Académique Documents
Professionnel Documents
Culture Documents
A Look Ahead
(continued)
After that, we will continue our
exploration of tools and techniques
by considering:
The Concept of Float
download ADM_Float_Calcs.xls
PERT/CPM
Some History
PERT was first used in the late 1950s by
the Navy for the Polaris Missile Program
PERT => Project Evaluation & Review Technique
PERT/CPM
Some History (continued)
Virtually simultaneously CPM was
developed by the duPont Company and
Remington-Rand-Univac.
CPM => Critical Path Method
PERT/CPM
Some History (continued)
PERTs strengths are in its use of
probabilistic estimates of activity
durations
CPMs strengths are in its ability to do
time-cost trade-offs
Today, PERT/CPM are widely recognized
as comprising one set of techniques
the differences are primarily viewed as only
of historical importance
Strategic Project Management
Activity Sequencing
Display Techniques
There are many suitable techniques
for displaying the sequence of
activities involved in a project
Gantt Charts
Precedence Diagramming
Arrow Diagramming
Conditional Diagrams
Gantt Charts
Gantt charts use horizontal bars (or lines)
to represent activities
Gantt charts are more commonly used for
schedule display than activity sequencing
see BOK Figure 6-6 (1996 & 2000) for an example
length of the bars show expected duration
activity inter-relationships are not explicitly shown
The Precedence
Diagramming Method
The Precedence Diagramming
Method (PDM) uses boxes to
represent activities and arrows to
represent dependencies
see BOK Figure 6-2 (1996 & 2000 for an
example
More on PDM
Dependencies can include:
Finish-to-Start
Finish-to-Finish
Start-to-Start
Start-to-Finish
Dependencies are usually indicated by the placement of
the arrow heads and tails relative to the nodes but no
consistent approach has been universally adopted.
10
More on ADM
Also known as Activity-on-Arrow (AOA)
Each activity is represented by one and
only one arrow in the network.
Nodes (events) are numbered uniquely.
Duplicate node numbers are not allowed
11
More on ADM
(continued)
Before an activity can begin, all
activities terminating at the activities
beginning node must be completed.
Neither the length of an activity arrow
nor its compass direction have any
significance.
Networks should (must) have only one
initial event and one terminal event.
Strategic Project Management
12
An Example to Try:
Draw an Arrow Diagram
A project consists of Activities A, B, C, D, E,
F, G, H, I, J, K, and L
A, B, and C, the 1st activities of the project, can
start simultaneously
A and B precede D
B precedes E, F, and H
F and C precede G
E and H precede I and J
C, D, F, and J precede K
K precedes L
I, G, and L are terminal activities for the project
Strategic Project Management
13
14
Conclusion of Sequencing
Techniques
Well return to ADM in just a few
minutes but first lets complete the
set of sequencing techniques by
considering Conditional
Diagramming
15
Conditional Diagramming
Conditional Diagramming methods allow
for probabilistic activities and looping
neither of these are allowed in traditional PDM
or ADM
16
Activity Durations
The next logical step in Project Time
Management is to determine activity
durations.
We are going to defer a detailed
discussion of estimating activity
durations until later in the course.
At this point we need to introduce the
concept of the Critical Path of a project.
Strategic Project Management
17
18
19
20
21
22
23
Class Example
Critical Path Calculations
4
2
2
0
3
2
1
Strategic Project Management
3
2
SPM Basic PERT/CPM (Part 1)
24
25
26
27