Académique Documents
Professionnel Documents
Culture Documents
By Abhishek Kumar Sinha, Janhvi Doshi, Vikram Vijay Guide: Professor Milind Sohoni
September 2010
2
Acknowledgement
We would like to thank Mr. G. P Nivdange and Mr. Ashok Ghule from MJP, Karjat, Mr. Ashok Jangle from Disha Kendra, and Mr. R. M. Ade from the Minor Irrigation, Karjat, for their invaluable support and guidance throughout the project.
10/09/10
Severe drinking water shortage in North Karjat beginning January Reliance on groundwater in most hamlets by Feb some wells dry out, hand-pumps dont work Invitation to CTARA to investigate options.
Various Options
North Karjat
Target area:
spans 120 sq. km covers over 70 hamlets current population (2011) 51,618 Intermediate population (2026) 63721 design population (2041) 81,140
Karjat Taluka
6
Key Outputs
Net Investment 200 lpcd - Rs. 57.25 crore and Rs. 7051 per capita 40 lpcd - Rs. 17.25 crore and Rs. 2119 per capita For comparison, Mumbais piped water system cost Rs. 7000 per capita, Thanes Rs. 10,000 per capita (both 200 LPD), MJPs Anjap project cost Rs.2700 for 55 LPD Novel design methodology for optimization of secondary network
Application of GIS in surveying of target area
Components of Design
RISING MAIN Elevated Storage Reservoir (ESR) Storage Reservoir Ground Mass Balancing Reservoir (GSR) (MBR)
NOTE: Tertiary network design requires both socio-economic data and data-related to land use and it extends beyond the scope of this project .
9
ESR
MBR WT PRising Main
10
11
Met all major design specifications Key design parameters include: 40 lpcd (sustenance norm) and 200 lpcd (livelihood norm) 6 hours of supply to villages per day (5-8 AM and 5-8 PM)
12
MBR
Gravity main ESR Distribution network
13
30 years
30 years 30 years 30 years
14
Available Sources
No. Source Remarks
Barvi Dam
Operated by MIDC Far from target area At low elevation Operating at full capacity Not enough water in summer season Perennial source Supplying water to many dependent areas
Perennial source Tail water discharge of Bhivpuri dam (1000MLD)
2 3
4
15
Available Sources
Target Area
16
Pej River
17
18
Villages identified and lat/long recorded using regional maps and Google Earth Population forecasted for Intermediate Stage (15 years, 2026) and Final Stage (30 years, 2041) Results of geometric and incremental methods of forecasting averaged Five sets of Census data used (1961-2001)
Design Demand = 1.2 x population x per capita demand (SF of 1.2 to account for 20% water losses)
19
20
Network for MBR to 19 ESRs Total length = 72,535m Looped system with 1 source point
Residual pressure of 2m after water delivery to ESR Only a looped system is feasible in given terrain Alternate sources may be added to given loop
21
Shilar
Aleman Kashele
Chinchpada Male
22
Dummy Nodes
Created at intervals of 500-1000m and at every sharp elevation drop or rise along the primary grid Entered into LOOP while designing gravity main to incorporate the elevation changes along pipeline (There are 19 ESRs in the primary grid but over 130 nodes were entered into LOOP) This relatively straightforward application of GIS can potentially replace costly and resource intensive land surveying
23
Dummy Nodes
24
Dummy Nodes
25
Elevation of villages Position of villages Population of villages Elevation of terrain Proximity to major road Appearance of the land
26
27
Staging height of ESR chosen by optimization of piping and ESR construction cost. As ESR height is increased: Pipe costs decrease Construction costs increase Height at which sum of both costs is minimum is chosen Optimum ESR height entered along with node-pipe connectivity information into Branch 3.0
Existing MBR for Anjap Project by MJP
28
29
30
Water structure Jack Well WTP 1st stage 2nd stage MBR
For 200 LPCD 19.47 MLD 22.94 MLD 6.28 MLD 6.50 ML
31
Rising main
32
Google Earth Google Maps Pipe diameter optimization software Branch 3.0 and LOOP 4.0 Topo-sheets of Karjat
33
Use of elevation data of Google Earth to create dummy nodes that monitor and record elevation changes along pipelines Manual detection of:
Road networks Hamlets Uncultivated land Available water sources and potential lift-up points High elevation points along terrain for storage tank location
34
More optimized and streamlined design process is possible with a stronger GIS interface catered specifically towards design of piped water systems. Automated detection of the following: Road networks Population centers Available water sources Uncultivated land Marking of contour lines Calculation of average head loss over a given drawn pipe path (using elevation data) Integration with Branch and Loop (C++ optimization programs)
35
200 lpcd
S. No . 1 2 Particulars Jack Well without Over Head Pump House Raw Water Pumping 1st Stage(Till Machinery 2026) 2nd Stage(Till 2041) Raw Water Rising Main Cost(Rs.) 1122289 13335000 19488000
40 lpcd
377287 2478000 3507000 17762000
3 4
34874000 24426480
WTP
6977800
8870840
1973700
43512000
8736000
55965000
11424000
6 7 8 9 10
Pure Water Rising Main MBR Gravity Main Distribution system(ESR + Pipe) Excavation cost Total
36
Design Population
Daily Demand Net Investment Cost per Person
81,140
19.47 MLD Rs. 57,21,47,601 7051
81,140
3.90 MLD 17,19,33,649 2119
For 40 LPCD
5
3.3
1
1
NOTE: O&M and pumping energy costs are NOT included in the above estimate
37
Summary
Net investment for piped water at both norms of 40/200 lpcd to north Karjat is economically feasible Estimated Net Investment: 200 lcpd - Rs.7051 per capita 40 lpcd - Rs. 2119 per capita Energy costs(@ Rs. 5 per unit, pumping efficiency 75%) 200 lcpd - Rs.400 per capita per annum 40 lpcd - Rs. 79 per capita per annum Energy cost per 1000 litre Rs. 4.56
38
Government/NGO Response
Next Steps
Meeting with Disha Kendra, MJP engineers, MLA They are interested in building this network at norm of 70-110 lpcd
Participation resolution must be passed by gram panchayats FAQ regarding charges, land acquisition, availability of water Detailed planning, MJP may want IIT to be involved
39
Detail Design
Target area to be refined Some villages from west to go, and some from east to come in. Design norm of 100 lpcd.
Design improvements to reduce energy cost Better lift up point Consultation between MJP,TATA Power and Irrigation Department. Better/different network design(consideration of 10/09/10
Single Village (SVS)-built by ZP, operated by GP Regional (RR)-built by MJP, operated by ZP, private body, cooperative. Issues: source and institutional sustainability.
SVS RR
Our Scheme:
Super-RR
Such schemes more likely when regional collapse of local groundwater sources.
Strong Weak
Weak Strong
Wider Issues Livelihood norm? Competition with irrigation Feasibility of regional water supply grid
Technical/Engg. Source stabilizationWatershed, percolation structures, local surface? Pilot study next summer Experience of other states
Cooperative sector
42
Thank You
43