Académique Documents
Professionnel Documents
Culture Documents
and Operation
SPP
Neighboring Country
Transmission
Transmission EGAT
MEA
Distribution
Distribution
PEA
06/10/09
Thailand
Generation
Transmission
Consumers
MEA/PEA
Distribution
Generation Operation Planning
Load Commissioning Maintenance Fuel Supply Irrigation
Fuel Cost
Forecast Plant Schedule Plan Requirement
Input
Constraints Output
Transmission System 3 Years
Constraints Operating Program
Fuel Supply
Agreement Daily Plan
Transmission System
Analysis
Transmission System Analysis
Sirikit 500 MW
THB-H 214 MW
Bhumipol 779.2 MW
SNR-H 720 MW
WN 2,031 MW
EPEC 350 MW
BPK 3,675 MW
Glow IPP 713 MW 132 kV HVAC Interconnection
TECO 700 MW Ratch
3,481 MW IPT 700 MW Rayong 1,232 MW
230 kV Transmission System
Generations
- Hydro
- Thermal
- Combined Cycle
- Gas Turbine
- HVDC
Energy Generation Fiscal Year
Coal 2003 Natural Gas
17.2% 66.2%
Renewable
Diesel Hydro 1.3% Malaysia
0.0% 6.4% 1.1%
Coal
20.0%
Gas
Fuel Oil 67.2%
4.1%
Installed Capacity (April 2007)
SPP Private producers
7.64% and import
EGAT Non-Hydro 40%
46.76%
IPP
30.24%
Imported
EGAT Installed EGAT Hydro 2.42%
Capacity 60% 12.94%
Combined Cycle
and Gas Turbines 52.3%
Thermal 31.5%
Transmission Lines
500 kV = 2,790 cct km
West
Gen. 5,257 MW Eastern
Load 2,380 MW Gen. 7,830 MW
Metropolitan Load 3,090 MW
Gen. 2,745 MW
Load 7,950 MW
Southern
Direction of
Gen. 1,721 MW
Load 1,640 MW Power Flow
Malaysia
Tie Line 350 MW
Load Center is in Central & Metropolitan Area
Peak Demand 24 April 2007
26,000 26,000
22,586.1 MW 24,000
24,000 Hydro
22,000 22,000
20,000 20,000
18,000 18,000
16,000 Thermal 16,000
14,000 14,000
12,000 Combine Cycle 12,000
10,000 10,000
8,000 8,000
6,000 6,000
IPP + Foreign
4,000 4,000
2,000 2,000
SPP & TNB 10 % 0
0
0 2 4 6 8 10 12 14 16 18 20 22 24
Time
Daily Load Curve
MW
22,000
4 May 06
26 April 05 21,064.3 MW
20,537 MW
21,000 30 March 04
19,325.8 MW
20,000
7 May 2003
18,121.4 MW
19,000
18,000
17,000
16,000
19,000
18,000
17,000
16,000
Weekday - Summer
15,000 Weekday - Winter
MW
11,000
10,000
1:00
4:00
6:00
8:00
10:00
12:00
13:00
14:00
15:00
17:00
19:00
21:00
23:00
0:00
2:00
3:00
5:00
7:00
9:00
11:00
16:00
18:00
20:00
22:00
0:00
Energy Statistic Year 2001 - 2005
480 140000
137,361.0 (+9.61%)
457.5 135000
125,318.79 (+7.35%)
Peak Energy (GWh)
412.5 125000
397.2 (+3.73%)
390 27 April 04 120000
382.9 (+10.0%)
7 May 03
116,743.45 (+7.71%)
367.5 115000
348.1 (+3.79%)
3 April 02
345 110000
108,389.24 (+5.06%)
335.4
322.5 24 April 01 105000
103,165.20
300 100000
2001 2002 2003 2004 2005
Year
Daily Power Generation Curve
21000
20000
MW
19000
18000
Peaking Load Generation
17000
16000
15000 Int. Load Generation
14000
13000
12000
11000
10000
9000
Base Load Generation
8000
7000
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (Hours)
MW
10000
11000
12000
13000
14000
15000
16000
17000
18000
1:00 19000
2:00
3:00
4:00
5:00
LoadDemand
6:00
7:00
8:00
9:00
10:00
11:00
SpinningReserve
12:00
13:00
14:00
Daily Reserve Capacity
15:00
16:00
17:00
StandbyReserve
18:00
19:00
20:00
21:00
22:00
23:00
0:00
Criteria of Power System Operation
Reliabilities (N-1)
• Securities
• Stabilities
• Constraints
Qualities
• Voltage
• Frequency
Least Cost Operation
Safety and Environmental Restriction
800
700
600
Spinning Reserve
500
MW400
300 800
200 700
100 600
0 500
1 2 3 4 5 6 7 8 9 10 MW400
Gen. SpinningReserve Unit Number 300
200
100
0
1 2 3 4 5 6 7 8 9 10
Gen. SpinningReserve Unit Number
Reserve Capacity Requirement
Reserve Type Time to Use Type of Plant Minimum Dispatcher
Requirement
0.5
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Normal
Restorative Alert
Emergency
National Control Center (NCC)
EGAT Control Centers
Northern Area
North Eastern Area
Control Center
Control Center (NEC)
(NAC)
Metropolitan Area
Control Center
(MCC)
Central Area
National Control Control Center
Center (NCC) (CAC)
500 kV
230 kV
Southern Area
Control Center
(SAC)
Power PT
Plants
T Generation
MAC
NCC
MEA
PEA
PEA CA Transmission
C NEC
PEA
SAC
PEA NAC
PEA
National Control Center (NCC)
• Generation Dispatch
• Main Grid System Security (500 kV & 230 kV)
• Frequency Control
• Voltage Control
• Switching Operation ( Supervision )
• Power Flow in main Transmission Line
• Power System Restoration ( Supervision )
• Co-operate with IPP, SPP, Neighboring
Country and Fuel Supplier (PTT)
• Manage Spinning Reserve
Regional Control Center (MAC,
CAC, NEC, SAC and NAC)
• Local Network Reliability
• Switching Operation ( Action )
• Local Network Restoration
• Voltage Control
• Power Flow in the own area
• Co-ordinate with PEA, MEA
• Substation Remote Control
Responsibility of Control Centers
National Control Center
Main Grid System Security
Generation Dispatch
Frequency Control Regional Control Centers
Voltage Control Local Network Reliability
Supervision of switching operation Local Generation Control
Monitor power flow Switching Operation
in the main grid Regional Voltage Control
Power System Restoration Regional Power Flow Control
Spinning Reserve management Regional Network Restoration
Co-ordinate with IPPs, SPPs, Co-ordinate with MEA/PEA
and Fuel Suppliers Substation Remote Control
Type of Communication networks
Emergency Plan
Blackout Restoration Procedure
Action plan for generation or gas shortage
Personnel of National Control Center
Shift in Charge
System Operator 1 System Operator 2
(Generation) (Switching)
• Generation Dispatch • Switching operation that
• Control Frequency involved power plants
• Control Voltage • Issue dispatch documents
• Manage water release for IPPs, SPPs
• Fuel Management • Network Monitoring
System Operator 3
(Data and Reports)
• Summarize amount Generation and Demand
• Summarize events in the system
• Update Log book
Frequency Control
Demand
Generation
50.0
51 0 49
Spinning Reserve
Voltage Control
+10%
+ 8%
- 8%
Emergency
-10% Condition
Tools for Voltage Control
C-Bank
C-Bank
C-Bank
Operation - Emergency Condition
Tripping of main transmission lines, Gen. unit, SVC causing
shortage of reactive sources and low voltage.
In severe case may lead to voltage collapse.
Voltage deviation is allowed at +/- 10% while bringing the
system back to normal state.
Special Protection Scheme (i.e. Load Shedding scheme) in
critical areas to prevent cascaded tripping of other lines or
equipments.
During the period of Generation shortage
• Reduce voltage in distribution network to reduce total system
load
System Control and Supporting Functions
Operational Investment
Planning Planning
Emergency Protection
Prevention Plan System
Power System
System
Control Control Centers
Restoration Plan Computer
Grid Code
System Interconnection Agreement (HVDC SIA
between EGAT-TNB)
HVDC Supplementary Agreement (Bulk Energy
Purchase)
Power Purchase Agreement (PPA)
Independent Power Producers (IPPs)
Small Power Producers (SPPs)
EGAT Power Plants
Power System Study
Northern
region NorthNorth
Eastern
Northern area Control Center
regionarea
Eastern
Control
Central region Center
Central area Control Center Metropolitan
area area Control Cen
Metropolitan
Sub-station
20-30 %
Sub-station
4. Supply to load approx. 20-30 % to
reduce voltage and damp then system
Sub
Sub
Sub
Sub
Sub
Sub
Sub
Blackout Restoration
North
BB-H, SK-H Northeast
UB-H, SRD-H,
LTK-H
Central
Metropolitan East
Rayong
West
SNR-H, VRK
Estimated Restoration
South time is 4 hours
RPB-H, BLG-H
Summary of Restoration time VS load recover after Blackout
30 minute (4.5%
%)
1:00 hr 11.9%