Académique Documents
Professionnel Documents
Culture Documents
Introduction
Well foundations are being used in India
from very early days. Taj Mahal
was built on such foundations. Wells
are classified as deep foundations.
The main difference between a well
and a pile foundation is that, while a
pile is like a beam under horizontal
flexible
loads, the well undergoes rigid body
movement under such loads.
Types of Wells
Wells have different shapes
and accordingly they are named
as
1.
Circular Wells
2.Dumb bell
3.Double-D Wells
Single
and
Rectangular Wells
6. Multiple
Holed
Wells
Double
Dredged
Components of Well
Foundation
The various component of
a well foundations are
Cutting Edge
Well Curb
Bottom Plug
Steining
Top Plug
Well Cap
Design of Wells
Design of wells basically involves finding
1. Depth of the well
2. Size of the well and
3. Design of the other components.
Depth of Scour
Well foundations are constructed in river beds, they
should be taken to a safe depth well below the
anticipated scour level. Scour around piers depends
on several factors like flood discharge, the angle of
attack of the flow, flow obstruction etc. The scour
depth is calculated as follows.
Q
Ds 0.473
w here
Ds Scourdepth (m)
q Design discharge(m3/s) sf Silt factor 1.76
Dm
Dm Mean diameter of soil particle in river bed (mm)
Type of material
Values of
Silt Factor
sf
Coarse silt
0.04
0.35
Fine sand
0.08
0.5
Fine sand
0.15
0.68
Medium sand
0.3
0.96
Medium sand
0.5
1.24
Coarse sand
0.7
1.47
Coarse sand
1.76
Coarse sand
2.49
D .Ds
3
D Grip length of
well
Size of Wells
The size of dredge hole of a well
varies. In small and shallow
wells, the minimum diameter of
the dredge
should
be 1.8
m.
minimum
size hole
of the
dredge
hole
In larger
should
be 3 wells,
m. the
The final
size
lateral
Steining
This
is
subjected
to
different
types
of
stresses.
At
the
sinking it is subjected
to water and earth
pressure. At dredging
stage, inside surface
subjected
is
to water
pressure while outside
surface to the earth
pressure.
IRC
recommends
some
rules
of
thumb
for fixing the thickness
of steining
which
are given below.
Brick Steining
Tk
De DH
8 40
w here
k 1.0 for sand
1.1for soft clay
Curb
The curb of a well transfers all the superimposed loads to the soil through the
cutting edge while sinking. The material used for curbs may be timber or
RCC. The forces acting on well curb are shown in Fig(b). The total
horizontal force on the well curb on both sides is
Wcot2
w here
De Di
Cutting Edge
The cutting edge is provided at the bottom of the well below the curb to cut
through the soil during sinking. It is generally made of steel and welded to
an angle iron to fit the outer dimensions of the well steining. The height of
the cutting edge is given by
qu.t
fc.tan
w here
he
Bottom Plug
After final grounding of the
well
to
the
required
foundation
level,
a concrete
plug
is
provided. The
bottom
plug transfer the entire
load to the ground. The
bottom plug functions
as
an
inverted dome
supported
along
the
periphery
of
the
steining. As it is not
feasible
to provide
reinforcement
at the
bottom, it is generally
made thick and a rich
concrete
mix
(M20)
is used.
Sand Filling
The bottom plug concrete is cured and
after curing, the well is filled with
sand
in
saturated
condition.
Sand filling provides
1. Stability to the bottom of the well.
2. Eliminate the tensile forces at the
base
3. Cancels
hoop
steining induced
stresses
in
Top Plug
The
top
plug
is
provided after
the
filling
is completed.
Top
plug helps in
transferring the load of
the
pier
and
superstructure to the
steining.
The
thickness of
the top
plug
is generally
kept greater than 50 %
of the smaller dimension
of the dredge hole. If
sand filling is used,
the
top
plug
is
simply
constructed
using PCC of 1:2:4
otherwise it is reinforced
with steel bars and
lean concrete of 1:3:6 is
Well Cap
As the shape of the well pier and cap
are different, the well cap forms an
interim layer to accommodate the
pier. The well cap is so designed
that the base of the pier is provided
with a minimum all round offset.
The centre of the well cap is
made to coincide with that of the
pier and not with that of the well.
Such positioning nullifies the effect of
the minor shifts which might have
occurred during well sinking.
p z(Kp Ka)
zK '
z DPD DK '
or
1 2
12
D2 K ' 2DK ' D1
1
(PB) m ax DK '(D
2D1)
2
Taking moment about E
2
Solving for D1
(1)
2D1 3H 1 9H 2 1 2D(3H 1 D)
1
1
(2)
(1 2)
1
D3
(PB) m ax
'(KP Ka)
6
HD
Normally around the w ell, scouring
takes place.
Beyond the w ellsurroundings, the
uncovered soil acts as a surcharge.The
surchargedepth D2 is verydifficult to
assessand may be assumed to be equal to
half the normaldepth of scour.The
pressuredistribution is shownin
Fig(b).The
equivlant maximum resistanceforceis
then given as
1
D2 (D D2)
( PB ) m a x d
F
The factorof safetyshould not be less than 2.
The maximum pressuref at the base of the
w ell for theno overturning moment condition is
W
f
A
w here
W is the net direct load on the w ell base after
making allow ancefor buoyancy and skin friction
A Area of w ell base
z section modulus of the w ell base The
maximum foundation pressure
should be kept w ithin thesafe bearing capacity
of the soil assuming no tension occursat the base.
Pa
d
2F
or
y
' K' y
2FPa
'
K' d
1.
2.
3.
Rectification of Tilt
1.
2.
3.
4.
5.
6.
7.
Eccentric grabbing
Eccentric loading
Water jetting
Arresting the cutting edge
Pulling the well
Strutting the well
Pushing the well by jacks