Flexible Budgets,

Overhead Cost Variances,


and
Management Control

Copyright 2015 Pearson Education, Inc. All Rights Reserved.

1.
2.
3.

4.

Explain the similarities and differences in


planning variable and fixed overhead costs
Develop budgeted variable and fixed
overhead cost rates
Compute the variable overhead flexiblebudget variance, the variable overhead
efficiency variance and the variable
overhead spending variance
Compute the fixed overhead flexiblebudget variance, the fixed overhead
spending variance and the fixed overhead
production-volume variance
Copyright 2015 Pearson Education, Inc. All Rights Reserved.
8-2

5.

6.

7.
8.

Show how the 4-variance analysis approach


reconciles the actual overhead incurred
with the overhead amounts allocated
during the period
Explain the relationship between the salesvolume variance and the productionvolume variance
Calculate variances in activity-based
costing
Examine the use of overhead variances in
nonmanufacturing settings
Copyright 2015 Pearson Education, Inc. All Rights Reserved.
8-3

To effectively plan variable overhead costs,


managers should focus on activities that add
value and eliminate those that do not.
Fixed overhead planning is similar ~ plan only
for essential activities and plan to be as
efficient as possible.

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-4

is a costing system that


Traces direct costs to output by multiplying
the standard prices or rate by the standard
quantities of inputs allowed for actual outputs
produced.
Allocates overhead costs on the basis of the
standard overhead-cost rates times the
standard quantities of the allocation bases
allowed for the actual outputs produced.

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-5

1.
2.

3.

4.

Choose the period to be used for the


budget.
Select the cost-allocation bases to use in
allocating variable overhead costs to
output produced.
Identify the variable overhead costs
associated with each cost-allocation
base.
Compute the rate per unit of each costallocation base used to allocate variable
overhead costs to output produced.
Copyright 2015 Pearson Education, Inc. All Rights Reserved.
8-6

Variable overhead flexible-budget variance


measures the difference between actual variable
overhead costs incurred and flexible-budget
variable overhead amounts.

This variance can be further broken down into the


Variable Overhead Efficiency Variance and the
Variable Overhead Spending Variance.
Copyright 2015 Pearson Education, Inc. All Rights Reserved

8-7

Variable overhead efficiency variance is the difference


between the actual quantity of the variable overhead
cost-allocation base used and the budgeted quantity of
the variable overhead cost-allocation base allowed for
the actual output X the budgeted variable overhead cost
per unit of the cost-allocation base.

Copyright 2015 Pearson Education, Inc. All Rights Reserved

8-8

Variable overhead spending variance is the


difference between actual and budgeted variable
overhead cost per unit of the cost-allocation
base, multiplied by the actual quantity of
variable overhead cost-allocation base used.

Copyright 2015 Pearson Education, Inc. All Rights Reserved

8-9

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-10

Fixed overhead costs are, by definition, a lump


sum of costs that remain unchanged for a given
period despite potentially wide changes in
activity within the relevant range.
These costs are fixed in the sense that, unlike
variable costs, fixed costs do not automatically
increase or decrease with the level of activity
within the relevant range.

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-11

1.
2.

3.

4.

Choose the period to be used for the


budget.
Select the cost-allocation bases to use in
allocating fixed overhead costs to output
produced.
Identify the fixed overhead costs
associated with each cost-allocation
base.
Compute the rate per unit of each costallocation base used to allocate fixed
overhead costs to output produced.
Copyright 2015 Pearson Education, Inc. All Rights Reserved.
8-12

Fixed overhead flexible-budget variance is the


difference between actual fixed overhead costs
and fixed overhead costs in the flexible budget.
The fixed overhead spending variance is the same
variance as the Fixed Overhead Flexible-Budget
Variance

Copyright 2015 Pearson Education, Inc. All Rights Reserved

8-13

Production-volume variance is the difference


between budgeted fixed overhead and fixed
overhead allocated on the basis of actual output
produced.
This variance is also known as the denominatorlevel variance.

Copyright 2015 Pearson Education, Inc. All Rights Reserved

8-14

Interpretation of this variance is difficult due to


the nature of the costs involved and how they
are budgeted.
Fixed costs are by definition somewhat
inflexible. While market conditions may cause
production to flex up or down, the associated
fixed costs remain the same.
Fixed costs may be set years in advance, and
may be difficult to change quickly.
Contradiction: Despite this, examination of the
fixed overhead budget formulae reveals that it is
budgeted similar to a variable cost.
Copyright 2015 Pearson Education, Inc. All Rights Reserved.
8-15

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-16

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-17

4-VARIANCE
ANALYSIS
SPENDING
VARIANCE

EFFICIENCY
VARIANCE

PRODUCTIONVOLUME
VARIANCE

VARIABLE
OVERHEAD

YES

YES

NEVER A
VARIANCE

FIXED
OVERHEAD

YES

NEVER A
VARIANCE

YES

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-18

You may recall from chapter 7 that the static


budget variance (the difference between the
static budget and the actual results) was
$93,100 Unfavorable for Webb Company, our
sample company.
The sales-volume variance (the difference
between the flexible budget and the static
budget) was $64,000 Unfavorable.
The sales-volume variance consists of two
components: The operating-income volume
variance and the production-volume variance.
Copyright 2015 Pearson Education, Inc. All Rights Reserved.
8-19

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-20

Activity-based costing systems focus on


individual activities as the fundamental cost
objects.
Variances are calculated for each activity

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-21

Nonmanufacturing companies can benefit


from overhead variances just as
manufacturing companies can.
Variance analysis can be used to examine
overhead costs and make decisions about
pricing, managing costs and the mix of
products.
Output measures will be different and can be
passenger-miles flown, patient days
provided, rooms-days occupied, ton-miles of
freight hauled, etc.
Copyright 2015 Pearson Education, Inc. All Rights Reserved.
8-22

TERMS TO LEARN

PAGE NUMBER REFERENCE

Denominator level

Page 292

Denominator-level variance

Page 298

Fixed overhead flexible-budget


variance

Page 297

Fixed overhead spending


variance

Page 297

Operating-income volume
variance

Page 307

Production-volume variance

Page 298

Standard costing

Page 290

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-23

TERMS TO LEARN

PAGE NUMBER REFERENCE

Total-overhead variance

Page 305

Variable overhead efficiency


variance

Page 293

Variable overhead flexiblebudget variance

Page 293

Variable overhead spending


variance

Page 295

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


8-24

Copyright 2015 Pearson Education, Inc. All Rights Reserved.


25