Estimation And Quantity

Surveying

CONTENTS
DADO
Brief Specification
Detailed Specification
Rate Analysis

FLY OVER
Approximate Estimate

Brief Specification for Dado

Provide dado on 12 mm thick rough


cement plaster (1:3) base and jointed with
alkali resisted cement as per IS: 4457
completed as per the direction of
Engineer-In-Charge.

Detailed Specification for


Dado
1. Materials
2. Preparation of surface & laying
3. Mortar and bedding
4. Fixing tiles for dado
5. Cleaning
6. Pointing and finishing
7. Mode of measurement

MATERIALS
White Glazed Tiles : The tiles shall be of

approved and shall generally conform to


IS : 777.
They shall be flat and true to shape and
free from cracks, blisters, welts, crawling,
crazing spots, chipped edges, corners or
other imperfections detracting from their
appearance.
The tiles shall be of square or rectangular
of nominal sizes such as 300x200mm,
150x150mm, 100x100mm.
Samples of tiles shall be got approved by

PREPARATION OF SURFACE & LAYING


Sub grade concrete or RCC slab or side

brick wall/ or plastered surfaces on which


tiles are to be laid shall be cleaned, wetted
and mopped.
The bedding/backing for the tile shall be of
C.M. 1.3 or as specified and shall be applied
and allowed to harden.
The mortar shall be roughened with wire
brushes or by scratching diagonal lines
1.5mm. deep at 7.5mm.
dado shall be truly horizontal and joints
truly vertical.

MORTAR AND BEDDING


Cement

mortar shall conform to the


specification for materials, preparations
etc. as specified under cement mortar.
The amount of water added while
preparing mortar shall be the minimum
necessary to give sufficient plasticity for
laying.
Care shall be taken in preparation of the
mortar to ensure that there are no hard
lumps that would interfere with even
bedding of the tiles.
The mortar of specified proportion and

FIXING TILES FOR DADO


The dado work, shall be done only after fixing

the tiles/slabs on the floor.


The approved white glazed tiles before laying
shall be soaked in water for at least 2 hours.
Tiles shall be fixed when the cushioning mortar
is still plastic and before it gets very stiff.
The back of the tile shall be covered with this
layer of cement mortar 1:2 using fine sand
(table III, zone IV, I.S. 383-1963) and the edge
of the tile smeared with neat white cement
slurry.
The tile shall then be pressed in the mortar and
gently tapped against the wall with a wooden
mallet.

The fixing shall be done from bottom of wall upwards

without any hollows in the bed of joints.


Each tile shall be as close as possible to one
adjoining.
The tiles shall be jointed with white cement slurry.
Any thickness difference in the thickness of the tiles
shall be arranged out in cushioning mortar so that all
tiles faces are in one vertical plane.
The top of the dado shall be touched up neatly with
the rest of the plaster above.
After fixing the dado/skirting etc. they shall be kept
continuously wet for 7 days.
If doors, windows or other openings are located within
the dado area, the corners, sills, jambs etc. shall be
provided with true right angles without any specials.

CLEANING
After the tiles have been laid in a room or the

days fixing work is completed, the surplus


cement grout that may have come out of the
joints shall be cleaned off before it sets.
After the complete curing, the dado or skirting
over shall be washed thoroughly clean.
In the case of flooring, once the floor has set, the
floor shall be carefully washed clean and dried.
When dry, the floor shall be covered with oil free
dry saw dust.
It shall be removed only after completion of the
construction work and just before the floor is
used.

MODE OF MEASUREMENT
Dado/flooring/skirting shall be measured in

sqm. correct to two places of decimal.


Length and breadth shall be measured
correct to 1 cm.
Between the exposed surfaces of skirting or
dado. No deductions shall be made nor
extra paid for any opening of area up to 0.1
sqm.
The rate shall include all the cost of labour
and materials involved.

Rate Analysis for Dado


Rate Analysis for 10 sq-m
The quantity of white-glazed tile is worked out by
assuming 1 mm on either side for thickness in joint
& tolerance in size of tiles. Thus, no of white-gazed
tiles
= 10/(0.152X0.152)
= ~ 432 tiles

Particular
s
White Gazed
Tiles

Quantity
Or
Numbers

Rate

Per

Amounts

432 Nos

Rs. 8.00

no

Rs. 3456.00

Wastage o
white gazed
tiles @ 5%

Rs. 172.00

C.M. (1:3) for


rough
plaster,
bedding &
wastage

0.18 cu m

Rs. 2510.00

Cu m

Rs. 451.80

White
Cement
Sundries

0.25 bags

Rs. 950.00

bag

Rs. 237.50
Rs. 6.90

Material Cost
=

Rs. 4325.00

Sq m

Rs. 1000.00

Labour:
Labour for
fixing,
making

10.00 sq m

Rs. 100.00

Labour Cost
= Rs. 1000.00
Add Material Cost
= Rs. 4325.00
------------------Total
= Rs 5325.00
10% Contractors Profit = Rs. 532.50
1.5% Water and electric
consumption charges = Rs. 79.88
-------------------Rate per 10 sq m
= Rs. 5937.38
Rate per sq m
= Rs. 593.74
Say
= Rs. 595.00

Approximate Estimate of FLY


OVER
Examples:
National ProjectAt Mohan Nagar Junction in Ghaziabad, India.

At Kampthee, Nagpur on NH-7, India


At Sirmaur Chauraha Rewa, M.P., India
International ProjectAt Junction of Che Kung Road and Hung Mui
Road, Honkong.

At Mohan Nagar Junction in


Ghaziabad, India
Name of Project

: Construction of Fly Over


Detail of Client: National Capital Region Planning Board
Details of Contractor: Asian Development Bank and
Wilbur Smith Associates
Scope of Work : Fly Over with 2 lanes on existing road for
700 meters
Cost of Work : Rs. 539,160,413.00
Duration of Work : 2 Years (work started on July 2008)
Details, Project Progress: Completed on July 2010
Resources Used : Manpower, Equipments, Machineries
New Technology :
Paver Finisher Hydrostatic with sensor
control
Per meter cost : Rs. 7,70,229

At Kampthee, Nagpur on NH-7, India


Name of Project :

Construction of Fly Over


Detail of Client :
NHAI
Details of Contractor :
Oriental Construction Company
Pvt. Ltd
Backbone Enterprises
Scope of Work :
Fly Over on 850 Meter 2 lane road
Cost of Work :
Rs. 721,122,350.00
Duration of Work
: 2 Years (work started on July 2010)
Details, Project Progress: Completed on July 2012
Resources Used :
Manpower, Equipments, Machineries
New Technology:
Fly Ash was used, Pile foundation was
done
Per meter cost :
Rs. 8,48,379.00

At Sirmaur Chauraha Rewa, M.P., India


Name of Project

: Construction of Flyover Bridge at


Sirmour Chouraha Rewa on Varanasi- Nagpur
Road, Rewa, MP
Detail of Client: Public Works Department M.P.
Details of Contractor: Abhay Mishra Comstruction
company
Scope of Work : Fly Over with 750 meters long two
lane
Cost of Work : Rs. 25 Crors
Duration of Work : 2 Years (Started on 2012)
Project Progress : Under Process
Resources Used : Manpower, Equipments,
Machineries
Per meter cost : Rs. 3,33,333

At Junction of Che Kung Road & Hung Mui


Road, Honkong.
Name of Project

: Construction of Fly Over


Detail of Client: Government of the Hong Kong
Special Administrative Region
Details of Contractor : HKSAR
Scope of Work : Construction of approximate
600
metres long dual 2-lane
Cost of Work
: Rs. 537,140,479.00
Duration of Work : December 2007
Details, Project Progress: Completion January
2013
Resources Used : Manpower, Equipments,
Machineries
Per meter cost : RS. 8,98,600

Average cost per meter


=Rs. 5,37,635

THANK YOU