Vous êtes sur la page 1sur 96

CHALLENGES OF THE SCL DELAY AND DISRUPTION PROTOCOL

Tony Farrow
Trett Consulting
www.trett.com

AGENDA
Background (Contracts, Delays,

Analysis, Claims, Disputes, Resolution)


The Protocol (Structure) The Protocol (Aims and Achievements) Challenges in Implementing the Protocol

Contracts and Project Delays


Contracts have completion dates and liquidated

damages are tied to completion date


Extension of Time clauses maintain LD provisions where there has been breach by Employer

If Employer causes a delay and there is no EOT


clause, time can (not universal) become at large and LD clause fails. EOTs also relate to financial matters including bonus situation

Contracts and Project Delays


Contract provisions define the basis of entitlement Contracts are imprecise as to how to demonstrate delay and prove entitlement Debate about actual delay and contractual

entitlement
Hence Delay Analysis Methodology has developed

SCL Protocol advances Delay Analysis


Delay to be on the critical path

Extension of Time Methods

Estimate or Model Methods (investigate the EVENT and its potential impact)
Actual Methods (identify the DELAY period and investigate what caused it)

Model Based Methods


Global and Net Impact Methods As-Planned Impact As-Planned But For Collapsed As-Built (As-Built But For) Time Impact Analysis (Impact / Update)

Actual Based Methods

As-Planned vs As-Built

Windows / Snap-Shot

Model Based Analysis


Activity 1 2 3 4 5 6 7 8 9 10 11

ACTIVITY A ACTIVITY B ACTIVITY C

Event Original Completion

Estimate of Delay

Actual Based Analysis


Activity 1 2 3 4 5 6 7 8 9 10 11

ACTIVITY A ACTIVITY B ACTIVITY C


Original Completion

Why Delay?

Prospective and Retrospective Approaches


P looks forward and anticipates delay

(Preventative; forward looking)


R looks back and establishes cause of delay (Curative; allocation of blame)

SCL Protocol offers another approach to


R; put yourself back at the time of the event and re-assess what might have

happened had things been done


differently.

Activity

Dur

10 11

Completion Date Week 7

A B C D

6 wks 1 wk 2 wks 2 wks

PLANNED PROGRAMME
Original Overall Duration 7 Weeks Critical Path runs through activities A and B

Activity

Dur

10 11

Completion Date Week 7

Completion Date Week 10

A B C D

8 wks 1 wk 5 wks 4 wks

AS-BUILT PROGRAMME
As-Built Overall Duration 10 Weeks Critical Path ran through activities C, D and B

Activity

Dur

10 11

Completion Date Completion Date Week 7 Week 10


Bad Weather

A B C D

8 wks 1 wk
VO

d2

d4
Late Info

5 wks 4 wks

d1
Lack of Resources

d3

DELAYING EVENTS
Events d1, d2 and d4 Owner Delays Event d3 Contractor Delay

Activity

Dur

10 11

Completion Date Week 7

A B C D

6 wks 1 wk 2 wks 2 wks

AS-PLANNED IMPACTED
Uses planned programme

Activity

Dur

10 11

Completion Date Week 7

A B C D

6 wks 1 wk 2 wks 2 wks

AS-PLANNED IMPACTED
Add in first delay to occur (d1)

Activity

Dur

10 11

Completion Date Week 7

A B C D

6 wks 1 wk 2 wks 2 wks

AS-PLANNED IMPACTED
Add in first delay to occur (d1)

Activity

Dur

10 11

Completion Date Week 7

A B C D

6 wks 1 wk
VO

2 wks 2 wks

d1

AS-PLANNED IMPACTED
Add in first delay to occur (d1) - 1 Week Critical Delay

Activity

Dur

10 11

Completion Date Week 7


Bad Weather

A B C D

6 wks 1 wk
VO

d2

2 wks 2 wks

d1

AS-PLANNED IMPACTED
Add in first delay to occur (d1) Add in 2nd delay to occur (d2) - 1 Week Critical Delay - No Critical Delay

Activity

Dur

10 11

Completion Date Week 7


Bad Weather

A B C D

6 wks 1 wk
VO

d2

2 wks 2 wks

d1

AS-PLANNED IMPACTED
Add in first delay to occur (d1) Add in 2nd delay to occur (d2) Add in 3rd delay to occur (d3) - 1 Week Critical Delay - No Critical Delay

Activity

Dur

10 11

Completion Date Week 7


Bad Weather

A B C D

6 wks 1 wk
VO

d2

2 wks 2 wks

d1
Lack of Resources

d3

AS-PLANNED IMPACTED
Add in first delay to occur (d1) Add in 2nd delay to occur (d2) Add in 3rd delay to occur (d3) - 1 Week Critical Delay - No Critical Delay - 2 Weeks Critical Delay

Activity

Dur

10 11

Completion Date Week 7


Bad Weather

A B C D

6 wks 1 wk
VO

d2

d4
Late Info

2 wks 2 wks

d1
Lack of Resources

d3

AS-PLANNED IMPACTED
Add in first delay to occur (d1) Add in 2nd delay to occur (d2) Add in 3rd delay to occur (d3) Add in 4th delay to occur (d4) - 1 Week Critical Delay - No Critical Delay - 2 Weeks Critical Delay - No Critical Delay

Activity

Dur

10 11

Completion Date Completion Date Week 7 Week 10


Bad Weather

A B C D

8 wks 1 wk
VO

d2

d4
Late Info

5 wks 4 wks

d1
Lack of Resources

d3

COLLAPSED AS-BUILT
Uses as-built programme logic linked

Activity

Dur

10 11

Completion Date Completion Date Week 7 Week 10


Bad Weather

A B C D

8 wks 1 wk
VO

d2

d4
Late Info

5 wks 4 wks

d1
Lack of Resources

d3

COLLAPSED AS-BUILT
Critical Path Identified and first employer delay removed

Activity

Dur

10 11

Completion Date Completion Date Week 7 Week 10


Bad Weather

A B C D

8 wks 1 wk 2 wks

d2

d4
Late Info

LackLackResources of of Resources LackLackResources of Resources LackLackResources Resources LackResources of Resources of of of of of of Resources of of of of of of Resources LackResources LackResources LackResources LackResources LackResources LackResources Lack Lack Lack

4 wks

dddddddddddddddd3 333333333333333

COLLAPSED AS-BUILT
Critical Path Identified and first employer delay removed

Activity

Dur

10 11

Completion Date Completion Date Week 7 Week 10


Bad Weather

A B C D

8 wks 1 wk 2 wks

d2

d4
Late Info

Lack of Resources

4 wks

d3

COLLAPSED AS-BUILT
Critical Path Identified and first employer delay removed 1 Weeks Critical Delay Allocated to d1

Activity

Dur

10 11

Completion Date Completion Date Week 7 Week 10


Bad Weather

A B C D

8 wks 1 wk 2 wks

d2

d4
Late Info

Lack of Resources

4 wks

d3

COLLAPSED AS-BUILT
Critical Path Identified and next employer delay removed 1 Weeks Critical Delay Allocated to d1

Activity

Dur

10 11

Completion Date Completion Date Week 7 Week 10


Bad Weather

A B C D

7 wks 1 wk 2 wks

d2

Lack of Resources

4 wks

d3

COLLAPSED AS-BUILT
Critical Path Identified and next employer delay removed 1 Weeks Critical Delay Allocated to d1 1 Weeks Critical Delay Allocated to d4

Activity

Dur

10 11

Completion Date Completion Date Week 7 Week 10


Bad Weather

A B C D

7 wks 1 wk 2 wks

d2

Lack of Resources

4 wks

d3

COLLAPSED AS-BUILT
Critical Path Identified and next employer delay removed 1 Weeks Critical Delay Allocated to d1 1 Weeks Critical Delay Allocated to d4

Activity

Dur

10 11

Completion Date Completion Date Week 7 Week 10

A B C D

6 wks 1 wk 2 wks
Lack of Resources

4 wks

d3

COLLAPSED AS-BUILT
Critical Path Identified and next employer delay removed 1 Weeks Critical Delay Allocated to d1 1 Weeks Critical Delay Allocated to d4 1 Weeks Critical Delay Allocated to d2

Results from Model Based Methods


Delay
d1 (VO)

As-Planned Impact
1 week critical delay

Collapsed As-Built
1 week critical delay

d2 (bad weather)

no critical delay

1 week delay

d3 (lack resources)

2 weeks critical delay

no critical delay

d4 (late info)

no critical delay

1 week critical delay

Activity

Dur

10 11

Completion Date Week 7

Completion Date Week 10

A B C D

8 wks 1 wk 5 wks 4 wks

AS-PLANNED vs AS-BUILT
As-Built Overall Duration 10 Weeks Critical Path ran through activities C, D and B

Activity

Dur

10 11

Completion Date Week 7

Completion Date Week 10

A B C D

8 wks 1 wk 5 wks 4 wks

AS-PLANNED vs AS-BUILT (WINDOWS)


Programme divided into time slices and analysed progressively

Activity

Dur

10 11

Completion Date Week 7

Completion Date Week 10

A B C D

8 wks 1 wk 5 wks 4 wks

AS-PLANNED vs AS-BUILT (WINDOWS)


Programme divided into time slices and analysed progressively

Activity

Dur

10 11

Completion Date Week 7

Completion Date Week 10

A B C D

8 wks 1 wk 5 wks 4 wks

AS-PLANNED vs AS-BUILT (WINDOWS)


Programme divided into time slices and analysed progressively

Activity

Dur

10 11

Completion Date Week 7

Completion Date Week 10

A B C D

8 wks 1 wk 5 wks 4 wks

AS-PLANNED vs AS-BUILT (WINDOWS)


Programme divided into time slices and analysed progressively

The planned programme is reconstructed and divided into snap-shot periods


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Planned Finish Date

Ground Works

Basement Floor 1 Floor 2

Floor 3

TIME IMPACT ANALYSIS

Delays occurring within the first snap-shot period are added and the programme is re-analysed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Planned Finish Date

Ground Works

Basement Floor 1 Floor 2


Delay Influenced End Date

Floor 3

TIME IMPACT ANALYSIS

The actual progress within the snapshot period is researched


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Planned Finish Date

Ground Works

Basement Floor 1 Floor 2


Delay Influenced End Date

Floor 3

TIME IMPACT ANALYSIS

The planned programme is updated to reflect the actual progress within the snapshot period and then re-analysed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Planned Finish Date

Ground Works

Basement Floor 1 Floor 2


Delay Influenced End Date

End Date based on Actual Progress

Floor 3

TIME IMPACT ANALYSIS

The next snapshot period is analysed


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
End Date as at end of 1st snapshot period

Ground Works

Basement Floor 1 Floor 2

Floor 3

TIME IMPACT ANALYSIS

Delays occurring within the 2nd snap-shot period are added and the programme is re-analysed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
End Date as at end of 1st snapshot period

Ground Works

Basement Floor 1 Floor 2


Delay Influenced End Date

Floor 3

TIME IMPACT ANALYSIS

The actual progress within the snapshot period is researched


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
End Date as at end of 1st snapshot period

Ground Works

Basement Floor 1 Floor 2


Delay Influenced End Date

Floor 3

TIME IMPACT ANALYSIS

The planned programme is updated to reflect the actual progress within the snapshot period and then re-analysed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
End Date as at end of 1st snapshot period

Ground Works

Basement Floor 1 Floor 2


Delay Influenced End Date
End Date based on Actual Progress

Floor 3

TIME IMPACT ANALYSIS

Programme Float

Two Main Types


Terminal Total

Contract Completion Date

10 days

TERMINAL FLOAT

10 days

15 days
TOTAL FLOAT

Who Owns the Float ?

Contract Completion Date

10 days

TERMINAL FLOAT

10 days

Contract Completion Date

10 days

TERMINAL FLOAT

EMPLOYER DELAY

10 days

Contract Completion Date

10 days

TERMINAL FLOAT

EMPLOYER DELAY

10 days 15 days

CONTRACTOR DELAY

Contract Completion Date

10 days

TERMINAL FLOAT

EMPLOYER DELAY

10 days 15 days

CONTRACTOR DELAY Original Contract period

CONCURRENCY

Contract Completion Date


Revision to the Works 4 weeks Insufficient Resources

Bad Weather

4 weeks

Contract Completion Date


Revision to the Works 4 weeks Insufficient Resources

Bad Weather

4 weeks

Revision to the finishing Works

Structure

Contractors M&E design fault identified

M&E

Finishings

Contract Completion Date


Delay A 4 weeks
Actual

Delay B 3 weeks

4 weeks

Completion

Contract Completion Date


Contractors Delay Fault A 4 weeks
Actual

Delay Employers B Fault 3 weeks

4 weeks

Completion

Contract Completion Date


Contractors Delay Fault A

EFFECT OF THE EMPLOYERS FAULT


4 weeks
Actual

Delay Employers B Fault 3 weeks

4 weeks

Completion

1 Week EOT

Contract Completion Date


Contractors Delay Fault A 4 weeks

1 Week no L&E/ 1 week LDs


Actual

Delay Employers B Fault 3 weeks

4 weeks

Completion

EFFECT OF THE CONTRACTORS FAULT

Contract Completion Date


Contractors Employers Delay Fault A 4 weeks
Actual

Delay Contractors Employers B Fault 3 weeks

4 weeks

Completion

Contract Completion Date


Contractors Employers Delay Fault A 4 weeks

2 Weeks EoT
Actual

Delay Contractors Employers B Fault 3 weeks

4 weeks

Completion

EFFECT OF THE EMPLOYERS FAULT

Contract Completion Date


Contractors Employers Delay Fault A

EFFECT OF THE CONTRACTORS FAULT


4 weeks
Actual

Delay Contractors Employers B Fault 3 weeks

4 weeks

Completion

1 Week Prolongation costs

THE SCL PROTOCOL

THE PROTOCOL (STRUCTURE)


CORE PRINCIPLES GUIDANCE NOTES
S1. Explains the Core Principles
S2. Deals with Programming and Record Keeping S3. Extensions of Time (Prospective) S4. Extensions of Time (Retrospective)

APPENDICES
A. Definitions B. Model Specification Clause (Programmes) C. Model Specification Clause (Records) D. Illustrations

CORE PRINCIPLES
Good Programme Systems and Management Good Record Systems and Management

Contemporaneous, incremental, assessment of delays and


award of Extensions of Time Time Impact Analysis is the preferred methodology

Float Project owns, Contractor receives compensation


Concurrency Contractor receives Time but no Money Retrospective delay analysis Re-live the Project; contradicts

usual assessment of damage?

GUIDANCE NOTES - S1
Definitions (Appendix A) Extension of Time principles

Float
Concurrency Mitigation (best endeavours)

Variations
Global Claims Overheads

Profit
Acceleration (does not address Constructive Acceleration)

GUIDANCE NOTES S2
Form of Programme (Appendix B)
Method Statement Timetables for issue (Initial and Agreed) Updates and Revisions Software

Record Keeping (Appendix C)

GUIDANCE NOTES S3
Extensions of Time during the Project (Prospective) Time Impact Analysis Updated Programmes Revised Programmes

Level of detail in any analysis


Illustrations (Appendix D)

GUIDANCE NOTES S4
Extensions of Time after the Project (Retrospective)

Four Methods
Updated/Revised Programmes Balance taken re time/costs Consider the terms of the Contract Factual analysis or Entitlement driven? Placing oneself back at the time of the delay

THE PROTOCOL -AIMS Not intended as a contract document Offers specification terms for programme management and record keeping Offers guidance in the management of delay and disruption that is, in the management of change Extensions of Time should be dealt with at the time Time Impact Analysis is the recommended method

THE PROTOCOL -ACHIEVEMENTS Hoped that Contracting Parties would adopt its recommendations Prospective X Hoped/Attempted to have industry contracting bodies adopt it Prospective X Attempted to have the Courts adopt it Retrospective X Delay Analysts adopt it

Added to knowledge; Great Debate!

THE PROTOCOL -CHALLENGES Must be Industry/Profession/Employer led

Main Contractors would be unwise adopting it with


Subcontractors It reduces risk pre-set rules/outcomes It increases risk assumes one solution for all cases Early delays tend to over-compensate the Contractor Protocol needs re-drafting to remove optional aspects

THE PROTOCOL -CHALLENGES Needs to deal more practically with constructive acceleration Should advance a debate on the fairness of condition precedent clauses Does it amend the basis upon which damage is normally assessed?

English law focussed; need to consider other legal systems.

THE PROTOCOL -CONCLUSIONS Drafting requirements

Commercial implications; risk issue


Methodology greatly influences outcomes Practical implications; skills and resources required Not widely adopted yet on live projects Authors to be complemented for creating Great Debate

DELAY CASE STUDY

1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B

10

11

12

13

14

Planned Completion

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme

1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B

10

11

12

13

14

Delay 1 Slow Progress

Planned Completion

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme As-Built Projected

1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B

10

11

12

13

14

Delay 1 Slow Progress

Planned Completion

Delay 2 Notified Late Switchgear Delivery Delay 3 Inherent Design Fault Discovered

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor

Approved Programme

As-Built

Projected

1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B

10

11

12

13

14

Delay 1 Slow Progress

Planned Completion

Delay 2 Notified Late Switchgear Delivery Delay 3 Inherent Design Fault Discovered

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor

Approved Programme

As-Built

Projected

1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B

10

11

12

13

14

Delay 1 Slow Progress

Planned Completion

Delay 2 Notified Late Switchgear Delivery Delay 3 Inherent Design Fault Discovered

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor

Delay 4 Crane Delay Approved Programme As-Built Projected

1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B

10

11

12

13

14

Delay 1 Slow Progress

Planned Completion

Delay 2 Notified Late Switchgear Delivery Delay 3 Inherent Design Fault Discovered

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor

Delay 4 Crane Delay Approved Programme As-Built Projected

1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B

10

11

12

13

14

Delay 1 Slow Progress

Planned Completion

Actual Completion

Delay 2 Notified Late Switchgear Delivery Delay 3 Inherent Design Fault Discovered

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor

Delay 4 Crane Delay Approved Programme As-Built Projected

1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B

10

11

12

13

14

Slow Progress

Planned Completion

Actual Completion

Late Switchgear Delivery

Inherent Design Fault

Crane Delay

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme As-Built Projected

REVIEW

Collapsed As-Built Method


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
Inherent Design Fault Crane Delay

10

11

12

13

14

Slow Progress

Late Switchgear Delivery

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme As-Built Projected

Collapsed As-Built Method


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
Inherent Design Fault Crane Delay

10

11

12

13

14

Slow Progress

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme As-Built Projected

Collapsed As-Built Method


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
Inherent Design Fault

10

11

12

13

14

Slow Progress

Both equally critical

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme As-Built Projected

Collapsed As-Built Method


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B 2 3 4 5 6 7 8 9 10 11 12 13 14

Slow Progress

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme As-Built Projected

Collapsed As-Built Method


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B 2 3 4 5 6 7 8 9 10 11 12 13 14

Slow Progress

Reverse the Sequence

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme As-Built Projected

Collapsed As-Built Method


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
Inherent Design Fault

10

11

12

13

14

Slow Progress

Reverse the Sequence

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme As-Built Projected

Collapsed As-Built Method


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
Inherent Design Fault

10

11

12

13

14

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme As-Built Projected

Collapsed As-Built Method


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B 2 3 4 5 6 7 8 9 10 11 12 13 14

Slow Progress

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor


Approved Programme As-Built Projected

Employers Liability for Week 11 & 12 As-Planned Impact Method


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B
Delay 3 Inherent Design Fault Discovered

10

11

12

13

14

Planned Completion

plus 1 Weeks Float

4 ACCESS GANTRY Main Contractor 200T CRANE Main Contractor

Approved Programme

Concurrency - No Critical Delay by Subcontractor A


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B 2 3 4 5 6 7 8 9 10 11 12 13 14

Planned Completion

4 ACCESS GANTRY Main Contractor 2000T CRANE Main Contractor


Approved Programme

Dominant Delay - 2 Weeks Delay by Subcontractor B


1 1 STEEL FRAME Sub-Contractor A 2 WALLS & ROOF Main Contractor 3 SWITCH GEAR Sub-Contractor B 2 3 4 5 6 7 8 9 10 11 12 13 14

Planned Completion

Late Switchgear Delivery

4 ACCESS GANTRY Main Contractor 2000T CRANE Main Contractor


Approved Programme

Answer 1 Month 11 - Subcontractor A Month 12 - Main Contractor Month 13 - Subcontractor B Answer 2 Month 11 - Subcontractor A Month 12 - Subcontractor B Month 13 - Subcontractor B Answer 3 Month 11 - Subcontractor B Month 12 - Subcontractor B Month 13 - Subcontractor B Answer 4 Month 11 - Employer's Liability Month 12 - Subcontractor B Month 13 - Subcontractor B

Vous aimerez peut-être aussi