METHOD STATEMENT FOR CONCRETE WORKS

1. Materials 1) Cement 2) Sand 3) Aggregates (Metal) 4) Water 5) Admixtures


1.1 Consumable materials (All details to be in appendix) a. Admixture b. Accelerator c. Super plasticizers d. Air entrained 2. Tools and Machineries I). Mason trowel II). Masonry level bar

III).

Power trowel

IV). Finishing trowel

V). Poker & vibrator sets

VI).

Mortar span

VII).

Pump car

VIII). Truck mixture

IX). Concrete mixture

X).Boom truck

XI). Air compressor machine

XII). Crane (bucket method)

XIII). Fork lift machine

XIV). Dumper & wheel barrow

4.

Work norms Pump machine 18m3/hr [3M+4L] Crane & bucket method 12m3/hr [3M+4L] Manual mixing & pouring - 2.5m3/hr [3M+4L] For successful execution of the work following selection shall be communicated Survey gang check the concrete leveling Materials suppliers with store keeper to maintain adequate stock Concrete gang with concrete foreman mixing ,pouring, compacting & leveling the concrete Q/A/,Q/C Engineer check the concrete mixes

5.

QA/QC CHECK SHEET FOR CONCRETE WORK


Date Building/Structure Name Location (floor/grid) : .. :

1. PREPARATION i) Casting method ii) Equipment a). b). c). Pump Car/Crane Piping for pumping concrete/Hopper Vibrator/Hammer Stand-by vibrator d). e). f). Level machine/Staff Hoe/trowel/level bar Lighting for night time work : OK : OK : OK : OK : OK : OK : OK : OK : NO . : NO . : NO . : NO . : NO . : NO : NO . : NO . Pump car with piping Crane and hopper

iii) Temporary access/plat form iv) v) Cleaning inside form Watering to form surface

2) BATCHING & DELIVERY a) Delivery sheet (copy of sheet annexed) b) Nominal strength c) Designed slump : OK : OK : OK : OK : OK : NO : NO . : NO ... : NO : NO .

d) Max size of coarse aggregate e) Type of cement

Prepared by Sub-Con

Checked by

Approved by Engineer

QA/QC CHECK SHEET FOR CONCRETE WORK


Date Building/Structure Name Location (floor/grid) : .. :

3)

CASTING i) Slump test 01 Slump test 02 Slump test 03 Slump test 04 ii) Test Cube Lot 01 ( 9 cubes) Lot 02 (9 cubes) Lot 03 (9 cubes) iii) Pouring/Compaction a) Compaction by vibrator b) Compaction by hummer Iv) Level & Finishing a) Level @2m interval : OK : NO : OK : OK : NO . : NO .. : OK : OK : OK : : NO .. NO .. : OK : Ok : Ok : N O .. : NO ..... : NO

: NO

Prepared by Sub-Con

Checked by

Approved by Engineer

6. Ref A 1 2 3 4

Rate Breakdown Description Concrete Gr 35(water) Material Cement Admixture Sand Metal 4.5% wastage Total material Mixing Mason Mixing labour Cutting labour Batching plant labour Laying Mason Concrete labour Machinery Total Cost per m3 Concrete Gr 30 Material Cement Admixture Sand Metal 4.5% wastage Total material Mixing Mason Mixing labour Cutting labour Batching plant labour

Qnt

Unit

Rate

Amount

0.508 0.508 1.705 1.057

Mt Mt MT Mt

5 6 7 8

0.350 1.060 0.100

No No No Lot

9 10 11

0.530 0.530

No No Lot

B 1 2 3 4

0.470 0.470 0.750 1.036

Mt Mt MT Mt

5 6 7 8

0.350 1.060 0.100

No No No Lot

9 10 11

Laying Mason Concrete labour Machinery Total Cost per m3

0.530 0.530

No No Lot

Ref C 1 2 3 4

Description Concrete Gr 25 Material Cement Admixture Sand Metal 4.5% wastage Total material Mixing Mason Mixing labour Cutting labour Batching plant labour Laying Mason Concrete labour Machinery Total Cost per m3 Concrete Gr 20 Material Cement Admixture Sand Metal 4.5% wastage Total material Mixing Mason Mixing labour Cutting labour Batching plant labour

Qnt

Unit

Rate

Amount

0.422 0.422 0.803 1.021

Mt Mt MT Mt

5 6 7 8

0.350 1.060 0.100

No No No Lot

9 10 11

0.530 0.530

No No Lot

D 1 2 3 4

0.378 0.378 0.855 1.004

Mt Mt MT Mt

5 6 7 8

0.350 1.060 0.100

No No No Lot

9 10 11

Laying Mason Concrete labour Machinery Total Cost per m3

0.530 0.530

No No Lot

Ref` E 1 2 3 4

Description Concrete Gr 15 Material Cement Admixture Sand Metal 4.5% wastage Total material Mixing Mason Mixing labour Cutting labour Batching plant labour Laying Mason Concrete labour Machinery Total Cost per m3

Qnt

Unit

Rate

Amount

0.275 0.275 0.855 1.004

Mt Mt MT Mt

5 6 7 8

0.350 1.060 0.100

No No No Lot

9 10 11

0.530 0.530

No No Lot

7.

Calculation Calculation relative to concrete volume Concrete Volume = Length (x) Width (x) Height (m3)
Reduction = Steel Volume (Nearly 0.5% to 2.5%of concrete volume) Addition = Yield Volume (can be find during the Trail mixing test) Addition = 0.25 m3 for pump car wastage

8.

Procedure for concrete work 1). Mix design trial mix Mix proportion of concrete shall be designed for each grade of concrete specified in the technical specification and trial mix shall be carried out for each mix design. (pl . see trail mix Method statement)

a.

b.

Quality of following materials used for concrete shall be checked by testing or manufacturers certificate in order to assure the quality of concrete. Cement Coarse aggregates Fine aggregates Water Admixture Compressive strength test for each trial mix shall be carried out at following curing days. At 7 days At 28 days

c.

Reports of tests mentioned above shall be submitted to Engineer, and each mix design shall be approved by Engineer prior to concrete work.

2). Preparation a. Concreting plan. Method and procedure of concreting shall be planned prior to concrete casting in consideration of following items.(see attached example drawing) Method of casting (pump or crane w/hopper) Layout of pump car & piping, or crane Required concrete volume per hour Casting sequence or layout with quantity Temporary access or platform for concrete place

b.

Following equipment shall be prepared in stand-by condition prior to casting concrete. Pump car & piping , or crane & hopper Vibrator and other tools for concrete compaction Tools for concrete pouting such as hoe/level/bar/ trowel/Power travel machine Level machine & staff Lighting for night time work

c.

Temporary access/plat form for casting concrete shall be provided prior to casting concrete.

d.

Inside form shall be thoroughly cleaned by pressured air prior to casting concrete.
Watering to form surface shall be carried out prior to casting concrete. When using pump car in order to cast concrete, the motor (cement : sand = 1:1) can be used for initial pumping purpose. So we have to prepare that mixture at least in one bags Batching & delivery Ready mix concrete shall be batching plant and delivered to site by truck mixer with delivery sheet. Following items mentioned in delivery sheet shall be checked at site. Time of departure (Concrete shall be cast within three hours after the time of departure) Nominal strength Designed Max . size of coarse aggregate Type of cement

e.

f.

3)

4) a.

Casting Slump test shall be carried out at the commencement of casting and for each 100 m3 of concrete (this volume can varied with specification ).Acceptable slump shall be _+ 2.5 cm of designed slump. Test cube for compressive strength test One set test cubes shall be prepared for each 30 m3 of concrete and at least one set on each day. A set of test cubes shall consist of 9nos. of test cube.(3 nos. For 7 day test , 3 nos. For 28 days test and 3 nos. for form removal)

b.

c.

Pouring & Compaction Pouring shall be carried out by taking care of following items. Concrete shall not be poured from high place that causes segregation .(Height not more than 1.5m ,If exceed put pocket or connect trimly pipe to pump car) Concrete shall not be poured at one place intensively. Concrete shall be poured layer by layer with proper compaction.

d.

Compaction shall be carried out by taking care of following items.


Compaction must be done as concrete placed, Put the poker into the concrete QUICKLY. Take the poker out very SLOWLY otherwise a hole, or weak spot , may be left in the concrete.

Always compact in a definite pattern so the radius of action overlap and covers the whole area of the concrete. The poker should be long enough to reach and enter into the layers of concrete under the one being compacted. Never touch the form with the poker as it can damage the formwork and alignment. Never touch the reinforcement with the poker.

Never spread or move concrete sideways with the poker, always use a shovel. Never leave the poker running when not in use.

For concrete of average workability( i.e.. Slump of 80 mm) with a poker size between 25-75 mm, concrete should usually be vibrated for between 5 and 15 seconds. It worse to UNDER - VIBRATE than to OVERVIBRATE concrete.

e.

Level & Finishing Level of concrete shall be checked by level machine at 2m interval. Surface finishing shall be carried out as per architectural requirement. No final finishing can begin until the bleed water has dried up. Mixing bleed water with the surface paste will weaken it , possibly resulting in a dusty surface. Excess bleed water can be removed by dragging an ordinary garden hose across the surface of the concrete. Never try to dry up the bleed water using stone dust or cement as this will weaken the concrete surface in the long run.

Floating can be done by hand or with a power float.

Submit QA/QC check sheet to main contractor 5) Curing Curing is done just after finishing the concrete surface ,as soon as it will not be damaged. The simplest method of APPLYING WATER is to put a continuous fine, misty spray of water over the concrete . The spray must be a very fine mist or else it will damage the surface of the concrete.

Another way of curing is, cover with PLASTIC SHEET or GUNNEY BAGS to slow down water loss. This method is easy and cheap. The only problem is that the sheets may cause concrete become darker in places. To avoid this keep concrete EVENLY moist. For better strength and durability, cure concrete for 7 DAYS. The concrete is cured LONGER ; it will have its best possible strength and durability. Other method of curing 1) Pounding method 2)Spary waste timber dust and apply water 3)Spary chemicals 6) Compressive strength test One set (3 cubes) shall be tested at 7 days and one set 28 days after casting. Average strength of 3 cubes shall be equal or greater than design strength and individual test result shall be greater than 85% of design strength. Each test report shall be submitted to Engineer.

07) Flow Chart of concrete work a). Lean concrete


Lean concrete Mark the locations on the Lean concrete Fixing of reinforcement & cover blocks R/f inspection by contractor NO OK R/f Inspection by consultant OK Erection of formwork NO

Inspection by Contractor NO OK Final inspection by consultant OK Concreting Curing Removal of formwork

NO

Inspection Not satisfied Satisfied

Do rectification as per Structural Engineers instructions

Carry out further works

b). Columns
Mark the locations on the foundation or floor slab

Fixing of reinforcement & cover blocks and (anchor bolts for base plates of steel columns)

R/f inspection by contractor NO R/f Inspection by consultant NO OK Erection of formwork

Inspection by Contractor NO OK Final inspection by consultant OK Concreting Curing Removal of formwork NO

Inspection Not satisfied Satisfied

Do rectification as per Structural Engineers instructions

Carry out further works

c). Beams
Mark the location and level

Erection of bottom form work with adequate supports Fixing of reinforcement & cover blocks

R/f inspection by contractor NO R/f Inspection by consultant OK Erection of formwork

NO

Inspection by Contractor NO OK Final inspection by consultant OK Concreting NO

Curing Removal of side formwork Removal of supports and bottom form Inspection Not satisfied Do rectification as per Structural Engineers instructions Satisfied Carry out further works

d). Ground slab

Lay gauge 1000 polythene layer On the compacted earth Mark the stud column starter bar as per the drawings

Lay R/F and Fix column starter bar as per details given in the drawings Fix stop board where necessary to hold concrete

Inspection by contractor NO Inspection by consultant OK Concreting NO

Curing

Removal of side formwork

Removal of supports and bottom formwork

Inspection Not satisfied Do rectification as per Structural Engineers instructions Satisfied Carry out further works

e). Suspended slab


Mark the location and levels

Erection of slab bottom formwork with supports Laying of R/F and cover blocks and M&E services Inspection by contractor NO OK Inspection by consultant NO Fixing of side board Cleaning Inspection by contractor & Consultant OK Concreting

NO

Curing Removal of formwork and support

Inspection Not satisfied Do rectification as per Structural Engineers instructions Satisfied Carry out further works