WELCOME

WORK CHALLENGES AND


IMPROVEMENTS SUGGESTED /
IMPLEMENTED

By
Jitendra Kumar Rout
Emp. No. 11480
Client : Mahanadi Coalfields Limited
Contrctor : IVRCL-AMR JV
Project Cost : 251.34 cr
RITES Fee : 6.56 cr
Project length : 41.6 Km + 6.22 Km diversion road
Project Importance
a) All roads inside Talcher Coal Mines spreading over 5-areas
b) All transportation road of Rigid Pavement
c) Use of Fiber-Reinforced Concrete
d) Use of slip-form paver
e) PQC of 192,000cum, DLC of 82,000cum, HYSD of 6000MT

CURRENT ASSIGNMENT
Consultancy services for supervision the work of "Strengthening &
widening of coal transportation road at Talcher coalfields of MCL
Layout Plan for Project Road
Typical Cross Section of Road
Reinforcement Details of PQC
Consultancy services for supervision the work of
"Strengthening & widening of coal transportation road at
Talcher coalfields of MCL
As Highway engineer , responsible for all field activities
including site testing's, level checking and all site
measurements.
Responsible for TBM checking, FRL modification(if any),
Hindrance removal, Site data storage.
Responsible for strict adherence to mines safety rules.
Implementation of approved work programme.

My Involvement
My Involvement
1) Working in remote locations inside coal mines with all dust
and humidity
2) Without any communication and proper transportation
3) Extended working hours usually beyond working hours


Improvements Suggested / Implemented
Work Challenges
Use of Helmet/Mask and safety shoe.
Problem with design of super-elevation shorted out .
Problem with frequent changing OGL in mines roads
addressed.




Project Handled by me while working with RITES in the last
9 Years
Projects Position
Consultancy services for supervision the work of
"Strengthening & widening of coal transportation road
at Talcher coalfields of MCL". Duration- April 2013 to
April 2014, Location- Talcher, Odisha.
Highway Engineer-I
Preparation of Pre-feasibility Study Report for Selected
State Highway Corridors for taking up in PPP Mode.
Highway Engineer
DPR for construction of diversion road from check-post
of Lingaraj OCP to NH-200 for coal evacuation
including a flyover and ROB on the level crossing
(2.0km long) at Lingaraj area of Talcher coalfields of
MCL.
Project co-ordinator
Feasibility & Detailed Project Report for development
of common rail/road corridor to meet the requirement
of large industries at Mahanadi-Angul-Talcher Belt.
Quantity Surveyor

Widening & Strengthening Of Road from Balinga to
Taparia for a length of 21.96 km in three packages
under Basundhara Area of MCL in Sundargarh District
(Orissa).

Project Engineer
Client:- Kolkata Municipality Corporation (KMC) for all three projects

Involvement:-
Supervision, quality control, recording measurements of works.
Preparation of IPC, variation reports etc.
Checking deficiencies in working drawing correcting same.
Facilitating redesign of structural members wherever necessary.
To review of contractors detailed works programme, Monitoring
progress and checking resources deployed against of works
programme, documentation as per ISO-9000

1.Construction of RCC Deck Slab supported on RCC MS line bored pile, beam
including pavement for Hooghly River front Development work of KMC from Baja
Kadamtala Ghat upto Fairlie Ferry Ghat at Kolkata. Project Cost = 25.34 Cr.
2. Development of Rabindranath Tagores Memorial Garden including repairing &
renovation of existing double storied building (Red House) at Nimtala Burning Ghat
of K.M.C. in Kolkata. Project Cost = 2.32 Cr.
3. Expansion of the Nimtala Burning Ghat in Kolkata, Project Cost = 13.66 Cr.
1) Hooghly River front Development work
Original area of project could not be handed over to working agency due to lack
of clearance from Ministry of Defence. So project was relocated to Armenium
Jetty to Millenium park. Since that area was a jetty during British period lots of
debris like wood, iron pieces encountered during piling work. So many places it
became impossible to carry piling work

Work Challenges
2) Development of Rabindranath Tagores Memorial Garden
a) The working platform was low. Piling work disrupted due to tidal water fluctuation
around full moon days and new moon days. And contractors claim was working
platform was well above highest water level indicated in tender drawing.

b) Superstructure was ISMB 500s to be bolted on pile cap which was round in
shape and exact same diameter of pile. ISMB 450 and ISMB 300 were to be
bolted to ISMB 500. It was not possible to fix ISMB 500 parallel to each other as
piles shifted.

3) Expansion of the Nimtala Burning Ghat in Kolkata
Land was not free as many religious structures were to be shifted
Sheet piling upto 24 meter was necessary as construction of basement was to be
underwater. But progress was slow/not satisfactory as working agency was
driving sheet piles manually

Work Challenges
Improvements Suggested / Implemented
1) Hooghly River front Development work
After several site visits by higher officials of KMC, RITES and discussions
design was modified. Pile points sifted, where piles could not reach to desired
depth additional piles introduced. Some places ISMB sections used in
superstructure.
Improvements Suggested / Implemented
2) Development of Rabindranath Tagores Memorial Garden
a) Working agency agreed to stop work during high tide rainy season and start work
in winter where tide is low. The work was executed in planned manner with help
of tide table.
b) Pile cap was modified to bigger rectangular shape.
3) Expansion of the Nimtala Burning Ghat in Kolkata

Land was cleared by co-operation from local people
Vibro-shinker used to speed up sheet piling work
Project in Picture
(Hooghly River front Development work)
Project in Picture
(Development of Rabindranath Tagores Memorial Garden)
Project in Picture
(Expansion of the Nimtala Burning Ghat in Kolkata)
DPR for construction of diversion road from check-post of Lingaraj OCP
to NH-200 for coal evacuation including a flyover and ROB on the level
crossing (2.0km long) at Lingaraj area of Talcher coalfields of MCL.
Importance:- 2 Km road includes 1.2Km elevated corridor
including one ROB, One Flyover, One connecting Ramp and
one Underpass,
Project Cost:- 125 Cr.
RITES DPR Fee:- 1.1 Cr.
Involvement:- (i) Topographic Survey
(ii) Rate Analysis
(iii) Quantity Estimation
(iv) Bid Document Preparation
(v) Approval of GAD from Railway


DPR for construction of diversion road from check-post of Lingaraj OCP
to NH-200 for coal evacuation including a flyover and ROB on the level
crossing (2.0km long) at Lingaraj area of Talcher coalfields of MCL.


LAYOUT PLAN
Detailed Report on Comprehensive Rail, Road & Pipe Line Corridor
in Meramundali AngulTalcherChhendipada Belt


1.Outer Corridor(Jarapada on NH-42 to Godibandha on NH-23)
4-lane divided carriageway , Length = 131.6 Km
Estimated cost = 571 cr
2.Inner Corridor (Jarasingha on SH-63 to Putagaria on outer Corridor)
2-lane undivided carriageway , Length = 30.1 Km
Estimated cost = 201 cr
3.Patrapada Mine link Corridor
(Km 34 of SH-63 to Patrapada village)
4-lane divided carriageway , Length = 21.8 Km
Estimated cost = 241 cr , Total Project Cost = 1014 Cr.
RITES Fee = 1.15cr (Highway Div share)






Scope :- 1) Detailed Site Reconnaissance
2) Traversing using GPS
3) Topographic survey
4) Traffic Survey and Projection
5) Pavement Condition survey and Design
6) Cost Estimate

Involvement :- 1) Detailed Site Reconnaissance of whole 182km
2) Establishing Traverse point using GPS
3) Topographic survey
4) Cost Estimate






Detailed Report on Comprehensive Rail, Road & Pipe Line Corridor
in Meramundali AngulTalcherChhendipada Belt
DPR for construction of diversion road from check-post of Lingaraj OCP
to NH-200 for coal evacuation including a flyover and ROB on the level
crossing (2.0km long) at Lingaraj area of Talcher coalfields of MCL.


LAYOUT PLAN
Client : Mahanadi Coalfields Limited
Contrctor : HSCL & EPIL
Project Cost : 22 cr
Project length : 21.96 KM
Project Importance
a) Project roads is connecting 2 states ( Odisha &
Chhattisgarh)
b) Use of slip-form paver

Rate Analysis and Cost Estimation for the works to be carried
for Package I from Dankuni to Chandannagar.
Rate Analysis and Cost Estimation for the works to be carried
for Package II from Chandannagar to Kalyani via Mogra.
Widening & Strengthening Of Road from Balinga to
Taparia for a length of 21.96 km in three packages under
Basundhara Area of MCL in Sundargarh District (Orissa).
Non availability of construction material within the near
vicinity of the project road,
Work supervision inspite of High volume of traffic due to
Coal transport
Improvements Suggested / Implemented
Work Challenges
Supervision of Construction of works.
Measurements of completed works.
Sole responsible regarding quality conformity tests.


So far my six years stint with the RITES has been quite
satisfying and enriching in terms of the breadth of the
knowledge and experience I have gained while working on
various challenging projects in diverse geographical
conditions.
I got a wide exposure which has also provided me the
necessary depth and the confidence to be able to hold my
own against the very best.
I enjoyed the challenges such as coordination with various
stake holders and performed my duties to the best possible
manner in the interest of the projects.

Working with RITES
While working on various projects I enhanced my Project
management Skills required in the atmosphere that is
intensively competitive, I have always maintained a
consistent performance in the projects I have been sent or
assigned.
One of my strongest points is my sincerity and strong
commitment towards the work which motivates me to take
initiatives in challenging situations.
I am sure with the varied experience and learning that I have
gained in such a short period will take me a long way in
RITES.

Working with RITES

THANK YOU