0 évaluation0% ont trouvé ce document utile (0 vote)
1K vues43 pages
These are very large sized projects, approximately 4000 MW each involving an estimated investment of about Rs. 16,000 crore. These projects will meet the power needs of a number of States/ distribution companies
located in these States, and are being developed on a Build, Own, and Operate (BOO) basis. In view of the fact that promotion of competition is one of the key objectives of the Electricity Act, 2003, and of the legal provisions regarding procurement of electricity by distribution companies, identification of the project developer for these projects is being done on the basis of tariff based competitive bidding. Guidelines for determination of tariff for procurement of power by distribution licencees have been notified in January 2005 under the provisions of the Electricity Act, 2003. The Power Finance Corporation (PFC), a PSU under the Ministry of Power, has been identified as the nodal agency for this initiative.
These are very large sized projects, approximately 4000 MW each involving an estimated investment of about Rs. 16,000 crore. These projects will meet the power needs of a number of States/ distribution companies
located in these States, and are being developed on a Build, Own, and Operate (BOO) basis. In view of the fact that promotion of competition is one of the key objectives of the Electricity Act, 2003, and of the legal provisions regarding procurement of electricity by distribution companies, identification of the project developer for these projects is being done on the basis of tariff based competitive bidding. Guidelines for determination of tariff for procurement of power by distribution licencees have been notified in January 2005 under the provisions of the Electricity Act, 2003. The Power Finance Corporation (PFC), a PSU under the Ministry of Power, has been identified as the nodal agency for this initiative.
Droits d'auteur :
Attribution Non-Commercial (BY-NC)
Formats disponibles
Téléchargez comme PPT, PDF, TXT ou lisez en ligne sur Scribd
These are very large sized projects, approximately 4000 MW each involving an estimated investment of about Rs. 16,000 crore. These projects will meet the power needs of a number of States/ distribution companies
located in these States, and are being developed on a Build, Own, and Operate (BOO) basis. In view of the fact that promotion of competition is one of the key objectives of the Electricity Act, 2003, and of the legal provisions regarding procurement of electricity by distribution companies, identification of the project developer for these projects is being done on the basis of tariff based competitive bidding. Guidelines for determination of tariff for procurement of power by distribution licencees have been notified in January 2005 under the provisions of the Electricity Act, 2003. The Power Finance Corporation (PFC), a PSU under the Ministry of Power, has been identified as the nodal agency for this initiative.
Droits d'auteur :
Attribution Non-Commercial (BY-NC)
Formats disponibles
Téléchargez comme PPT, PDF, TXT ou lisez en ligne sur Scribd
• ERCs to adopt the tariff through transparent process of
bidding • Moving away from cost plus approach • Encourage private sector investment Guidelines for tariff based competitive bidding
• Guidelines for competitive bidding for tariff determination
– notification of 19th January, 2005.
• Objectives - promoting competitive procurement,
facilitating transparency and fairness, reducing information asymmetry, protecting and providing flexibility to suppliers on availability of power while ensuring certainty on tariffs for buyers. Provisions of the National Electricity Policy
• The aims and objectives - supply of reliable and quality
power of specified standard in an efficient manner and at reasonable rates and protection of consumer interests
• Competition to bring benefits to consumers, competition
to determine the price Provisions of Electricity Tariff Policy
• Objective - to promote competition, efficiency in
operations, improvement in quality of supply, ensure availability of electricity to consumers at reasonable and competitive rates.. • Introducing competition in different segments of the industry leading to benefits to consumers through reduction in capital costs and also efficiency of operations. • Price to be determined competitively. Provisions of Electricity Tariff Policy
• All future requirement of power to be procured
competitively by distribution licensees, except in cases of expansion of existing projects or where there is a State controlled / owned company as an identified developer and where regulators will need to resort to tariff determination based on norms.
• Even PSUs will have to bid for projects for determination
of tariff, after a period of 5 years Launch of Ultra Mega Projects through tariff based competitive bidding
• Desired capacity addition of 100,000 MW by 2012
• Capacity addition not feasible from the ongoing and proposed new projects already identified. • Need to develop large capacity projects at the national level to meet the requirements of a number of states • Thrust to development of projects through competitive bidding. • Ultra Mega Power Projects – to reduce power shortage Launch of Ultra Mega Projects through tariff based competitive bidding
• Economies of scale leads to cheaper power through
development of large size power projects using latest technologies. • Ministry of Power, CEA and Power Finance Corporation working in tandem for development of five projects under tariff based competitive bidding route. • The Ultra Mega Power Projects - each with a capacity of minimum 4,000 MW, scope for expansion. Launch of Ultra Mega Projects through tariff based competitive bidding
• Meet the power needs of a number of states through
regional and national grids.
• To enhance investor confidence, reduce risk perception
and get good response to competitive bidding, necessary to provide the site, fuel linkage in captive mining blocks, water and obtain environment and forests clearance, substantial progress on land acquisition leading to possession of land, through a Shell Company. Launch of Ultra Mega Projects through tariff based competitive bidding
• UMPPs developed on a Build, Own, and Operate (BOO)
basis. • PFC under the Ministry of Power, nodal agency • Shell companies to be responsible for tying up necessary inputs from the likely buyers of power and tying up of power off takes from these projects with appropriate terms and conditions and Payment Security Mechanism Role of Ministry of Power
Ministry of Power - facilitator and co-ordinate with Ministry/
Agencies for ensuring:
– Coal Block Allotment/ Coal Linkage
– Environment/ Forest clearances
– Required support from State Govt. Agencies
Role of Ministry of Power
• Coordinate with Financial Institutions towards financial
closure.
• To facilitate PPA and proper payment security
mechanism - with State Govt./ State utilities
• Monitoring the progress of shell companies w.r.t
predetermined timelines. Selection of sites
Criteria for selection of sites:
– Pit head location with domestic coal,
– Coastal location with imported coal, – Coastal location with domestic/blended coal,
Through a preliminary scrutiny by CEA of a number of potential
sites identified in the country. UMP Projects identified
Two pit head and three coastal locations, for
setting up Shell companies by PFC
– Sasan Power Limited (M.P.)
– Akaltara Power Limited (Coastal Gujarat)
– Coastal Gujarat Power Limited
– Coastal Karnataka Power Limited
– Maharashtra Ultra Mega Power Project Co.
Functions of the Shell Companies
To facilitate following activities
• Preparation of project report
• Land acquisition • Allocation of fuel linkages/coal blocks. • Allocation of water by the state Govt. • Appointment of consultants for EIA & Project Report Functions of the Shell Companies
• Appointment of consultants for International Competitive
Bidding (ICB), document preparation & evaluation.
• Various approvals and statutory clearances.
• Off-take/sale of power – section 63 of EA2003 provision.
Functions of the Shell Companies
• Power Evacuation/ (Transmission) System.
• Rating of Projects
• PFC appointed the Technical Consultants, for
conducting studies and prepare bankable Project Report, through a competitive bid process. Payment security mechanism
• Revolving Letter of Credit by distribution licensees;
• Escrow account establishing irrevocable claims of
receivables of distribution utility
• In a likely event of any default, direct supply to HT
consumers or any other more credible distribution licensees . Funds requirement
• UMPPs entail investments of Rs. 15,000 crores for each
project
• For good and credible developers and power projects
offering less expensive power, debt funding no constraint
• FIs involved at various stages including the final
evaluation of the bids, for updating them
• Development through large private business groups, on
their own or through consortiums with parties and agencies from outside Discussions with Heads of Financial Institutions • To elicit support meeting of Heads of Financial Institutions – SBI, LIC, IDBI, HDFC/IDFC, ICICI, PFC,
• Points for consideration
• F.I. representation in Pre-Qualification Committee
• Rating of Green Field Projects for better terms of funding • Publicize globally • The proposed payment security mechanism is adequate Discussions with Heads of Financial Institutions
• Involvement of F.I. in selection of Consultant for Project
Report
• Activating Bond Market
• Access ECB (Present limit to be liberalized)
• 20 year debt tenure [12+8 (LIC)]
• Attracting Venture Capital
Short listed eleven technical consultants
• WAPCOS
• TCE Engineers Consulting Ltd.
• DCPL Development Consultant Pvt. Ltd.
• Lahmeyer International Pvt. Ltd.
• L&T Sargent & Lundy Ltd.
• NTPC Ltd. Short listed eleven technical consultants
• Fitcher Consulting Engineers
• Desien Pvt. Ltd.
• Macon Pvt. Ltd.
• Tractebel Engineers & Contractor Pvt. Ltd.
• STEAG Encotec (Germany)
• Desien Pvt. Ltd. -
Discussions with Top Industry Leaders
• There should be full State Govt. support so that
facilitation like land acquisition, water availability etc, consent of State Pollution Control Board etc. are available to Shell Companies/Project Developers.
• Since these are large projects, each involving a capital
expenditure of the order of Rs.15,000 crores, the sectoral capping and the group capping for the purpose of debt financing, as notified by the RBI, will need to be revisited and properly enhanced. Discussions with Top Industry Leaders
• Proposed Debt : equity ratio of 70 : 30 to be revisited,
proportion of debt could be enhanced.
• Ministry of Power to ensure that power evacuation and
transmission system is put in place in time and there should also be sufficient redundancy in the system, so that the advantages of Open Access in transmission and distribution are fully availed of. Discussions with Top Industry Leaders
• It is good that the pit-head power stations are being
provided captive coal blocks rather than linkage.
• The criteria for evaluation of bids to be formulated by
Shell Company on the basis of advice of consultants to avoid ambiguity, after pre-qualification, the commercial consideration like tariff to be the sole criterion for selection.
• Long Term debt and take out financing would be useful
and render better tariff.
• 80 1A benefit under Income Tax Act should be extended
Support of State Governments
• State’s role - ensuring water, land at reasonable price ,
environment clearance and coordination by the district administration at the time of visit by the prospective developers.
• State governments can participate in equity in these
projects, optional to the states. Support of State Governments
• Shell Companies, deal with sanctions, clearances, land
acquisition etc,
• Similarly, States that are likely buyers of power of these
plants, to evolve consensus and basic agreement regarding broad framework of the Power Purchase Agreement, with mutual rights and obligations properly structured therein. Salient features of Plant and Choice of Technology
• UMPPs to use Super Critical Technology to achieve
higher levels of fuel efficiency, saving of fuel and lower green-house gas emissions. • Flexibility in unit size subject to adoption of specified minimum Supercritical parameters. • Integrated power project with dedicated captive coal blocks for pithead projects. • Coastal projects to use imported coal. Bidding Process
• Two stage selection process - Request for Qualification
(RfQ) for qualifying criteria for selection of bidders, eligibility to participate in the second stage
• The second stage Request for Proposals (RfP) from
qualified bidders
• Evaluation of the response to the RfP, successful bidder
is identified on the basis of the lowest levelised tariff. Selection of Sites for Setting up of UMPPs
• Nine projects identified to be taken up, 4 at pithead and
5 at coastal locations. The nine sites for the UMPPs identified by the CEA in consultation with the States are as follows:-
– Five coastal sites at:- Mundra in Gujarat, Krishnapatnam in
Andhra Pradesh, Tadri in Karnataka, Girye in Maharashtra, and Cheyyur in Tamil Nadu. Selection of Sites for Setting up of UMPPs
• Four pithead sites at :- Sasan in Madhya Pradesh,
Tilaiya in Jharkhand, Sundergarh District in Orissa and Akaltara in Chhattisgarh, Marakana in Tamil Nadu, additional site at Ghataprabha in Belgaum District, in Karnataka.
• CEA examining the preliminary feasibility of these sites
for development of UMPPs. Role of the Ministry of Power
• Coordination among various Ministries/Agencies of the
Central Government, and State Governments/Agencies.
• Coordination with Central Ministries/Agencies for
ensuring: • Coal block allotment/coal linkage • Environment/forest clearances • Water linkage Role of the Ministry of Power
• Required support from State Governments and their
agencies:
• Working out allocation of power to different States
from UMPPs in consultation with the States. • Facilitating PPA and proper payment security mechanism with State Governments/State Utilities. • Monitoring the progress of Shell companies with respect to predetermined timelines. Concept of Special Purpose Vehicles (SPVs)
• As per competitive bidding guidelines issued
under the Electricity Act for procurement of power by distribution licencees. • Guidelines permit procurement of electricity by more than one distribution licencee (also known as a procurer) through a combined bid process, and in such a case the procurers shall have the option to conduct the bid process through an authorised representative. • . Concept of Special Purpose Vehicles (SPVs)
• The concept of “Authorised Representative” forms part of
the standard bidding documents (issued under the competitive bidding guidelines)
• Authorised representative is the corporate body
authorised by the procurers to carry out the bid process for the selection of the successful bidder on their behalf.
• Accordingly, PFC has set up separate SPVs for each of
the 9 UMPPs identified, as authorized representatives of the procurers (distribution companies of the power procuring States). These SPVs are 100% owned subsidiaries of PFC SPVs set up • Sasan Power Limited for project at Sasan, Madhya Pradesh. • Coastal Gujarat Power Limited for project at Mundra (Gujarat). • Coastal Karnataka Power Limited for project at Tadri, Karnataka. • Coastal Andhra Power Limited for project at Krishnapatnam, AP • Coastal Tamil Nadu Power Limited for the project at Cheyyur in TN The names of the SPVs • Coastal Maharashtra Mega Power Limited for the project at Girye, Maharashtra.
• Orissa Integrated Power Limited for the project in
Sundergarh District in Orissa.
• Jharkhand Integrated Power Limited for the project near
Tilaiya dam, in Jharkhand.
• Akaltara Power Limited for the project at Akaltara in
Chhattisgarh. SPV Composition
• The Boards chaired by a Director of the PFC; other
members - officials of PFC, and representatives of the distribution companies of the major power procuring States inducted on the Boards at the appropriate stage.
• On completion of the entire process for selection of the
project developer, the SPVs transferred to the selected bidders i.e. to the selected project developers. Role of SPVs
• Carry out various activities on behalf of the procurers.
• Completion of these activities prior to award of the project, to enhance the investor’s confidence, reduce risk perception and get a good response to the competitive bidding process. • Main activities undertaken by the SPVs – Appointment of Consultants to undertake preparation of Project Report, – preparation of Rapid Environment Impact Assessment Report etc. Role of SPVs
• Appointment of Consultants for International Competitive Bidding
(ICB), document preparation & evaluation
• Finalise RfQ/ RfP documents in consultation with States / bidders
• Carry out RfQ/ RfP process and award of project
• Acquisition of land for the project
• Obtaining Coal blocks for pit-head projects
Role of SPVs
• Getting clearance regarding allocation of water by the
State Govt. for pithead locations
• Approval for use of sea water from Maritime Board/ other
Govt. Agencies for coastal locations Role of SPVs
• Obtain clearance from the State Pollution Control Board,
initiate forest clearance etc. for the project and for the coal mines, environment and forest clearances from the Central Government.
• Obtaining geological reports/ other related data from