Vous êtes sur la page 1sur 40

IE 305 BUS 307

CH 5

CAPACITY PLANNING

2006 Prentice Hall, Inc.

S7 1

Capacity
The throughput, or the number of units a facility can hold, receive, store, or produce in a period of time Determines fixed costs

Determines if demand will be satisfied


Three time horizons
2006 Prentice Hall, Inc. S7 2

Planning Over a Time Horizon


Long-range planning Intermediaterange planning Short-range planning Modify capacity Add facilities Add long lead time equipment Subcontract Add equipment Add shifts

*
Add personnel Build or use inventory Schedule jobs Schedule personnel Allocate machinery Use capacity

* Limited options exist


Figure S7.1
2006 Prentice Hall, Inc. S7 3

Design and Effective Capacity


Design capacity is the maximum theoretical output of a system
Normally expressed as a rate

Effective capacity is the capacity a firm expects to achieve given current operating constraints
Often lower than design capacity

2006 Prentice Hall, Inc.

S7 4

Utilization and Efficiency


Utilization is the percent of design capacity achieved
Utilization = Actual Output/Design Capacity

Efficiency is the percent of effective capacity achieved


Efficiency = Actual Output/Effective Capacity

2006 Prentice Hall, Inc.

S7 5

Bakery Example
Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 8 hour shifts

Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls

2006 Prentice Hall, Inc.

S7 6

Bakery Example
Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 8 hour shifts

Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls Utilization = 148,000/201,600 = 73.4%

2006 Prentice Hall, Inc.

S7 7

Bakery Example
Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls Utilization = 148,000/201,600 = 73.4% Efficiency = 148,000/175,000 = 84.6%

2006 Prentice Hall, Inc.

S7 8

Bakery Example
Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 8 hour shifts Efficiency = 84.6% Efficiency of new line = 75% Expected Output = (Effective Capacity)(Efficiency)

= (175,000)(.75) = 131,250 rolls

2006 Prentice Hall, Inc.

S7 9

Managing Demand
Demand exceeds capacity
Curtail demand by raising prices, scheduling longer lead time

Long term solution is to increase capacity

Capacity exceeds demand


Stimulate market

Product changes

Adjusting to seasonal demands


Produce products with complimentary demand patterns
2006 Prentice Hall, Inc. S7 10

Economies and Diseconomies of Scale


Average unit cost (dollars per room per night)

25 - Room Roadside Motel

50 - Room Roadside Motel

75 - Room Roadside Motel

Economies of scale

Diseconomies of scale

25

50 Number of Rooms

75
Figure S7.2
S7 11

2006 Prentice Hall, Inc.

Capacity Considerations
Forecast demand accurately
Understanding the technology and capacity increments Find the optimal operating level (volume)

Build for change

2006 Prentice Hall, Inc.

S7 12

Approaches to Capacity Expansion


(a) Leading demand with incremental expansion
Demand New capacity Expected demand

(b) Leading demand with one-step expansion


Demand New capacity Expected demand

(c) Capacity lags demand with incremental expansion


Demand New capacity Expected demand

(d) Attempts to have an average capacity with incremental expansion


Demand New capacity Expected demand

Figure S7.4
2006 Prentice Hall, Inc. S7 13

Break-Even Analysis
Technique for evaluating process and equipment alternatives Objective is to find the point in dollars and units at which cost equals revenue Requires estimation of fixed costs, variable costs, and revenue

2006 Prentice Hall, Inc.

S7 14

Break-Even Analysis
Fixed costs are costs that continue even if no units are produced
Depreciation, taxes, debt, mortgage payments

Variable costs are costs that vary with the volume of units produced
Labor, materials, portion of utilities
Contribution is the difference between selling price and variable cost
2006 Prentice Hall, Inc. S7 15

Break-Even Analysis
Assumptions Costs and revenue are linear functions
Generally not the case in the real world

We actually know these costs


Very difficult to accomplish

There is no time value of money


2006 Prentice Hall, Inc. S7 16

Break-Even Analysis
900 800 700 Cost in dollars 600 Total revenue line

Break-even point Total cost = Total revenue

Total cost line

500
400 300 200 100
|

Variable cost

Fixed cost

Figure S7.5
2006 Prentice Hall, Inc.

| | | | | | | | | | | 0 100 200 300 400 500 600 700 800 900 1000 1100

Volume (units per period)


S7 17

Break-Even Analysis
BEPx = Break-even point in units BEP$ = Break-even point in dollars P = Price per unit (after all discounts) x = Number of units produced TR = Total revenue = Px F = Fixed costs V = Variable costs TC = Total costs = F + Vx

Break-even point occurs when

TR = TC or Px = F + Vx
2006 Prentice Hall, Inc.

F BEPx = P-V

S7 18

Break-Even Analysis
BEPx = Break-even point in units BEP$ = Break-even point in dollars P = Price per unit (after all discounts) x = Number of units produced TR = Total revenue = Px F = Fixed costs V = Variable costs TC = Total costs = F + Vx

BEP$ = BEPx P F P = P-V F = (P - V)/P F = 1 - V/P


2006 Prentice Hall, Inc.

Profit = TR - TC = Px - (F + Vx) = Px - F - Vx = (P - V)x - F


S7 19

Break-Even Example
Fixed costs = $10,000 Direct labor = $1.50/unit Material = $.75/unit Selling price = $4.00 per unit

$10,000 F BEP$ = = 1 - [(1.50 + .75)/(4.00)] 1 - (V/P)

2006 Prentice Hall, Inc.

S7 20

Break-Even Example
Fixed costs = $10,000 Direct labor = $1.50/unit Material = $.75/unit Selling price = $4.00 per unit

$10,000 F BEP$ = = 1 - [(1.50 + .75)/(4.00)] 1 - (V/P)


$10,000 = = $22,857.14 .4375 $10,000 F BEPx = = = 5,714 4.00 - (1.50 + .75) P-V

2006 Prentice Hall, Inc.

S7 21

Break-Even Example
Multiproduct Case
BEP$ = F

Vi 1x (Wi) Pi

where

V P F W i

= variable cost per unit = price per unit = fixed costs = percent each product is of total dollar sales = each product

2006 Prentice Hall, Inc.

S7 22

Multiproduct Example
Fixed costs = $3,500 per month

Item Sandwich Soft drink Baked potato Tea Salad bar

Price $2.95 .80 1.55 .75 2.85

Cost $1.25 .30 .47 .25 1.00

Annual Forecasted Sales Units 7,000 7,000 5,000 5,000 3,000

2006 Prentice Hall, Inc.

S7 23

Multiproduct Example
Fixed costs = $3,500 per month

Item Sandwich Soft drink Baked potato Tea Salad bar

Price $2.95 .80 1.55 .75 2.85

Cost $1.25 .30 .47 .25 1.00

Annual Forecasted Sales Units 7,000 7,000 5,000 5,000 3,000

Item (i) Sandwich Soft drink Baked potato Tea Salad bar

Annual Weighted Selling Variable Forecasted % of Contribution Price (P) Cost (V) (V/P) 1 - (V/P) Sales $ Sales (col 5 x col 7) $2.95 .80 1.55 .75 2.85 $1.25 .30 .47 .25 1.00 .42 .38 .30 .33 .35 .58 .62 .70 .67 .65 $20,650 5,600 7,750 3,750 8,550 $46,300 .446 .121 .167 .081 .185 1.000 .259 .075 .117 .054 .120 .625
S7 24

2006 Prentice Hall, Inc.

BEP = Multiproduct Example V 1 - P x (W ) F


$ i i i

Fixed costs = $3,500 per month $3,500 x Forecasted Annual 12 = $67,200 = .625 Units Item Price Cost Sales Sandwich $2.95 $1.25 7,000 $67,200 Daily Soft drink .80 .30 7,000 = sales 312 days = $215.38 Baked potato 1.55 .47 Annual 5,000 Weighted % of Tea Selling Variable .75 .25Forecasted 5,000 Contribution Item (i) Price (P) Cost (V) (V/P) 1 - (V/P) Sales $ Sales (col 5 x col 7) Salad bar 2.85 1.00 x $215.38 3,000 .446 = 33 Sandwich $2.95 $1.25 .42 .58 $20,650 .44632.6 .259 $2.95 sandwiches
Soft drink Baked potato Tea Salad bar .80 1.55 .75 2.85 .30 .47 .38 .30 .33 .35 .62 .70 .67 .65 5,600 7,750 .121 .075 per day .167 .117 .054 .120 .625
S7 25

.25 1.00

3,750 8,550 $46,300

.081 .185 1.000

2006 Prentice Hall, Inc.

Strategy-Driven Investment
Operations may be responsible for return-on-investment (ROI) Analyzing capacity alternatives should include capital investment, variable cost, cash flows, and net present value

2006 Prentice Hall, Inc.

S7 26

Net Present Value (NPV)


F P= (1 + i)N

where

F P i N

= future value = present value = interest rate = number of years

2006 Prentice Hall, Inc.

S7 27

NPV Using Factors


F P= N = FX (1 + i)
where X = a factor from Table S7.1 defined as = 1/(1 + i)N and F = future value
5% .952 .907 .864 .823 .784 6% .943 .890 .840 .792 .747 7% .935 .873 .816 .763 .713 10% .909 .826 .751 .683 .621
S7 28

Portion of Table S7.1

Year 1 2 3 4 5

2006 Prentice Hall, Inc.

Present Value of an Annuity


An annuity is an investment which generates uniform equal payments
S = RX
where X = factor from Table S7.2 S = present value of a series of uniform annual receipts R = receipts that are received every year of the life of the investment

2006 Prentice Hall, Inc.

S7 29

Present Value of an Annuity


Portion of Table S7.2 Year 1 2 3 4 5 5% .952 1.859 2.723 4.329 5.076 6% .943 1.833 2.676 3.465 4.212 7% .935 1.808 2.624 3.387 4.100 10% .909 1.736 2.487 3.170 3.791

2006 Prentice Hall, Inc.

S7 30

Process, Volume, and Variety


Figure 7.1

Volume Low Volume Repetitive Process High Volume Mass Customization (difficult to achieve, but huge rewards) Dell Computer Co.

High Variety one or few units per run, high variety (allows customization) Changes in Modules modest runs, standardized modules Changes in Attributes (such as grade, quality, size, thickness, etc.) long runs only
2006 Prentice Hall, Inc.

Process Focus projects, job shops (machine, print, carpentry) Standard Register

Repetitive (autos, motorcycles) Harley Davidson Product Focus (commercial baked goods, steel, glass) Nucor Steel
S7 31

Poor Strategy (Both fixed and variable costs are high)

Some Possible Growth Patterns


Volume Volume

Growth

Decline

Time

Time

Cyclical
Volume Volume

Stable

0
2006 Prentice Hall, Inc.

Time

Time
S7 32

Developing Capacity Alternatives


Design flexibility into systems
Take a big picture approach to capacity changes Prepare to deal with capacity chunks Attempt to smooth out capacity requirements Identify the optimal operating level

2006 Prentice Hall, Inc.

S7 33

Planning Service Capacity


Need to be near customers
Capacity and location are closely tied

Inability to store services


Capacity must me matched with timing of demand

Degree of volatility of demand


Peak demand periods
2006 Prentice Hall, Inc. S7 34

Measuring Capacity
By units of output ( barrels of beer , # of cars)

Standard time time to produce a product by a qualified operator at a normal pace.


2006 Prentice Hall, Inc. S7 35

Levels of Capacity
Must be measured at these three levels
Machine or individual worker

Work center
Plant

2006 Prentice Hall, Inc.

S7 36

Calculating Processing Requirements


Product Annual Demand Standard processing time per unit (hr.) Processing time needed (hr.)

#1 #2 #3
2006 Prentice Hall, Inc.

400 300 700

5.0 8.0 2.0

2,000 2,400 1,400 5,800


37
S7 37

Determining Capacity Available


Measurement
Demonstrated capacity comes from historical data

Calculation
Calculated or rated capacity is based on available time, utilization and efficiency.

2006 Prentice Hall, Inc.

S7 38

Capacity Req.
Load determination
1. Determine time needed for each order at each center. 2. Sum the CR for individual orders to obtain a load. Time needed for order
Sum of Setup and Run times
2006 Prentice Hall, Inc.

Example 150 gear shafts with a setup of 1.5 hours and run time of 0.2 hours Standard time = 1.5 + ( 150 x 0.2)
S7 39

QUESTIONS???

2006 Prentice Hall, Inc.

S7 40

Vous aimerez peut-être aussi