RAINWATER HARVESTING
SYSTEM OF SPAMAST CAMPUSES
Ferdinand Zamora
BSAE
campuses.
To determine the water consumption of SPAMAST
campuses.
To determine the rainfall characteristics of
SPAMAST campuses.
To analyze the rainwater harvesting potentials of
SPAMAST campuses.
To design of rainwater harvesting system.
To estimate the cost of construction for rainwater
harvesting system in SPAMAST campuses.
Significance of Study
To provide option to have alternate source of
similar researches.
METHODOLOGY
Research Locale
The design and estimates of rainwater
harvesting system of SPAMAST campuses (Malita
campus, Buhangin campus and Digos campus)
from November, 2014 to January 2015.
METHODOLOGY
Gathering Procedure
Water distribution of SPAMAST campuses
Gathering of water consumption of SPAMAST
campuses
Gathering available rainfall data from
SPAMAST meteorological station.
Analyzing rainwater harvesting potentials
Design and estimates of rainwater harvesting
system
450
400
350
300
250
200
150
100
50
0
Jul.-10
Aug.-10
Sep.-10
Oct.-10
Nov.-10
Dec.-10
Jan.-11
Feb.-11
Mar.-11
Apr.-11
May.-11
Jun.-11Jul.11
Aug.-11
Sep.-11
Oct.-11
Nov.-11
Dec.-11
Jan.-12
Feb.-12
No.
Building Name
Area (m)
Gen.Ed Bldg.-Cas
820
Gen.Ed Bldg.-Buhangin
1428
Dormitory-Buhangin
320
GenEd Bldg.-Main
820
Dormitory-Main
200
Academic Bldg.-Main
360
Education Bldg.-Main
700
FMS Bldg.-Main
360
Admin-Main
240
Figure 17.
Harvester
Details.
Table 7.
Total Cost Estimates of Rainwater Harvesting
System in SPAMAST Campuses.
Cost of
Construction
()
No.
Building Name
410
6 m
136,886.60
GenEd bldg.-Buhangin
714
8 m
137,640.60
W.Dorm-Buhangin
160
3 m
84,964.32
Acad. Bldg.-Malita
410
3 m
84,964.32
Admin Bldg.-Malita
100
3 m
79,406.04
FMS Bldg.-Malita
180
3 m
86,421.10
Educ. Bldg.-Malita
350
4 m
97,214.70
W.Dorm.-Malita
120
3 m
80,279.64
GenEd Bldg.-Malita
410
6 m
136,886.60
Tank Capacity
924,663.92
July 2014, valuing 597.00 m. The lowest measured data in was 35.00
m on March 2013
irrigation purposes.
The total cost estimates for construction of rainwater harvesting
Conclusion
The following conclusions were drawn:
the water that procured from water districts will be decreased with
surface & ground water as later is concerned with the rising cost as
well as ecological problems.
It was finally concluded that implementation of RAINWATER
Recommendation
There is a need to conduct seminar and training on the current
SPAMAST campuses.