Vous êtes sur la page 1sur 20

CHAPTER 1 SUBSTRUCTURE

1.1 Earthwork

INTRODUCTION

Earthwork: the processes whereby the surface of the
earth is excavated and transported to and compacted
at another location.

The introduction of the internal combustion engine,
electric power and hydraulic power have led to the
development of a wide range of earthwork plant (size,
capacity and efficiency).

Scale: ranges from small works (the excavation of
ditches and trenches for drainage and pits and trenches
for foundations) to the large earthworks (highways and
dams).

INTRODUCTION

carried out at an early stage in a construction project,
completion of the earthworks within the scheduled
time is often the key to the completion on time of the
whole project

success often depends on:

o an adequate site investigation and preparing
practical and satisfactory designs of the
earthworks.

o the choice and efficient use of the correct types
and size of plant to meet the particular
requirements of the site.


SCOPE OF EARTHWORKS

Site clearing (Pembersihan tapak)

Cutting and excavation (Pengorekan dan pemotongan)

Transport and moving (Pemunggahan,Pengangkutan
dan Penuangan)

Compaction (Pemadatan)

Sloping (Pencerunan)

Site clearing

Clearing, grubbing, demolishing, breaking up and
removing all trees, shrubs, vegetation, butts,
structures such as walls, fences and other obstruction
within the site which have been designated to be
demolished or removed

All spoils and debris shall be removed and disposed of
off-site at an approved certified construction landfill

Site clearing


Cutting and excavation

Most construction projects require the movement of
earthwork on site. This will result in altering the
existing elevation to a different or finish elevation.

To determine the amount of soil to be moved, the
estimator needs to have a plot plan or topographic
survey.

This drawing is developed by plotting the readings
(elevations) obtained from a topographic field survey
usually performed by a licensed land surveyor.

Cutting and excavation

Part of the permanent works (e.g. cuttings)

A temporary expedient in the construction of the
works (e.g. for foundations and drainage)

The sides of the excavations are required to remain
stable during their design life, can be achieved by:
excavating the material to a stable slope angle
by retaining or supporting the material.

Cutting and excavation


Cutting and excavation


Transport and moving

Trucks are used to transport excavated material,
aggregates and construction material

As the primary hauling unit provides a high degree of
flexibility.

Found in the crust of the earth

Classified as rock or soil

Soil characteristics that affect a soils behaviour for
construction purposes.

Transport and moving

Lab tests are required to fully determine a soils
physical and chemical properties which control those
characteristics.

Transport and moving


Compaction

Increased bearing capacity
Increased compressibility
Reduce permeability
Improve stability
Heavy/highway vs. building foundation compaction
operations

Compaction


Sloping

Function of the natural angle of repose, density,
surface and subsurface water flow.

Early stabilization of surfaces is critical

Eliminate points of concentrated flow using slope
drains as outlets.

Difficult slopes may require riprap, gabions, or other
measures for permanent stabilization .

Sloping


Sloping


KEYS TO SUCCESSFUL
EARTHWORK OPERATIONS

1. Control surface and subsurface water
2. Maintain optimum moisture range by drying, mixing ,
or wetting
3. Identify and monitor cut & fill quantities
4. Good layout (horizontal & vertical control)
5. Minimize handling - minimize stockpiling

KEYS TO SUCCESSFUL
EARTHWORK OPERATIONS

6. Optimize haul lengths
7. Minimize cycle time
8. Proper selection and sizing of excavators and haul
units
9. Alternate haul unit wheel paths
10. Experienced personnel in the field

Vous aimerez peut-être aussi