Académique Documents
Professionnel Documents
Culture Documents
Why Cables ?
Unlike
other components of power system such as Transformer, Circuit Breakers, Isolators etc. Cables are considered highly reliable. Cables installed more than 30 years are still found to be performing quite satisfactorily. Many cables have exceeded their anticipated life. This is basically due to inherent simplicity in their construction and application.
supply Longer life and low maintenance. Higher resistance to moisture, vibration and polluted atmosphere. Used for thickly populated areas.
linked Polyethylene Cable was developed to overcome the susceptibility of PILC cables to ingress of moisture. Polyethylene has the best dielectric properties, but poor thermal properties on account of its thermoplastic in comparison to impregnated paper, is cross linked by dry Nitrogen curing process to improve its thermomechanical properties without loss of electrical properties.
HT Network Parameter
Year 2002-03 2003-04 Cable Length (kms.) 894 1050 Cable Laid per year 125 207
1185 1268
1291
170 103
39
2005-06
2006-07
0
0
1
0
PILC
Single Core 20 D 25 D Multi Core 15 D 20 D
XLPE
Single Core 15 D Multi Core 12 D 20 D
HV commissioning.
DC
testing
before
laying. Prepare the cable route on T.P. Map. Co-ordination with other agencies for their existing network on the proposed cable route. In Torrent Power SEC Ltd. We had total 1291 K.M. of HT U/G Cable, supplying power to 2080 Nos. of 11KV distribution sub-station.
Handling of Cable
Cable drums or coil must not be droped or
thrown from truks/raiway wagon during unloading operation. The site chosen for storage of cable should be well-drained and should preferably have a concrete surface/firm surface. When for any reason, it is necessary to rewind a cable on to another drum, the barrel of the drum should have a diameter not less then that of the original drum.
Handling of Cable
The arrows painted on the flange of the
drum indicate the direction in which the drum should be rolled. The cable will unwind and become loose if the drum is rolled in the opposite direction. In no case should the drums be stored 'on the flat '; that is, with flange horizontal.
cables for fixed installation :PILC - 15 D XLPE - 12 D Where D = Overall diameter of Cable Maximum permissible tensile strength for cables
For cables pulled with stockins Armoured Cables - P = 9 D2 Unarmoured Cables - P = 5 D2 Where P = Pulling force in Newtons D = Outer diameter in mm.
For Cables pulled by pulling eye :- If the cables are pulled by gripping the conductor directly with pulling eye, max.permissible tensile strength depends on the material of the conductor and on their cross section.
board and barricade area for excavation of trench and stack of materials. Ensure trench bed consists of soft soil and free from projecting stones. Minimum depth should be maintained. Unwind cable along trench with the help of jack and roller. Lay cable in prepared trench with help of roller.
about 2 to 3 inches. Place half round muff on the cable. Backfill the cable trench by excavated soil of without stones in trench properly, ram it thoroughly. After completion of work remove all packing, waste material and dump in appropriate place.
the backfilled areas are level with ground surface. Record actual excavation dimensions, location, cable route and jointing details for future reference.
Trench Dimensions
Recommended
depths from the upper surface of the street pavement or ground to the cable axis. 46 to 76 cm (18 to 30 107 cm (42 in.) 180 cm (72 in.)
3.3 to 11 KV
in.) 22 to 33 KV 66 KV
power cable is laid in the proximity of communication cable, the minimum horizontal and vertical separation shall normally be 0.6 m ( or 2 ft. ), but in any case not less than 26 cm ( or 8 in. )for single core cable and 30 cm ( or 12 in. ) for multi core cable.
being carried out by engineers only. 2. Coordination with other utility is carried out before finalizing cable route. No trial pit is excavated for 11kv cable laying. 3. Detail drawing of the site including the cable route / joint details corresponding to the fixed landmarks is being prepared by the company draughtsman. 4. Repair arrangement of drainage/ Water pipe line is being done by the company.
Excavation Work
Continued.
Thank You