INVESTORS MEET

Redevelopment of 4 Bus Terminal Projects by Uttarakhand Transport Corporation

Presentaton outline

BACKGROUND PROJECT DETAILS FEATURES OF RFP FEATURES OF CONCESSION AGREEMENT

Project Details Background

UTC owns and operates more than 1000 buses on inter-state and intra-state routes serving the people of the state UTC aims for improving the infrastructure at the bus terminals and wishes to redevelop the following bus terminal/s on PPP:. Ramnagar (appr.2.8 4acres) Kashipur (appr. 3.3 acres) Rudrapur (app. 4.17 acres) Srinagar (appr 2.95 acres) Old bus terminal of Srinagar (~0.6 acre) would also form a part of the Project. to be developed as a commercial area with facility for boarding and alighting of the passengers

PROJECT DETAILS

Project Details
Status of Land : UTC owner
Bus terminals for up-gradation Kashipur Rudrapur Ramnagar Srinagar PPP On Develop, Operate, Maintain and Transfer UTC - Implementing Agency Concession Period 25 years including 2 years construction period Project Components Redevelopment of Bus Terminal Redevelopment of Bus Repair Workshop Development of Commercial Area for Cost Recovery

Land Details

Bus Terminals Workshop (in Acres) Bus Terminals (in Acres) Commercial (in Acres) Total Land (in Acres) % of Workshop % of Bus Terminals % of Commercial

Kashipur Srinagar Srinagar Old Rudrapur Ramnagar Total 0.99 1.66 0.65 3.3 30% 50% 20% 0.63 1.95 0.36 2.94 21% 66% 12% 0.6 0.6 0% 0% 100% 1.47 2.2 0.49 4.16 35% 53% 12% 0.63 2.05 0.16 2.84 22% 72% 6% 3.72 7.86 2.26 13.84 27% 57% 16%

Kashipur Location

The Project Site shall cover the area admeasuring approximately 3.3 acres and located at busy intersection in Kashipur and bound by:
Rudrapur Road on the North side Private commercial development on the East Side Property of the Railways on the South Side Railway line on the West Side

Kashipur (1/2)

Workshop

Bus Terminal

Kashipur (2/2)

Commercial

Ramnagar Location

The Project Site shall cover the area admeasuring approximately 2.84 acres located at Ramnagar and is bound by:
Land of the Forest Department on the North side Residential development on the East Side Residence development on the South Side Ranikhet Road on the West Side

10

Ramnagar

Bus Terminal Workshop

Commercial

11

Srinagar Location

The existing terminal building is located in the heart of town and is being used by only a limited number of buses. The new site is sandwiched between river Alkananda and NH

Srinagar Location

The new Project Site shall cover the area admeasuring approximately 2.95 acres located at new Srinagar and is bound by:
Industrial Training Institute (ITI) on the North side Badrinath Road on the East Side Street and Co-operative society on the South Side River Alaknanda on the West Side

13

Srinagar

Commercial
Bus Terminal Workshop

14

Rudrapur Location

The Project Site shall cover the area admeasuring approximately 4.17 acres located at Rudrapur and is bound by:
National Highway 87 on the North side State Highway on the East Side Local road on the South Side Local road towards Daryanagar on the West Side

15

Rudrapur

Commercial Bus Terminal

Workshop

16

Estimated CAPEX and OPEX


(in Rs Cr.) Capex Break Up Kashipur Srinagar Srinagar Old Rudrapur Ramnagar Total Workshops Bus Terminals Commercial Total Capex % of Workshop % of Bus Terminals % of Commercial IDC Total Project Cost PV of O&M Cost 2.59 2.35 1.02 5.96 43% 39% 17% 1.65 1.17 1.68 4.50 37% 26% 37% 1.68 1.68 0% 0% 100% 1.83 28.72 5.21
17

3.84 3.17 3.26 10.27 37% 31% 32%

1.65 1.57 1.27 4.49 37% 35% 28%

9.73 8.26 8.90 25.88 38% 28% 34%

Return

Years Project IRR Equity IRR

1-5 -25% 0%

1-10 7% 0%

1-15 14% 16%

1-20 16% 19%

1-25 17% 20%

1-30 17% 20%

18

SALIENT FEATURES OF RFP

19

Architectural Plan Preferred Bidder shall submit the Architectural Plan/s for each bus terminal prepared by a member of the Indian Institute of Architects or an equivalent institution outside India. Architectural Plan/s shall consist of the following :

Overall concept plan including landscaping Architectural Plan/s for each floor and specifically highlighting the Workshop and Bus terminal Facility. Area utilisation plan for Workshop, Bus terminal Facility and Commercial Area Implementation plan: The methodology should clearly demonstrate the compliance of the approach to be adopted by the Bidder for the implementation of the Project to the minimum specifications set out in the Draft Concession Agreement. Timelines for development: The Bidder shall indicate the activity

20

Project Facilities

Bus Bays and Bus Movement Area Bus Boarding/ Alighting Platform Seating in Passenger Movement Area Ticketing Counters Cloak Room Dormitories Drinking Water Public Conveniences Police Control Room Lighting Public Address System Generator Back-up Footpaths Petrol Pump Parking Area (open & basement) Fire fighting System , etc

21

Source of Revenue

Bus Entry fee Parking fee Lease rent from commercial Advertisement

22

Comparative user fee


In Rs

UTC Bus Entry Fee- Local Bus Entry Fee- Other State Vehicle Parking Night Bus Parking Dormitory Urinal 1 50

ISBT Delhi
50

ISBT Dehradun
50

Baijnath (HP)
20

Kanpur (UP)
10

Varanasi (UP) 20

50 5 100

70

50

100

100

NA 5 Free

NA Free

23

Traffic Assessment Result- Ramnagar


Population 47099 (2001)

Bus Operator
Rajasthan Transport Corporation Delhi Transport Corporation UP Roadways UTC Total

Bus Trips
2 6 8 59 75

Bus Bays
Boarding/ alighting 13

Idle Parking 8

24

Traffic Assessment Result- Rudrapur


Population - 88720 (2001)
Bus Operator Rajasthan Transport Corporation Bus Trips 1 Bus Bays Boarding/Alighting 16

Delhi Transport Corporation


UP Roadways Haryana Roadways Chandigargh Roadways UTC

13
48 27 5 298 Idle Parking 11

Total

392

25

Traffic Assessment Result- Kashipur


Population 186980 (2001)

Bus Operator
Chandigargh Roadways Delhi Transport Corporation

Bus Trips
3 1

Bus Bays
Boarding/Alighting 10

Haryana Roadways
HP Roadways UP Roadways UTC Grand Total

4
1 79 130 218
26

Idle Parking 4

Traffic Assessment Result- Srinagar


Population 894940 (2001) Bus Operator Chandigargh Roadways Delhi Transport Corporation HP Roadways UP Roadways UTC Total Bus Trips 10 10 50 3 60 133 Idle Parking 8 Bus Bays Boarding/Alighting 13

27

THANK YOU