BSC6900 GU

Installation &
Commissioning
www.huawei.com

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Foreword

The commissioning is performed after the hardware


installation and before the services are provided

The OMU operating system is installed before the


OMU is delivered

The commissioning ensures the RNC works properly


as designed

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page3

References

BSC6900 GU OMU Administration Guide

BSC6900 GU Commissioning Guide

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page4

Objectives

Upon completion of this course, you will be able to:

Describe BSC6900 commissioning procedure

Outline OMU software functions

Complete BSC6900 commissioning

Complete BSC6900 application software installation

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page5

Contents
1.

BSC6900 O&M System Introduction

2.

BSC6900 Software Installation

3.

BSC6900 Commissioning

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page6

BSC6900 O&M Subsystem

Component

LMT

OMUa boards

SCUa boards

OM modules

on other boards

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page7

BSC6900 O&M Subsystem

BSC6900 O&M system adopts server and client


mode

OMU as a server

LMT as a client

EMS (Element Management System) system

iManager M2000 works for integrated O&M

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page8

OMU IP Address Planning


IP Address

Planning Principle

Internal fixed

The preset IP addresses of the internal Ethernet adapters

IP address

are:
Active BAM: 80.168.3.50 (255.0.0.0)

Standby BAM: 80.168.3.60 (255.0.0.0)

External fixed

The preset IP addresses of the external Ethernet adapters

IP address

are:
Active BAM: 172.121.139.201 (255.255.255.0)

Standby BAM: 172.121.139.202 (255.255.255.0)

The settings can be reconfigured on site based on the


actual networking topology

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page9

OMU IP Address Planning


IP Address

Planning Principle

Internal/Extern

The virtual IP address is set in the same subnet with the

al virtual IP

internal/ external fixed IP addresses of the active and

address

standby BAMs

Backup

The preset backup channel IP addresses of the active and


standby BAMs are:

Active BAM: 192.168.3.50 (255.255.255.0)

Standby BAM: 192.168.3.60 (255.255.255.0)


The IP address should not be changed

channel IP
addresses

Commissioning
IP address

The preset commissioning IP addresses are:


Active BAM: 192.168.6.50 (255.255.255.0)
Standby BAM: 192.168.6.60 (255.255.255.0)
The IP address should not be changed.

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page10

OMU Internal Network IP Address


Virtual IP
Planning Active OMUa
Standby OMUa

80.168.3.40/8

80.168.3.50/8
ETH4-SCU7
ETH5-SCU6

80.168.3.60/8
Internal
network
segment

ETH4-SCU7
ETH5-SCU6
192.168.3.60/24

192.168.3.50/24
Intel Ethernet
adapters
ETH3UPDATE

Intel Ethernet
adapters
Dedicated
backup
channel

ETH3UPDATE
SCUa

SCUa

Backboard
BSC6900 FAM
Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page11

OMU External Network IP Address


Planning
Virtual IP
Active OMUa

Standby OMUa

172.121.139.202/24

172.121.139.201/24
External
network
Segment
GE adapter

172.121.139.200/24

ETH0

ETH0

ETH1

ETH1
Hub

Commissioning
Ethernet
adapter

ETH2

ETH2

LMT/
M2000

192.168.6.50/24
192.168.6.60/24

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page12

Contents
1.

BSC6900 O&M System Introduction

2.

BSC6900 Software Installation

3.

BSC6900 Commissioning

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page13

BSC6900 Software
LMT

MPS/EPS
LMT Software
Host Software
Windows XP
SP2

Java
Environment

Program
File

Data File
OMU Server
Patch File
(optional)

OMU Application
Dopra Linux

Mysql Database

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page14

OMU Software

The OMU
software consist
of multi-level
service
monitoring
entities and
service processes

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page15

OMU Software Installation


Procedure

Obtain the Installation Information on the OMU

Remotely Logging In to the OMU

Uploading the OMU Application Installation Package


to the OMU

Installing the OMU Application in the Active


Workspace

Checking the Installation Directory of the OMU


Applications

Checking the Status of omud Process

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page17

Obtain the Installation


Information on the OMU

Before the installation, obtain the following


information from Data Sheet of BAM Software
Installation

Password of the operating system administrator

Fixed IP addresses of the internal and external


networks

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page18

Remotely Logging In to the


OMU

On the computer run


the SSH terminal,
PuTTY

Enter the IP address of


the OMU

Log in to the OMU as


user root

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page19

Uploading the OMU Application


Installation Package to the
Decompress the BSC6900 version software package to the
OMU
local drive D

Log in to the OMU through the psftp software

Run the lcd D:\ to set the local directory

Run the mkdir /mbsc/upgrade to create the target directory

Run the cd /mbsc/upgrade to go to the target directory

Run the put -r V900R011C00 to upload the OMU application


installation packet to the OMU

After the loading is complete, enter the exit command to exist


the psftp software

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page20

Installing the OMU Application


in the Active Workarea

On the PuTTY terminal, run the following commands

cd /mbsc/upgrade/V900R011C00/install/setup

chmod +x ./install_bam.sh

./install_bam.sh

Enter the run mode

Setting the office name

Setting the language

Setting the admin/FTP password

Setting the external virtual IP address

Setting the OMU system type

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page21

Checking the Installation


Directory of the OMU
Log in to the OMU by PuTTY
Applications

Run the cd /mbsc/bam

Check whether the OMU


installation directory

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page22

Checking the Status of omud


Process

Log in to the OMU by PuTTY

Run the /etc/rc.d/omud status

The returned information is running, it means the


omud is working normally

The returned information is unused, run the


/etc/rc.d/omud start command to start the omud

The returned information is neither running nor


unused, reinstall the OMU application in the active
workspace

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page23

Contents
1.

BSC6900 O&M System Introduction

2.

BSC6900 Software Installation

3.

BSC6900 Commissioning

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page24

Contents
3. BSC6900 Commissioning
3.1 BSC6900 Commissioning Introduction
3.2 BSC6900 Commissioning Procedure

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page25

Introduction to BSC6900
Commissioning

Definition of BSC6900 Commissioning

The commissioning of equipment, BSC6900


board software and data file loading , interfaces
verification , and services verification after
hardware installation

To ensures that the BSC6900 works properly as


designed

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page26

Preparation For BSC6900


Commissioning

Preparation For BSC6900 Commissioning

Verify hardware status

BSC6900 hardware is installed and passed the hardware


installation check and powering-on check

OMU is configured before delivery

LMT PC meets the configuration requirements

Software preparation

BAM and LMT application software are ready

License file is ready

MML command script for initial configuration is ready

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page27

Preparation For BSC6900


Commissioning (Cont.)

Verify commissioning network status

At least one BTS and one NodeB are connected to the local
BSC6900. The BTS and the NodeB should have passed
commissioning and can provide basic functions

At least one set of Core Network (CN) equipment is connected


to the local BSC6900. The CN equipment should have passed
the commissioning and can provide basic functions

If the BSC6900 is connected to the RNC, then that RNC must


have passed the commissioning

Three single-mode UEs, three single-mode MSs and one dualmode UE are ready for test and are registered in the HLR

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page28

Contents
3. BSC6900 Commissioning
3.1 BSC6900 Commissioning Introduction
3.2 BSC6900 Commissioning Procedure

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page29

BSC6900 Commissioning
Procedure
BSC6900 Commissioning Procedure

Verifying the Equipment

Activating and Verifying the License

Loading the BSC6900 Board Software and Data Files

Verifying the Interfaces

Handling the Alarms Generated During the Commissioning

Verifying the Services

Connecting the BSC6900 to the M2000

Creating Scheduled Tasks

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page30

Verifying the Equipment

Verifying the Equipment

Verifying the OMU

Log in to the OMU through PuTTY

Check that the OMU application is normally installed

If OMU application is not installed or abnormal, please


reinstall software

Verifying the LMT

Log in to the BSC6900 through the LMT

Run the MML command LST VER to check the version of OMU

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page31

Activating and Verifying the


License
Activating and Verifying the License

Downloading license to OMU active workspace


directory /ftp/license (DLD LICENSE)

Querying the detail information of the license file (LST


LICENSE)

Activating the license file (ACT LICENSE)

Checking the license consistency between host and


OMU (CMP LICENSE)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page32

Loading the BSC6900 Board


Software and Data Files

Loading the BSC6900 Board Software and Data Files

Generating the Data File

Clear the data in the BAM database (RST DATA)

Generate the data file in ineffective state


SET CFGDATAINEFFECTIVE
Batch Commands
FMT DATA

Setting the Loading Mode (SET LODCTRL)

Loading the MPS/EPS/TCS (RST SUBRACK)

Checking the consistency of the data and the version (ACT


CRC & CMP BRDVER)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page33

Verifying the Abis Interface

Verifying the Abis Interfaces (over TDM)

Verifying Physical links at the BSC (DSP E1T1 & DSP


OPT)

Verifying Control Plane on the Abis interface (DSP


LAPDLNK)

Verifying User Plane on the Abis interface (DSP


ABISTS)

Verifying Cell status and Channels (DSP BTSSTAT)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page34

Verifying the Abis Interface

Verifying the Abis Interfaces (over IP)

Verifying Physical Links at the BSC (DSP ETHPORT &


DSP PPPLNK & DSP MPGRP)

Verifying Control Plane on the Abis interface (DSP


LAPDLNK & DSP ADJNODE)

Verifying User Plane on the Abis interface (DSP


IPPATH)

Verifying Cell status and channels (DSP BTSSTAT)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page35

Verifying the Abis Interface

Verifying the Abis Interfaces (over HDLC)

Verifying Physical Links at the BSC (DSP E1T1)

Verifying Control Plane on the Abis interface (DSP


LAPDLNK)

Verifying User Plane on the Abis interface (DSP


HDLCLNK)

Verifying Cell status and Channels (DSP BTSSTAT)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page36

Verifying the A Interface

Verifying the A Interface (over TDM)

Verifying Physical Links at the BSC (DSP E1T1 & DSP


OPT)

Verifying Control Plane on the A interface


DSP MTP2LNK
DSP MTP3LNK
DSP SSN
DSP N7DPC

Verifying User Plane on the A interface (DSP ACIC)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page37

Verifying the A Interface

Verifying the A Interface (over IP)

Verifying Physical Links at the BSC (DSP ETHPORT &


DSP PPPLNK & DSP MPGRP)

Verifying Control Plane on the A interface


DSP SCTPLNK
DSP MTP3LNK
DSP SSN
DSP N7DPC
DSP ADJNODE

Verifying User Plane on the A interface (DSP IPPATH)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page38

Verifying the Gb Interface

Verifying the Gb Interface (over FR)

Verifying Physical Links at the BSC (DSP E1T1 & DSP


BC )

Verifying Control Plane on the Gb interface (DSP


SIGBVC & DSP PTPBVC & DSP NSVC)

Verifying User Plane on the Gb interface (DSP PTPBVC


& DSP NSVC)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page39

Verifying the Gb Interface

Verifying the Gb Interface (over IP)

Verifying Physical Links at the BSC (DSP ETHPORT &


DSP PPPLNK & DSP MPGRP)

Verifying Control Plane on the Gb interface (DSP NSVL


& DSP SIGBVC & & DSP PTPBVC)

Verifying User Plane on the Gb interface (DSP NSVL &


DSP PTPBVC)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page40

Verifying the Ater Interface

Verifying the Ater Interface

Verifying Physical Links at the BSC (DSP E1T1 & DSP


OPT)

Verifying Signaling Links at the BSC (optional) (DSP


ATERSL)

Verifying status of timeslots on the Gb interface (DSP


ATERTS)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page41

Verifying the Pb Interface

Verifying the Pb Interface

Verifying Physical Links at the BSC (DSP E1T1)

Verifying Control Plane on the Pb interface (DSP


LAPDLNK)

Verifying status of timeslots on the Pb interface (DSP


PBCIC)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page42

Verifying the Iub Interface

Verifying the Iub Interface (over ATM)

Verifying Physical Links at the BSC (DSP E1T1 & DSP


OPT)

Verifying the Control Plane on the Iub Interface (DSP


SAALLNK & DSP UIUBCP & DSP ADJNODE)

Verifying the User Plane on the Iub Interface (DSP


AAL2PATH)

Verify the Management Plane on the Iub Interface (DSP


IPOAPVC)

Verifying the Cell Setup (DSP UCELL)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page43

Verifying the Iub Interface

Verifying the Iub Interface (over IP)

Verifying Physical Links at the BSC (DSP ETHPORT &


DSP OPT)

Verifying the Control Plane on the Iub Interface (DSP


SCTPLNK & DSP UIUBCP & DSP ADJNODE)

Verifying the User Plane on the Iub Interface (DSP


IPPATH)

Verify the Management Plane on the Iub Interface (DSP


IPOAPVC)

Verifying the Cell Setup (DSP UCELL)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page45

Verifying the Iu-CS Interface

Verifying the Iu-CS Interface (over ATM)

Verifying Physical Links at the BSC (DSP E1T1 & DSP


OPT)

Verifying the Control Plane on the Iu-CS Interface


DSP SAALLNK
DSP MTP3LNK
DSP SSN
DSP N7DPC
DSP ADJNODE

Verifying the User Plane on the Iu-CS Interface (DSP


AAL2PATH)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page46

Verifying the Iu-CS Interface

Verifying the Iu-CS Interface (over IP)

Verifying Physical Links at the BSC (DSP ETHPORT &


DSP OPT)

Verifying the Control Plane on the Iu-CS Interface


DSP SCTPLNK
DSP M3LNK
DSP SSN
DSP N7DPC
DSP ADJNODE

Verifying the User Plane on the Iu-CS Interface (DSP


IPPATH)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page47

Verifying the Iu-PS Interface

Verifying the Iu-PS Interface (over ATM)

Verifying Physical Links at the BSC (DSP E1T1 & DSP


OPT)

Verifying the Control Plane on the Iu-PS Interface


DSP SAALLNK
DSP MTP3LNK
DSP SSN
DSP N7DPC
DSP ADJNODE

Verifying the User Plane on the Iu-PS Interface (PING


IP)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page48

Verifying the Iu-PS Interface

Verifying the Iu-PS Interface (over IP)

Verifying Physical Links at the BSC (DSP ETHPORT &


DSP OPT)

Verifying the Control Plane on the Iu-PS Interface


DSP SCTPLNK
DSP M3LNK
DSP SSN
DSP N7DPC
DSP ADJNODE

Verifying the User Plane on the Iu-PS Interface (DSP


IPPATH)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page49

Handling the Alarms Generated


During the Commissioning

Handling Alarms During RNC Commissioning

Checking alarm on the LMT

Handling the Alarms by LMT online help

Handling alarms by HUAWEI Technical Support

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page50

Verifying the GSM Services

To be sure BSC can provide services defined in


license file

Basic services

Speech service, data service, mobility management,


and OM management

Feature services

Inter-system handover, location service, and AMR


service

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page51

Verifying the UMTS Services

To be sure BSC can provide services defined in


license file

Basic services

Voice service, CS stream service, PS service,


mobility management, and OM management

Feature services

Inter-system handover, HSDPA service, HSUPA


service, MBMS service, and location service

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page52

Connecting the BSC6900 to the


M2000

Connect the BSC6900 to the OM network

Configure the IP route from the BSC6900 to the


M2000 (ADD OMUIPRT & ADD EMSIP)

Create the BSC6900 on the M2000

iManagerTM M2000

DCN

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page53

Creating Scheduled Tasks

Scheduled tasks for backing up system data (ADD


SCHTSK & ADD SUBTSK)

Scheduled tasks for backing up logs (ADD SCHTSK


& ADD SUBTSK)

Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved.

Page54