Académique Documents
Professionnel Documents
Culture Documents
GUJARAT
TECHNOLOGICAL
UNIVERSITY
PREPARED BY
1.ALPA MAISURIA 140490714011
GUIDED BY
Prof. HIREN RAHOD
CIVIL ENGG. DEPARTMENT
S.N.P.I.T & R.C
1
Content
Overview of project planning
Major steps in project planning
Project planning : Work break down structure
Scheduling Techniques
2
Select project
Major Steps in
Project Planning
Continue.
Continue.
Continue.
Projects are rarely carried out in a vacuum. There is usually some kind of
infrastructure into which the project must fit. Where the project manager are
new to the organization , they must find out the precise nature of this
infrastructure.
Step 2.1: Identify relationship between the project and strategic planning
Step 2.2 : Identify installation standards and procedures.
Step 2.3 : Identify project team organization.
Continue.
The general purpose of this part of planning operation is to ensure that the appropriate
methods are used for the project.
Step 3.1 : Distinguish the project as either objective- product driven
Step 3.2 : Analyze other project characteristics ( including quality based ones)
Step 3.3 : Identify high level project risks
Step 3.3 : Take into account user requirement concerning implementation.
Step 3.4 : Select development methodology and life cycle approach.
Step 3.5 : Review overall resources estimates
Continue.
The more detailed planning of the individual activities now takes place. The longer term
planning is broad and in outline, while the more immediate tasks are planned in some
detail.
Step 4.1: Identify and describes project products ( or deliverables )
Step 4.2 : Document generic product flows
Step 4.3 : Record product instance
Step 4.4 : produce ideal activity network
Step 4.5 : Modify the ideal to take into account need for stages and checkpoints.
Continue.
Continue
Step 9 & 10 : Execute plan / lower level of planning
Once the project is underway, plans will need to be drawn up in greater
detail for each activity as it becomes due. Detailed and lower level of
planning of the the later stages will need to be delayed because more
information will be available nearer the start of the stage.
Project planning is an iterative process. As the time approaches for the
particular activities to be carried out they should be re-planned in more
detail.
11
Specification
(HOW)
OBS (WHO)
ORGANISATIONA
L BREAK DOWN
STRUCTURE
CBS (HOW
MUCH)COST
BREAK DOWN
STRUCTURE
SCHEDULING
12
13
14
15
Mathematical Analysis
PERT
Program Evaluation and Review Technique
CPM
Critical Path Method
Sometimes treated synonymously
All are models using network diagrams
16
Network Diagrams
Two classic formats
AOA: Activity on Arrow
AON: Activity on Node
Each task labeled with
17
Node Formats
18
Network Diagram
The distinguishing feature of a Network Diagram is that the ordering of Tasks is shown
by connecting with its predecessor and successor tasks. tasks.
Continue..
You would use a Network Diagram when Project Tasks:-
Are well defined and have clear beginning and end point
Are ordered
Continue.
Advantages
Show precedence well
Reveal interdependencies not shown in other techniques Ability to calculate critical
path
Ability to perform what if exercises
Disadvantages
Default model assumes resources are unlimited
You need to incorporate this yourself (Resource Dependencies) when determining the real
Critical Path
Difficult to follow on large projects
21
One of the most difficult and most error prone activities when constructing a
Project Schedule is the determination of the TIME DURATION for each task
within a Work Breakdown Structure (WBS), specially when there is a high degree
of complexity and uncertainty about a task.
PERT is a technique that uses Optimistic time (O), Pessimistic time (P) and
Realistic Time (R) estimates to calculate the EXPECTED TIME (ET) or a
particular task.
22
Continue
The Optimistic time (a) and Pessimistic time (b) reflects the
minimum and maximum possible periods of time for an activity to
be completed.
The Realistic time (r) or the Most likely time , reflects the Project
managers Best Guess of the amount of time required for a task
completion.
23
PERT Formula
Combined to estimate a task duration
24
PERT Formula
Confidence Interval can be determined
Based on a standard deviation of the
expected time
Using a bell curve (normal distribution)
25
SLACK TIME:-The Slack Time available for any Task is equal to the difference between the
Earliest completion Time (ECT) and the Latest Completion Time (LCT)
SLACK TIME = (LCT ECT)
CRITICAL PATH:- Is a sequence of Dependent Tasks that have the Largest sum of Estimated
Time (ET). IT is the Path that has no Slack Time built in.
The Critical Path on PERT chart is shown with thick Dark line.
Continue.
27
28
Continue.
Advantages
Accounts for uncertainty
Disadvantages
Time and labor intensive
Assumption of unlimited resources is big issue
Lack of functional ownership of estimates
Mostly only used on large, complex project
29
Continue.
The process for determining and optimizing the critical path
Note: Critical Path may change to another as you shorten the current
30
31
Bar Charts
Milestone Chart
Gantt Chart
Lines of balance (LOB) techniques
32
Gantt chart
A graphical representation of a Project that shows each task as a horizontal bar
whose length is proportional to its time for completion.
In the GANTT Chart Time is displayed on the horizontal axis and the Tasks/
Activities are arranged vertically from top to bottom, in order of their start dates.
A detailed GANTT Chart for a large project might be quite complex and hard to
understand. To simplify the chart Project manager can combine related activities
into one Task.
33
Continue.
GANTT CHART do not show how tasks must be ordered (precedence) but
simply show when a task should begin and should end
GANTT Chart is often more useful to for depicting relatively simple projects or
sub projects of a large project, the activities of a single worker, or for monitoring
the progress of activities compared to scheduled completion dates..
34
Continue.
35
Continue.
Disadvantages
Easily understood
Easily created and maintained
Note: Software now shows dependencies among tasks in Gantt charts
In the old days Gantt charts did not show these dependencies, bar
36
Milestone Chart
Milestone charts are the modification over the
original gantt charts
Continue.
38
Line of balance
A conventional network technique applied to
develop and control a single batch.
It was developed as a production planning tool
before PNTs.
It has a much less wide application area.
39
Requirements of Lob
Identifiable stages in production to exert managerial control.
Known manufacturing times between stages.
Delivery schedule.
Resources can be varied as required.
40
THANK U
41