Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed to produce a product MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced Dependent demand drives MRP MRP is a software system
Finally, repeating the process for all components, we have the final materials requirements plan:
Day: A LT= B LT= C LT= D LT= E LT= Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement 1 2 3 4 5 6 7 8 9
10
A
B(4) D(2) E(1) D(3) C(2) F(2)
Total Unit Demand Day 10 50 A Day 8 20 B (Spares) Day 6 15 D (Spares)
First, the number of units of A are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of A on the 9th day to receive them on day 10.
Day: A Required Order Placem ent 1 2 3 4 5 6 7 8 9 50 10 50
LT = 1 day
Next, we need to start scheduling the components that make up A. In the case of component B we need 4 Bs for each A. Since we need 50 As, that means 200 Bs. And again, we back the schedule up for the necessary 2 days of lead time.
Day: A B R e q u ire d O rd e r P la c e m e n t R e q u ire d O rd e r P la c e m e n t 20 200 20 50 200 1 2 3 4 5 6 7 8 9 10 50
Spares
4x50=200
Finally, repeating the process for all components, we have the final materials requirements plan:
Day: A LT=1 B LT=2 C LT=1 D LT=3 E LT=4 F LT=1 Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement 1 2 3 4 5 6 7 8 9 50 200 100 55 55 20 200 200 200 400 300 20 200 400 100 300 10 50
20 20 200
A
Part D: Day 6
C(2) F(2)
40 + 15 spares
plan specifying how many and when the firm plans to build each end item
Frozen
Moderately Firm
Specific changes allowed within product groups as long as parts are available
Flexible
Significant variation allowed as long as overall capacity requirements remain at the same
levels
10
Flexible
Forecast and available capacity
15 Weeks
26
11
Creates schedules identifying the specific parts and materials required to produce end items Determines exact unit numbers needed
Determines the dates when orders for those materials should be released, based on lead times
12
Inventory transactions
Secondary reports
Primary reports Planned order schedule for inventory and production control Exception reports Planning reports Reports for performance control
13
Production sequence
Modular BOM
Subassemblies
Super BOM
Fractional options
14
Pegging
15
16
17
Requirements
Scheduled
Projected Net
receipts
available balance
Planned Planned
18
MRP Example
X A(2) C(3) C(2) B(1) D(5)
Item X A B C D On-Hand Lead Time (Weeks) 50 2 75 3 25 1 10 2 20 2
19
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10
X LT= Onhand A LT= Onhand B LT= Onhand C LT= Onhand D LT= Onhand
20
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10 95 50 45 45
X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20
50 50
50
50
50
50
50
50
50
A(2)
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
21
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10 95 50 45 45
X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20
50 50
50
50
50
50
50
50
50
A(2)
B(1)
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
22
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10 95 50 45 45
X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20
50 50
50
50
50
50
50
50
50
A(2)
B(1)
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
C(3)
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
23
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10 95 50 45 45
X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20
50 50
50
50
50
50
50
50
50
A(2)
B(1)
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
C(3)
C(2)
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
24
Day: Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10 95 50 45 45
X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20
50 50
50
50
50
50
50
50
50
A(2)
B(1)
45 90 75 75 75 75 75 75 75 75 15 15 45 25 25 25 25 25 25 25 25 20 20
15
C(3)
C(2)
D(5)
45 10 10 10 10 10 35 35 40
20 40
40 40 100
35
20 20
20
20
20
20
20 80 80
80
25
No Feedback Realistic?
Feedback
Yes
Execute: Capacity Plans Material Plans
26
Goal: Plan and monitor all resources of a manufacturing firm (closed loop):
manufacturing
marketing
finance engineering
27
(L4L)