Académique Documents
Professionnel Documents
Culture Documents
MANAGEMENT
2
GROUP
ND
Farizan
1210931012
Mustaqim
2nd GroupSlides
Entrepreneur
Hafizh Jafri
1210932003
IndahAlbani
12110931020
Putri
Focusing Discuss
Project Management
2nd Group
Impresario
Slides
2nd Group
Cost Estimate
Direct labour
Direct cost
Direct materials
Direct expenses
Overhead costs
Contingency sum
Escalation
Mark-up for profit
Selling price
2nd Group
Impresario
Slides
Direct costs
costs that can be directly attributed to project work. These are also variable costs,
because their rate of expenditure depends on the intensity of project activity. When
no work is being done on the project, there are no direct costs
Indirect
costs costs
that must be incurred by the organization to
accommodation, insurances, maintenance, accountants,
Direct
The Labour
wages and
2nd Group
Impresario
Slides
Direct materials
Equipment, materials and bought-out services used specifically on the project
Direct expenses
Travel, accommodation and other cost chargeable specifically to the project. Can
include the hiring of external consultant
Contingency sum
Usually calculated as a small percentage of above-the-line cost, in an attempt to
compensate for estimating errors and omissions
Escalation
An addition to allow for costs that increase with time as a result
ination
There are various ways in which
they can be calculated and their
levels
are
often
judged
according to the strength of the
competition and what market
will stand
of annual cost
The estimated costs of items that are not included in the quoted price which might
have to be charged extra if the need for them is revealed as project work proceeds
Impresario
2nd GroupSlides
Classification of Estimates
According to Confidence
Ballpark
estimates
Comparative
Estimate
Feasibility
estimates
Definitive
estimates
cannot
be
made
until
most
can be derived only after
as their name implies, are
design
work
has
been
a significant amount of
made by comparing work to
finished, all significant
preliminary
project
design
be done on the new project
purchase
orders
have
been
has been carried out
or one of its tasks with
placed at known prices and
similar work done on
work on the project is well
previous projects
advanced or nearing
completion
The degrees of accuracy quoted in these examples are about as good as could ever be expected. It is very likely
that many organizations will assign wider limits. It is also common to find asymmetric limits, slewed about zero. A
company might, for example, work on the assumption that its ballpark estimates are accurate to within +50 or 10
per cent.
Impresario
2nd GroupSlides
Our Philosophy
VERSION CONTROL OF PROJECT COST ESTIMATES
For example, suppose that a project specification were to be developed and given the
serial number X1234. As different strategies and solutions are investigated, the relevant
versions of the project specification would be numbered X1234 case A, X1234 case B
if an error resulted in the re-issue of a cost estimate for project X1234 case B, the
corresponding estimate would be labelled X1234 case B, revision 1 (the original would
be issued at revision 0).
10
Our Philosophy
Ways of approaching cost estimating
Top-down
Very early in the project life history, there will be outline proposals for the nature and
scope of the project, but certainly no detailed task list or comprehensive work
breakdown
Bottom-up estimating
This method can only take place when a good project specification exists and a fairly
complete task list has been compiled
11
Estimating
Format
General purpose
Cost estimating format
General
purpose
Project cost and
price summary
format
Large Project
Small
project
Our Services
15
Grade 1
Grade 2
Grade 3
Grade 4
Grade 5
Grade 6
2nd Group
Impresario
Slides
16
17
2nd Group
Impresario
Slides
18
2nd Group
Impresario
Slides
20
2nd Group
Impresario
Slides
21
External factors
event and conditions that lie outside the control of the project
management organization.
acts of god all project are subject to risk, the following are
just four from a long catalogue of happenings that can be
classified as acts of god :
An earthquake devastates a project organizations
headquarters
A hurricane and flood put a project site under a metre of
water and delay the start or ruin the work in progress
An influenza epidemic puts half the project workforce out of
action
The project manager (a keen golfer) is struck by lightning
2nd Group
Impresario
Slides
Working Factor
working factors can have a profound effect on the
project outcomes, the project manager will often
find that some or all of them are determined by
managers or circumstances over which the project
manager has no authority or power
Output
External factors
23
2nd Group
Impresario
Slides
24
2nd Group
Impresario
Slides
25
2nd Group
Impresario
Slides
26
2nd Group
Impresario
Slides
Schedule
A schedule is obtained by doing additional
work on the initial plan, so that resources
needed to carry out all the project activities
are taken into account
28
2nd Group
Impresario
Slides
29
2nd Group
Impresario
Slides
30
None of the money invested in the failed IT software and systems design will be
recoverable.
IT hardware is not best known as an investment proposition, and depreciates so rapidly
that it becomes obsolete and worthless in a matter of a year or two, if not worse.
Staff who have been affected by the failed project, some of whom might have resisted the
proposed changes, will be demotivated, demoralized.
Far from achieving the expected benefits, the failed project will have damaged the
organizations performance, prestige and prospects.
Customers will suffer reduced or interrupted service.
2nd Group
Impresario
Slides
4 Important Areas
INTRODUCTION TO PROJECT FINANCIAL
APPRAISAL
METHODS
the simple payback method
uses one of a range of techniques based
on discounting the forecast cash flows
31
32
the initial acquisition cost of software, plant or equipment needed for the project (this
might be a single purchase payment, a series of phased payments, or payments scheduled
against a leasing or rental plan; the differences between these options are important not
only for the timing of payments, but also for the tax implications);
interest payable on financing loans;
if the project is for new machinery or plant, the costs of operating and maintenance;
commissioning, debugging and other implementation costs;
staff or operator training costs;
all other expenses and fees payable as a result of the new project.
2nd Group
Impresario
Slides
33
Against these items of expenditure must be balanced all the savings and
revenues (the project benefits) that the new project is expected to generate
savings in operating and maintenance costs achieved by replacing old methods with the
new project (for example, although a stainless steel tower bought to replace an old steel
tower might be expensive initially it would have a longer life and would not need regular
repainting);
revenue from the sale of products or services made possible by the new project;
proceeds from the sale of assets no longer required as a result of the new project;
proceeds from the eventual sale of the new project hardware, some time in the future,
after
the new project has reached the end of its economic life.
2nd Group
Impresario
Slides
Individual Service
SIMPLE PAYBACK METHOD
34
2nd Group
Impresario
Slides
sensitivity analysis
36
4 Important Areas
PROJECT FUNDING
Project owners
viewpoint
Project funding from
the contractors
viewpoint
37
2nd Group
Impresario
Slides
THANK YOU
2ND GROUP