B Month 13 - Subcontractor B