Académique Documents
Professionnel Documents
Culture Documents
3/22/13
Directing and coordinating human and material resources throughout the life of a project by using modern management techniques to achieve predetermined objectives of Scope Cost time quality and participation satisfaction
BY CONTRAST
3/22/13
General management of business and industrial corporations assumes a broader outlook with greater continuity of operations Nevertheless, There are sufficient similarities as well as differences between the two so that modern management techniques developed for general management may be adapted for project management.
What is Project Management?
3/22/13
General Management Special Knowledge Domains Project Management
Supporting Disciplines
3/22/13
Specifically, Project management in construction encompasses a set of objectives which may be accomplished by implementing a series of operations subject to resource constraints.
3/22/13
The functions of project management for construction generally include the following:
Specification of project objectives and plans Maximization of efficient resource utilization Implementation of various operations through proper coordination and control of planning, design, estimating, contracting and construction Development of effective communications and mechanisms for resolving conflicts among the various participants.
What is Project Management?
2)
3/22/13
A good construction plan is the basis for developing the budget and the schedule for work.
(PMBook)
Thus, a project manager / planner must synthesize the steps required to yield this result.
3/22/13
the generation of required activities, analysis of the implications of these activities, and choice among the various alternative means of performing activities.
Basic Concepts in the Development of Construction Planning
3/22/13
Schedule Oriented
Time Resour Oriente ce d Oriente (Critica d (Job l Path Scope Proble Schedu Alternative Emphases in Construction Planning m) le)
Basic Concepts in the Development of Construction Planning
Direct Costs
Indirec t Costs
3)
3/22/13
Review the cost, time and reliability impacts of the alternative approaches Adopt the most optimum technology and construction method (i.e. value engineering).
4)
3/22/13
Along with the choice of technology and the consideration of the general method of construction, the planning process is also to define the various work tasks that must be accomplished. The work tasks represent the necessary framework to:
3/22/13
Through which they will result in completion of the project in a timely and efficient fashion.
Defining Work Tasks
Therefore,
3/22/13
It is common to begin with fairly coarse definitions of activities and then to further sub-divide tasks as the plan becomes better defined. As a result, the definition of activities evolves during the preparation of the plan.
Natural hierarchy of activities with large, abstract functional activities repeatedly subDefining Work Tasks divided into more and more specific sub-tasks
3/22/13
5)
Precedence relations between activities signify that the activities must take place in a particular sequence.
3/22/13
Excavat e Trench
Place Formwo rk
3/22/13
Work activity has to be associated with time duration. A straightforward approach to the estimation of activity durations is to keep historical records of particular activities and rely on the average durations from this experience in making new duration estimates.
Initial Duration Estimation Overall Adjustment (e.g. Learning) Activity Duration Estimate
3/22/13
7)
ESTIMATING RESOURCE REQUIREMENTS FOR WORK ACTIVITIES Resource requirements are usually estimated for each activity.
Therefore, By making resource requirement estimates for each activity, the overall resource requirements for the entire the project can be identified.
3/22/13 Typically, resources are categorized into the following three different components:
Note: Resource estimates and resource allocation is essential for purposes of project monitoring and cash flow planning.
Estimating Resource Requirements For Work Activities