Copyright Siemens AG. All rights reserved Energy Sector / Power Transmission Solutions
Protection zone
IdCH IdLH UdH IacY
UsumY
3 3 3
UsumD
DCFilter
Protection zone
IacD Uac IdCN UdN HSGS HSNBS IdLN MRTB Idee2 Idee1
MRS IdMRS
Other Pole
Page 2
April 2009
E T PS EN21
Copyright Siemens AG 2008. All rights reserved. Energy Sector - Power Transmission Solutions
IdCH
IdLH
UdH IacY
UsumY
3 3 3
UsumD
DCFilter
IacD Uac IdCN UdN HSGS HSNBS IdLN MRTB Idee2 Idee1
MRS IdMRS
Other Pole
Page 3
April 2009
E T PS EN21
Copyright Siemens AG 2008. All rights reserved. Energy Sector - Power Transmission Solutions
Protection Task
Initiated Sequences At rectifier: Converter Block to Pole Control At inverter: Converter Block to Pole Control, Bypass Pair Firing Inhibit Retarded Protection Task for both stations if firing pulses are blocked: Opening of HSNBS ESOF to Pole Control Typical settings Threshold = 0.25 p.u. Delay time = 10 ms
Copyright Siemens AG 2008. All rights reserved. Energy Sector - Power Transmission Solutions
Page 4
April 2009
E T PS EN21
IdCH
IdLH
UdH IacY
UsumY
3 3 3
UsumD
DCFilter
IacD Uac IdCN UdN HSGS HSNBS IdLN MRTB Idee2 Idee1
MRS IdMRS
Other Pole
Page 5
April 2009
E T PS EN21
Copyright Siemens AG 2008. All rights reserved. Energy Sector - Power Transmission Solutions
Protection Task
Evaluation Principle Abs(IdLN IdCN) > threshold, (2 stages) Initiated Sequences ESOF to Pole Control Open AC circuit breaker Opening of HSNBS 1st stage: Threshold = 0.25 p.u.; Delay time = 50 ms 2nd stage: Threshold = 0.07 p.u.; Delay time = 500 ms
Typical settings
Page 6
April 2009
E T PS EN21
Copyright Siemens AG 2008. All rights reserved. Energy Sector - Power Transmission Solutions
IdCH
IdLH
UdH IacY
UsumY
3 3 3
UsumD
DCFilter
IacD Uac IdCN UdN HSGS HSNBS IdLN MRTB Idee2 Idee1
MRS IdMRS
Other Pole
Page 7
April 2009
E T PS EN21
Copyright Siemens AG 2008. All rights reserved. Energy Sector - Power Transmission Solutions
Protection Task
Evaluation Principle Abs(IdLH IdLN) > threshold, (2 stages) Initiated Sequences ESOF to Pole Control Open AC circuit breaker Opening of HSNBS 1st stage: Threshold = 0.25 p.u.; Delay time = 200 ms 2nd stage: Threshold = 0.07 p.u.; Delay time = 1000 ms
Typical settings
Page 8
April 2009
E T PS EN21
Copyright Siemens AG 2008. All rights reserved. Energy Sector - Power Transmission Solutions