Académique Documents
Professionnel Documents
Culture Documents
Systems
A . K. Mukerjee
Chief Scientific Officer (Retired)
Centre for Energy Studies
Indian Institute of Technology,
Delhi
New Delhi – 110016.
A Typical PV System
Introduction
Power
LAMPS
DC LOAD
FANS,
etc.
PV ARRAY Conditioner
DIODE R
AC LOAD
E
BATTERY
T
R
E
V
IN GRID
Construction of PV Array
1. PV Array consists of several
Modules
2. Single, polycrystalline or
amorphous
silicon
3. Packing Factor
Losses
1. The transmission of the radiation is
reduced because of reflection of
the protective glass sheet on top
and absorption in it, and
2. The packing factor. That is, the
entire area of the module is not
covered by the solar cells but there
are large gaps between the
adjacent solar cells.
Space Wasted by Round Solar
Cells
Suppose that the radius of the cells is r.
Then the total area required to place
four cells is:
At = (2r + 2r) X (2r+2r) = 4r X 4r =
16r2 …………..(1)
However, the area covered by the four
cells, the cell area, is:
4X (π r2) = 4 πr2.
Therefore, the ratio of the cell area to
the total area At, is:
4 πr2 /16r2 = π/4 = 0.7854.
Connection of Array
T1
R1 R2 R3 R4
A1 B1 C1 D1
S1
A2 B2 C2 D2
S2
A3 B3 C3 D3
S3
T2
VMPP
Battery charge/discharge
controller
Note: Temp. Comp. at B+ = 14.56 mV/C (16.13mV/C)
Float Charging = 14.5 V
1N 5822 Load disconn. = 11.5 V
F1 D1 Load Re-conn. = 12 V
B+ To L2
+ C1
100
2
D3 SW 25V
1N 5822 1A
1
D2
PV+
1N 5822
8K2 R18
1% R16 2M2
MTP 2955 E D7 to D14 R9 8K2
3 2 8 * 1N 4148 (8K2) R6
1% R12
10K
5K6
4
4
R4
3 5
+ + D10
V+
V+
3V3
3
R1 D4 D5 R2
1 U1A 2K2 U2B 7
OUT D8 LM324 OUT
22K LM324 R13
1
V-
R7
4K7 39K 39K D9 Green LED
R3
1N 4148
1N 4148
11
11
1% 1% C2
(Charging)
1
B- 1M R5 R10 R14
2K2 8K2 270 R17 0.01 1K8
R8 1K
PV-
C3
0.1
D13
LM 385 - 2.5V R22 Battery Low 3V3
D12 12K BC107A 3
22K D14 2 Q1
47K 0.1
11
R24
C4 RED 1
1K8
11
U3C 8
3
OUT R30 TO CT OF
LM324 U4D 14 1 2 TRANSFORMER
10 LM324 OUT
+ R26 R25 SW BASE
2K2
V+
2 12 C7
4K7 + 1B WINDING
V+
2K7 0.01
4
R21
1
LAMPS
MPPT
FANS,
DC LOAD
etc.
PV ARRAY
CHARGE/
DISCHARGE
CONTROLLER
BATTERY
Assumptions
The following assumptions have been made:
The electrical efficiency of the circuit of the
MPPT = 90 %
The charge/discharge cycle efficiency of the
battery (assuming new ones) = 90 %
The diode is usually a built-in part of the MPPT
and therefore neglected. However it is
necessary to save the circuit from accidental
input voltage inversion.
Wiring and cabling will introduce another 5 %
loss.
Calculations
The energy requirement for 7 days will
be calculated below.
Power required = 1000 Watts
Therefore, energy needed for 7 days =
1000 W X 24 Hr X 7 days = 168,000
Watt – hours.
For an 8 hour sunlit day the energy
given directly to the load is:
1000 W X 8 Hr X 5 Days = 40,000 W –
Hr -------------------- A1
Since sunlight is available for only 5
days.
Calculations (Continued)
Hence, the rest of the energy must be
stored in and supplied by the battery
bank.
This energy is:
168,000 – 40,000 = 128,000 W – Hr
--------A2
Again, the charge – discharge efficiency
of the battery bank is 90 %. Therefore,
the energy supplied to the battery is:
128,000/0.9 = 142,222 W – Hr
-------------------A3
The size of the battery
bank
If the voltage of the battery bank is 108
Volts, as desired, then its charge is:
1, 42,222 W - Hr/108 V = 1316.87
Ampere – hours.-------- B1
Since it is assumed that the batteries
must retain 50 % of the charge after
discharge, their charge holding capacity
must be twice this value. That is:
Total charge = 1,316.87 X 2 = 2,633.75
A – Hr------------B2
Battery Sizing (Continued)
1. For 108 volts a string of 9 batteries, of
12 volts each, must be used.
2. The charge capacity of each battery
must be:
3. 2633.75 A - Hr/9 = 292.6 A –
Hr.-----------B3
4. In case 300 A - Hr batteries, which are
rare, are not available then two strings
of 9, 150 A – Hr ones may be connected
in parallel
Series – Parallel
Connection
CHARGE DISCHARGE
CONTROLLER CONTROLLER
D 1 D 2
D 4 TO LOAD
1
D 3 B T1 B T5
12
12
12 B T2 B T6
12
From B T3 B T7
MPPT
12
12
B T4 B T8
2
2
Diodes D1 , D2 ,D3 and D4
W – Hr -------------- B6
Dissipation in D3 & D4
Energy passing through D3 & D4 is:
1. 40,000 W – Hr +1, 42,222 W – Hr = 1,
82,222 W – Hr --------- B7
2. This energy is passed in:
8 hours X 5 days = 40 hours --------------
B8
3. Hence the power is: 1, 82,222 W –
Hr/40 Hr = 4,555.55 Watts -------------- B9
4. This amounts to: 4,555.55 W/108 V =
42 Amperes --------------- B10
Power loss in D3 & D4
(Continued)
1. The voltage drop across the
diodes is 0.7 Volts.
2. Therefore the power dissipated in
D3 and D4 is: 42 A X 0.7 V =
29.53 Watts
3. Therefore energy consumed is:
29.53 W X (8 Hours X 5 days) =
1181 W – Hr --------------- B11
Total Array Energy
1. Thus the energy consumed by the four
diodes is:
1,142.4 W – Hr + 1,181 W – Hr =
2,323.4 W – Hr ------------------ B12
2. This must be supplied by the PV array.
Therefore the total array energy rises
to:
40,000 W – Hr +1, 42,222 W – Hr +
2,323.4 W - Hr = 1, 84,545.4 Watt –
hours -----B13
Total Array Energy
(Contd.)
1. This energy is given by the MPPT
which itself has an efficiency of 90
%. Hence the energy delivered at
the input of the MPPT from the
array is:
1,84,545.4/0.9 = 2, 05,050.44
E2
(PT)(PTF)(η)
Where now LPD is the pumping
in meters.
Pumping Time Factor
Use of an MPPT in the system
normally increases the daily
volume pumped by an additional
20%. Hence, a reasonable default
value for PTF when a MPPT is used
is 1.2 if the pump is connected
directly to the PV array, then the
PTF will be 1.0.
Pump Efficiency
The wire-to-water efficiency, η, will
be specified by the pump
manufacturer. For fractional
horsepower pumps, it is typically
about 25% while larger pumps will
be more efficient.
Numerical
Numerical:
Specification for pumping system:
Volume of water to be lifted = 2000
gallons/day.
Water reservoir = 200 ft. underground
Worst case peak Sun day = 6 hrs.
PTF = 1
Peak Sun = 6 hrs.
Assume pump efficiency = 25%
Piping friction losses = 5%
Calculations
Therefore effective height = 200X 1.05
= 210 ft.
Substituting in equation E1, pump HP =
1.17. However, the service factor is 25%
for a 1HP motor which means that a 1
HP motor can operate at 1.25 HP
without any damage to itself.
1.17 HP = 1.17 X 746W = 872.82 W.
Pump Operating DC Voltage = 96 V
Solar Array Calculations
Since this is the load, the solar
array wattage can be calculated as
given in section C above. It is
important to notice that the use of
an MPPT in the system normally
increases the daily volume
pumped by an additional 20%.
Therefore, the final array size will
be less by 20%.
Design of a PV operated
Pump
Thank You