Project Charter
Title: Company: Facilitator: Design Firefighting system for oil installation of Pakistan State Oil Pakistan State Oil Health, Safety & Environment Department Project Need: Pakistan State Oil is the largest oil marketing company of Pakistan having huge infrastructure for storing petroleum products. The storage facilities are protected by firefighting system. Consultants are usually approached to design these systems for PSO who charge handsome amount for the activity. HSE department took initiative to do the same job through internal resources so as to save the money for the company.
In-Scope Petroleum products (HSD, PMG) Calculation of foam requirements Calculation of water requirements Calculation of GPM of fire pump Hydraulic Analysis based on NFPA requirements Estimated Time: Two month Estimated Cost: Approvals
DGM HSE GM Operations
Out-Scope
Project Management
Process Groups Knowledge Areas Initiating Process Group Planning Process Group Executing Process Group Monitoring & Controlling Process Group Closing Process Group Project Integration Management Project Charter Firefighting system design (Foam, Water, GPM, Hydraulic Analysis) Activity List & WBS Close Project Project Scope Management
Cost Management'!A1 On time project completion +- 10 allowable difference in calculation Project Organogram'!A1
Verify results from the consultant report Select Team Kick-off meeting Initial training & understanding Information / Report distribution
Stakeholder Register
Communication Plan'!A1
Risk Assessment'!A1
Activity List
Project Management Plan
Risk Management
Cost Management
Quality Management
Stakeholder Register
Sr. No. Stakeholders Priority Stakeholder interest in the project Handling products Responsible for the facility Overall responsible of the facilities Responsible for safe receipt, storage and dispatch of the product Responsible for execution of projects keeping all safety measures in consideration as recommended by consultant Owner of the facility Issue / renew explosive lisence on the basis of recommendations mentioned in the explosive rule 1 Oil Installation 4 Strategy to reduce impact Conduct preliminary Lack of awareness meeting and explain Lack of interest scope Demand chages as Periodic updation on per experience the status of the project Risk Lack of interest Very technical exercise Periodic updation on the status of the project Conduct preliminary meeting and explain scope Periodic updation on the status of the project Presentation in ManCom and seek approval Document to Report Draft Report Final Report
Operations Dept.
Final Report
Construction Dept.
Management Committee
Final Report
Explosive Dept.
Final Report
Activity List
Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Presentation to ManCom for concept approval Approval of the project charter Finalization of Project Team Kick-off meeting with stakeholders (internal) Liturature Review - NFPA codes, Explosive Lisence) Survey of the facility and data gathering Interview with Facility Inchage Measuring physical parameters of tank farm Developing fire lines layout Signing off the measurement and layout from Facility Incharge Developemnt of Calculation template for foam and water requirements and GPM of fire pump Conduct hydraulic analysis on Pipe flow expert
Activity List
Task Name
Presentation to ManCom for concept approval Approval of the project charter Finalization of Project Team Kick-off meeting with stakeholders (internal) Liturature Review - NFPA codes, Explosive Lisence) Survey of the facility and data gathering Interview with Facility Inchage Measuring physical parameters of tank farm Developing fire lines layout Signing off the measurement and layout from Facility Incharge Development of Calculation template for foam and water requirements and GPM of fire pump Conduct hydraulic analysis on Pipe flow expert Validate results from consultant report
Duration
Start
Finish
Predecessors
1 2 3 1,2,3,4
Resource Names
Project team leader DGM HSE,GM Construction,GM Operations Project team leader Project team leader Engineer HSE,Engineer Operations,Engineer Construction
15 days 7 days
Mon 11/21/11
Fri 12/9/11
Mon Tue 12/20/11 12/12/11 Mon Mon 1 day 12/12/11 12/12/11 Wed 2 days Tue 12/13/11 12/14/11 Mon 3 days Thu 12/15/11 12/19/11
5 7 8 9 10
Project team leader Project team Project team Facility Incharge,Project team leader Engineer Construction,Engineer HSE,Engineer Operations Engineer Construction,Engineer HSE,Engineer Operations Project team leader GM Construction,GM Operations,Engineer Construction,Project team leader,Engineer HSE,Engineer Operations Engineer Construction, Project team leader, Engineer HSE,Engineer Operations
12 13
11 11,12
14
7 days
13
15
14
Gantt Chart
Project Organogram
Sr. Executive
(HSE)
Sr. Engineer
(HSE)
Sr. Engineer
(Construction)
Sr. Engineer
(Operations)
Resource Management
WBS Element
Presentation to ManCom for concept approval Approval of the project charter Finalization of Project Team Kick-off meeting with stakeholders (internal)
Responsible HR
Services
Software
Powerpoint Lotus Notes MS Office MS Office
Hardware
PC Projector PC
Facilities
Board room
Communication Material
Email Telephone
Project Team Leader Deliver Presentation Project Team Leader Getting approvals Project Team Leader Project Team Leader Conduct Meeting
PC Projector
PC
Workstation
Measurement Project Team Leader Data gathering Project Team Interviews Layout design Project Team Leader Conduct Interview Project Team Measurements Project Team Project Team Leader Layout design
Email Telephone
Meeting
MS Office
PC
Workstation
Pipeflow expert PC
Workstation
NFPA Codes Copy of Explosive rules Consultant Report NFPA Codes Copy of Explosive rules Consultant Report Consultant Report
Communication Plan
Stakeholder Information Required
Justification of the project Benefits to the company Cost to the company Support and resources required
Information provider Form of information Mode of information provide Time of information provision
Management Committee
Powerpoint presentation
Consultant Report Tank and dyke wall data Pipeline and pump data Construction Dept. Fireline layout Draft Report Final Report Operations Dept. Draft Report Final Report Draft Report Final Report Visit Plan
Project Team Report Manager Operations Project Team Report Installation Manager
During site survey Issue of draft report Issues of final report During site survey Issue of draft report Issues of final report
Oil Installation
Risk Assessment
WBS Element Risk Probability Severity Risk Rating
3 6 3 0 2 2 2 2 3 2 3 3 6 4 6 6
Risk Status
Low Medium Low Low Medium
Existing Controls
Strong jestification with benefits to the company Timely submission of charter and follow-up Skills hunting before project initiation Make liteature available in advance
Change Control
Presentation to ManCom for concept approval Approval of the project charter Finalization of Project Team Kick-off meeting with stakeholders (internal) Liturature Review - NFPA codes, Explosive Lisence) Survey of the facility and data gathering Interview with Facility Inchage Measuring physical parameters of tank farm Developing fire lines layout Signing off the measurement and layout from Facility Incharge
Concept would be rejected Delay in approval Unavailability of required skills Unavailability of literaute Facility Incharge unavailable Human error Design Error
1 3 1
3 2 3
Low Medium Ask for Back-up in advance Medium Data validation by Faclity incharge Medium Validation through consultant report
3 3 3 2 3 3 3 2
0
9 9 9 4 0
Low
High High High Medium Low Validation through consultant report Validation through consultant report Reverse engineering approach, development of template and recalculation Timely submission of report and follow-up
Developemnt of Calculation template for foam and Calculation Error water requirements and GPM of fire pump Conduct hydraulic analysis on Pipe flow expert Validate results from consultant report Prepare draft report and submit for review Calculation Error Difference in calculation & design Delay in Review -
Change Management
Code Existing Issue Proposed Change Justification of Change Budget Impact Residual Risk Responsibility Schedule Resources