PREPARED BY : KMASZ
QUESTION 1
Chainage , m Cut volume (m3) Fill volume (m3) Corrected volume (+ 10 % shrinkage) (+) CUT Cumulative volumes,m3
(-) FILL
0 100 200 300 400 480 500 600 700 800 900 1000 1100 1200
0 + 290 + 760 1680 620 120 -20 -110 -350 -600 -780 -690 -400 -120
0 290 1050 2730 3350 3470 3450 3340 2990 2390 1610 920 520 400
QUESTION 2
Chainage (m) Volume of cutt (m )
3
Volume of fill (m )
Corrected volume
Cumulative volume 3 (m )
(1)
(2)
(3)
(4)
(5)= (3)+(4)
0 13000 22500 7500 -5250 -16375 -20375 30500 93250 163250 229500
0 13000 35500 43000 37750 21375 1000 31500 124750 288000 517500
QUESTION 3
Agregate volume for setting out circular curves proposed as follows:
Chainage , m 0 100 200 300 400 480 500 600 700 800 900 1000 1100 1200
Cumulative volumes,m3 0 290 1050 2730 3350 3470 3450 3340 2990 2390 1610 920 520 400
From the data, draw a mass haul diagram using the scale below:
X axis : 1 cm = 100 m Y axis: 1 cm = 250 m3
Analysis of MHD; Given Freehaul distance is 600 m , Balance line at 400 m3 of aggregate volume.
Estimate of freehaul, haul and overhaul.
STEP 1
Draw a MHD using the scale below:
Y axis: 1 cm = 250 m3
Cumulative volume m3
STEP 2
Given Freehaul distance is 600 m, Balance line at 400 m3 of cumulative volume.
Cumulative volume m3
Freehaul line 6 cm
Balance line
Chainage ,m Measuring freehaul line = 6 cm
Cumulative volume m3
Axis y; Measurement line = 6 cm Freehaul volume = 6cm x 250 m3 = 1500 m3 Freehaul distance = 600m (given) E F Axis x; Measurement line = 6 cm Freehaul distance = 6cm x 100 m = 600 m
Chainage ,m
Freehaul = Freehaul volume x freehaul distance stn.m 100 Freehaul = 1500 x 600 = 9000 stn.m 100
Cumulative volume m3 A
Axis y; Measurement line AB = 12.3 cm Haul volume = 12.3cm x 250 m3 = 3075 m3 E F haul distance = 6.1 cm x 100 m Axis x; Measurement line EF = 6.1 Average cm = 610 m
Haul = Haul volume x average haul distance stn.m 100 Haul = 3075 x 610 = 18757.5 stn.m 100
Cumulative volume m3
STEP 5
determine overhaul
How to determine average over haul distance???
Average overhaul distance = Line AB /2 = 6.3 / 2 = 3.15 At the point line parallel with axis-x = Line EF A Axis y; Measurement line AB = 6.3 cm Overhaul volume = 6.3cm x 250 m3 = 1575 m3 F Axis x; Measurement line EF = 7.5 cm
Average overhaul distance = 7.5 cm x 100 m = 750 m
Chainage ,m
= 2362.5 stn.m
QUESTION 4
Distance HAUL FREEHAUL OVERHAUL Volume HAUL FREEHAUL OVERHAUL WASTE HAUL FREEHAUL 4.4cm x 10000 0.8 cm x 10000 3.6 cm x 10000 13 cm x 10000 44000 x 280 100 8000 x 200 100
36000 x (300-200) 100
Cumulative volume m3
5.6cm X 50 4 cm x 50 6 cm x 50
OVERHAUL
36000 Stn. m
QUESTION 5
Cumulative volume m3
Chainage ,m
Distance FREEHAUL OVERHAUL FREEHAUL OVERHAUL 4 cm x 50 4.9 cm x 50 4 cm x 50 7.2 cm x 50 200 m 245 m 200 m 360 m
Volume FREEHAUL OVERHAUL FREEHAUL OVERHAUL 4.4 cm x 5000 3.6 cm x 5000 2 cm x 5000 4.3 cm x 5000 22 000m3 18 000m3 10 000m3 21 500m3
BORROW
4.5 cm x 5000
22 500m3
TOTAL COST OF EARTHWORK Freehaul prices in freehaul distance = freehaul volume x freehaul distance x freehaul prices = (22 000 + 10 000) x 200 x RM1.25/200 = RM 40 000 = overhaul volume x freehaul distance x freehaul prices = (18 000 + 21 500) x 200 x RM1.25/200 = RM 49 375 = overhaul volume x (average overhaul distance freehaul distance) x overhaul prices = [(18 000 x (245 200) x (RM1.25 + RM0.40)/100) + (21 500x (360 200) x (RM1.25 + RM0.40)/100)] =RM 70 125 = borrow volume x borrow prices = 22500 x RM 0.75 = RM 16 875
Borrow prices
= RM 176 375