Académique Documents
Professionnel Documents
Culture Documents
GRID
Technical Institute
This document is the exclusive property of Alstom Grid and shall not be transmitted by any means, copied, reproduced or modified without the prior written consent of Alstom Grid Technical Institute. All rights reserved.
Z3 Z2
Z1
Z1 Z2 Z3
Z1 Z2 T2
1 .
Trip
Trip
1 . T2
Z1 Z2
Z3
T3
T3
Z3
Zone 1 set to 80% leaves 2 end zones Faults in end zone results in instantaneous tripping at one end and time delayed at the other Time delay may lead to system stability problems Sequential clearance leaves no dead time for high speed A/R cycle (transient fault becomes permanent) Longer clearance times - More damage
Z1X Z1 Z2 Z3
A/R Z1X
&
&
A/R Z1X
Z1 Z2
1 T2
1 .
Trip
Trip
1 .
1 T2
Z1 Z2
Z3
T3
T3
Z3
No signalling channel required (may be used as temporary replacement for carrier aided scheme when comms. channel out of service) Provides fast fault clearance at both ends for a transient fault anywhere along the line length Allows the use of high speed A/R cycle
Tripping can occur for external faults (but will be followed by an autoreclose) Basic distance scheme logic applies following reclose (i.e. potential for time delayed clearance for permanent faults) Only suitable to systems where autoreclose is used (for example can not be used on cable circuits)
Z3 Z2 Z1
Z1 Z2 Z3
T1 = 40ms (allows for slowest pickup of Zone 2) T2 = 18ms (prevents LOL trip for external fault with CB pole scatter)
LDA LDB LDC & .
0
T1
1 .
.. & .. .
T2 0
Z2
&
Trip
Fast fault clearance without the need for a signalling channel Only applicable where 3 phase tripping is used Only operates for unbalanced faults
Load current (above the current detector settings) must exist prior to the fault to arm the scheme Can be used as back up to signal aided scheme
Provide high speed clearance for all faults on line (for example current differential) Does not provide inherent back-up protection
SOLUTION IS TO PROVIDE DISTANCE PROTECTION FOR BACKUP PROTECTION OF ADJACENT LINES WITH AN AIDED TRIPPING SCHEME FOR HIGH SPEED PROTECTION OF WHOLE LINE
Requires the use of an ON/OFF signalling channel between line ends (i.e. HF/VF/Fibre Optic/Radio)
Acceleration
Transfer tripping
Direct Permissive Underreach Permissive Overreach
Blocking
Z3 Z2
Z1
Z1 Z2 Z3
Z1 Z2 T2
1 .
Trip
Trip
1 . T2
Z1 Z2
Z3
T3
T3
Z3
All faults anywhere along the protected line can be cleared instantaneously at both line ends Scheme can be advantageous for protecting 3 terminal lines due to ease of application
A very secure signalling channel is required :incorrect operation leads to false tripping Circuit breakers at both line ends must be closed and contribute fault current to obtain high speed fault clearance If the channel fails only the Basic scheme logic will be provided
Z3 Z2
Z1
Z1 Z2 Z3 Tx Rx Tx Rx
Z1/Z2 Z3 T3
1 . 1 T2 .
Trip
Trip
1 . T3
Z1/Z2 Z3
Change Z1 reach
1 . T2
Permissive Schemes
Z3 Z2 Z1
Z1 Z2 Z3 0
100
0
100
& Z1 T2 Z2
Z3
T3
T3
Z3
C
Fault
D
21 21
Send
A
Rx + Z2
C
Fault
D
21 21
Rx + Z2
Scheme is very secure as signalling channel only keyed for internal fault (Zone 1 initiation)
If one terminal of the line is open then only Basic scheme logic will apply
If there is a weak infeed at one terminal then only Basic scheme logic will apply If signalling channel fails then only Basic scheme logic will apply Resistive coverage is governed by Zone 1 setting (may be limited on short lines for MHO)
Z2
Z1
Z1 Z2 Z3
Rx Tx
Rx Tx
& Z1 T2 Z2
Z3
T3
T3
Z3
Z2
Z1
Z1 Z2 Z3
Rx Tx
Rx Tx
& Z1 T2 Z2
Z3
T3
T3
Z3
Z2
Z1
Z1 Z2 Z3
CB open
& 1 Rx Tx Rx Tx 1
&
CB open
& Z1 T2 Z2
Z3
T3
T3
Z3
Z1
Z2
Z4
Send Logic : Z2 Trip Logic : Rx + Z2 Open terminal echo : CB Open + Rx Weak Infeed echo : Z4 + Rx
CB open Z4
& & 1 Rx Tx Rx Tx 1
& &
CB open Z4
& Z1 T2 Z2
Z3
T3
T3
Z3
Z1
Z2
Z4
Send Logic : Z2 Trip Logic : Rx + Z2 Open terminal echo : CB Open + Rx Weak Infeed echo : Z4 + Rx Weak Infeed trip : Z4 + LDOV reset + Rx
CB open Z4 LDOV
CB open Z4 LDOV
Z1 Z2 T2
Z1 T2 Z2
Z3
T3
T3
Z3
Provides better resistive coverage, especially on short lines, where MHO measuring elements are used For cases where one line terminal is open, open breaker echo logic can be used For cases of weak or zero infeed at one line terminal weak infeed logic can be used (reverse looking zone required)
Duplex signalling channel required Scheme is theoretically less secure then PUR as signalling channel is keyed for external faults If signalling channel fails then only Basic scheme logic will apply
Blocking Schemes
Z1
Z2
& Rx Tx Rx Tx
&
& Z1 T2 Z2
Z3
T3
T3
Z3
Z1
Z2
& Rx Tx Rx Tx
&
& Z1 T2 Z2
Z3
T3
T3
Z3
Provides better resistive coverage than PUR on short lines where MHO elements are used
Fast tripping will still be possible at closed end of line for all fault positions with remote breaker open Fast tripping will still be possible at strong infeed terminal for all fault positions where remote terminal has no or weak infeed
Historically only 2 forward zones of protection available (unless relay has >3 Zones) If signalling channel fails supervision must revert the relay back to Basic scheme logic
Historically current sensitivity is lower as tripping elements (Z2) are controlled by high set current level detectors (to ensure blocking elements (Z3/Z4) are more sensitive than tripping elements)
Teed Feeders
A-A - Zone 1 reach of relay at A B-B - Zone 1 reach of relay at B C-C - Zone 1 reach of relay at C ABC Zone not covered by Zone 1 from any terminal. Hence schemes reliant on Zone 1 operation would not work (Z1 ext, PUR)
C Za Zc
Ia
Zb
Ic
Actual impedance to fault from terminal A Measured voltage at terminal A Measured current at terminal A Impedance measured by relay A
V I V/I
Relay therefore measures a greater impedance than the actual impedance and underreaches. Must allow for this underreach when setting Zone 2 elements to ensure correct scheme operation
No infeed from terminal B. Fault therefore not covered by Zone 1 from any terminal. Hence schemes reliant on Zone 1 operation would not work (Z1 ext, PUR)
Relay at terminal B sees a reverse fault. No scheme will operate at this terminal. Fault clearance will be sequential following opening of breaker A from relay A Zone 1 element.
DEF schemes are identical to Distance schemes DEF Forward replaces Zone 2, DEF Reverse replaces Zone 3/4 Reverse No equivalent to Zone 1 as the DEF elements can not have a defined reach, hence no schemes using Zone 1 can be replicated (Z1 ext, PUR)
Ea
RF 21 67N
Independent signalling channel
Eb
21
67N
Independent signalling channels allows the use of different schemes for the distance and DEF elements, for example PUR distance with POR DEF
Ea
RF 21 67N 21 67N
Eb
Shared Channel
Shared signalling channels limits the use of schemes for the distance and DEF elements. Both use the same scheme logic.