OUTLINE OF PRESENTATION
INTEGRATION
PROJECT CHARTER
LOCATION MAP

SCOPE
PROJECT BRIEF

16 ELEMENTS OF EXECUTION PLANNING

PROGRAMMING & PLANNING


PROJECT TABLE OF ORGANIZATION
SAFETY PROCEDURES AND INSPECTIONS
QA/QC & INSPECTION PROCEDURES
DESIGN REVIEW, COORDINATION AND DETAILING
BUILDING SERVICES ENGINEERING/ COORDINATION
BUILDING INFORMATION MODELING & COORDINATED SERVICES DRAWINGS
BUILDABILITY, VALUE ENGINEERING AND INNOVATION
CONSTRUCTION METHODS & TEMPORARY WORKS
CONSTRUCTION PHASING AND SITE LOGISTICS
PROCUREMENT
WORKS PACKAGING AND PROCUREMENT MANAGEMENT
COMMERCIAL INPUT ON SUBCONTRACT / SUPPLY CONDITIONS

PROJECT OPERATING BUDGET


SUSTAINABILITY, CSR AND ENVIRONMENT
RISK MANAGEMENT

PROJECT CHARTER
PROJECT TITLE
PROJECT OWNER

: CENTRIO TOWER
: CDO GATEWAY CORP.

DESIGNERS/CONSULTANTS:

Architectural

: G&W Architects,
Engineers & Consultants

Structural

: Sy^2 + Associates

Mechanical/Fire Protection

: RD Aguilos

Plumbing/Sanitary

: CL Madriaga Engineers

Electrical Consultant

: IRAIDO Tech. Leader, Inc

GENERAL CONTRACTOR

: Makati Development Corp.

ESTIMATED PROJECT COST : Php 702 065 382.85


(3 flrs Podium + 21 flrs Residential)

LOCATION MAP

CENTRIO TOWER
PROJECT

THIS
SITE

CO
RR
AL
ES

AV
EN
U
E

GEN LUNA
STREET

JR
IV E
RA
STR
EET

J. E
BA
RL
E

ST
RE
ET

RAM
ON
AVI
CHA
DA
VEZ
TOW
STR
ER
EET
ASP

IRA

CENT
RIO M
ALL

PROJECT BRIEF
Lot Area

3,936.14 m2

Gross Floor Area (GFA)

20,641.53 m2

Covered Floor Area (CFA)

25,450.83 m2

Net Saleable Area (NSA)

15,881.98 m2

Gross Leasable Area (GLA)

133.34 m2

Gross Parking Area (GPA)

4,809.30 m2

Residential Gross Floor Area


(RGFA)

20,304.16 m2

Building Efficiency

62.93 % (NSA+GLA/CFA)

Residential Footprint
Efficiency

78.22% (NSA / RGFA)

No. of Floors

24 Floors (Ground floor to Roof Deck)

Parking

2 Floors ( Ground Floor to Second


Floor)

Amenities / Residential

1 Floor

Residential Floors

3rd Floor to 23rd Floor


(21 floors)

Studio

292 Units (55.94%)

1 Bedroom

188 Units (36.02%)

2 Bedrooms

42 Units (8.05%)

TOTAL

522 Units

(3rd floor)

Residential Units

1/16

PROGRAMMING AND PLANNING

PROGRAMMING AND PLANNING


DESIGN UPDATES
MILESTONES
PROJECT SCHEDULE

1/16

DESIGN UPDATES

1/16

MILESTONES
MILESTONE DATES
ACTIVITY

TARGET

GROUND BREAKING
BORED PILE

July 19, 2013

COMPLETION OF EXCAVATION

June 4, 2014

NTP AWARD OF SUPERSTRUCTURE

July 30, 2013

FIRST CONCRETE POURING

April 7, 2014

TOPPING OFF

May 14, 2015

WATER TIGHTNESS

July. 22, 2015

TESTING AND COMMISIONING

Dec 15, 2015

ENERGIZATION OF PERMANENT
POWER

Dec 20, 2015

PERMANENT WATER CONNECTION

Nov 15, 2015

ELEVATOR OPERATION

November 15, 2015

ACTUAL

STATUS /
REMARKS

Feb. 19, 2013

DONE

July 11, 2013

DONE

Dec. 12, 2013

DONE

1/16

MILESTONES
MILESTONE DATES
ACTIVITY

START OF HANDOVER TO OWNER & CRU

FIRE SAFETY AND INSPECTION CERTIFICATE (FSIC)

OCCUPANCY PERMIT

PROJECT COMPLETION / HANDOVER TO AVIDA

TARGET

March 15, 2016

June 10, 2016

January 15, 2016

December 20, 2016

PROJECT TECHNICAL CLOSE-OUT

March 20, 2017

PROJECT FINANCIAL CLOSE-OUT

May 20, 2017

ACTUAL

STATUS /
REMARKS

2/16

PROJECT SCHEDULE

BID RESULT
MDC BUDGET

62,252,141.05

MOMENTUM

106,257,047.64

ACTUATE

131,642,032.30

ARN BUILDERS

337,964,330.13

2/16

PROJECT TABLE OF ORGANIZATION

TABLE OF ORGANIZATION
MANPOWER SCHEDULE

2/16 CENTRIO TOWER TABLE OF ORGANIZATION


LEGEND:
GEOGRAPHICAL / SUPPORT TEAM

Hired

COG
COG 1
1 HEAD
HEAD
M. C.
M.
C. MONSALVE
MONSALVE

For
Hiring/Replacement

OPCEN BASED (SHARED)

PLANNING
PLANNING HEAD
HEAD
I.S.
I.S. SUERTE
SUERTE

VISMIN
VISMIN OPCEN
OPCEN HEAD
HEAD
A.
A. E.
E. MAUS
MAUS

CDO BASED (SHARED)


PROJECT BASED

PROJECT
PROJECT MANAGER
MANAGER
TBH
TBH

VISMIN
VISMIN CRFG
CRFG
C.T.
C.T. INDIANO
INDIANO

CG
CG VISMIN
VISMIN OPCEN
OPCEN
MA.
MA. FE
FE TRACES
TRACES

VISMIN
VISMIN COSG
COSG
BENJAMIN
BENJAMIN JOSE
JOSE

PROJECT
PROJECT IN
IN CHARGE
CHARGE
A.
A. S.
S. ALVAREZ
ALVAREZ
Q.S.
Q.S. DEPT.
DEPT.

ACCOUNTING
ACCOUNTING DEPT.
DEPT.

ADMIN
ADMIN DEPT.
DEPT.

E.C.P.D.

PROJECT
PROJECT CONTROLLER
CONTROLLER
ASST.ADMIN. OFFICER
QUANTITY
QUANTITY SURVEYOR
SURVEYOR
(CONCURRENT)
(CONCURRENT) ASST.ADMIN. OFFICER
IRISH
L.
IRISH P.
P. LOMO
LOMO
L. D.
D. NACALABAN
NACALABAN
C.T.
C.T. INDIANO
INDIANO
ASS.
ASS. QUANTITY
QUANTITY SURVEYOR
SURVEYOR
E.B.
E.B. AMORES
AMORES

DOCTOR
DOCTOR

TIMEKEEPER
TIMEKEEPER

IT
IT SPECIALIST
SPECIALIST

DOCS CONTROLLER

TBH
TBH

TBA
TBA

As of April 28, 2014


Required- 41
Hired
- 24
Balance
- 17

TBA
TBA

DM
DM MASLA
MASLA

T.S.D. DEPT.

QA DEPT.

QUANTITY
TSD
QUANTITY ASSURANCE
ASSURANCE EHS
EHS SUPERVISOR
SUPERVISOR
TSD -- COORDINATOR
COORDINATOR
RALPH
R. G. RODRIGUEZ
S. A. TORRES
RALPH LAO
LAO

PURCHASING
PURCHASING SPECIALIST
SPECIALIST
TBA
TBA

ARCHITECTURAL
ASST. QUALITY
QUALITY ASSURANCE
ASSURANCE PROJECT
PROJECT NURSE
NURSE
ARCHITECTURALASST.
JETHRO
TBH
J.
JETHRO VILLAROJO
VILLAROJO
TBH
J. D.
D. TAPPOL
TAPPOL

WAREHOUSEMAN
WAREHOUSEMAN
AL
AL C.
C. MAGHANOY
MAGHANOY

MEPF
MEPF

SAFETY OFFICER

TBA
TBA

TBH
TBH

WAREHOUSE
WAREHOUSE AIDE
AIDE
R.
R. Q.
Q. MABAGAL
MABAGAL

CADD
CADD OPERATOR
OPERATOR

SAFETY OFFICER

DRIVER
DRIVER

CADD OPERATOR
CARL ALABA

C.O.
C.O. MANDAL
MANDAL

PURCHASING

EHS DEPT.

TBA
TBA

C.A.
C.A. GASATAYA
GASATAYA

EQUIPMENT
EQUIPMENT ENGR.
ENGR.

MAINTENANCE
MAINTENANCE TEAM
TEAM

UTILITY
UTILITY

R.
R. R.
R. BOYLES
BOYLES
PROJECT
PROJECT SUPERINTENDENT
SUPERINTENDENT
TBN
TBN

M.E.F.P.

CQC

SURVEY TEAM

BY
BY THIRD
THIRD PARTY
PARTY

SURVEY
SURVEY HEAD
HEAD
E.
E. SINGAYAN
SINGAYAN

REBAR
REBAR ENGR
ENGR
TBH
TBH

FORMWORKS
FORMWORKS ENGR
ENGR
RYAN
RYAN E.
E. ILOGON
ILOGON

SURVEY
SURVEY AIDE
AIDE
A.B.
A.B. BLANILA
BLANILA

CONCRETE
CONCRETE ENGR
ENGR
TBH
TBH

CONCRETE
CONCRETE ENGR
ENGR
LITO
LITO BITANTOS
BITANTOS

FOREMAN
FOREMAN
ARTHUR ANJAO
ANJAO
ARTHUR

GENERAL
GENERAL FOREMAN
FOREMAN
LIBRANDO
LIBRANDO REPUELA
REPUELA

FOREMAN
FOREMAN
ANGELITO
ANGELITO SALIGUMBA
SALIGUMBA

SURVEY
SURVEY AIDE
AIDE
A.C.
A.C. AJAN
AJAN

EQUIPMENT
EQUIPMENT //
MAINTENANCE
MAINTENANCE HEAD
HEAD

MEFP
MEFP HEAD
HEAD
TBH
TBH
ELECTRICAL/AUX.
ELECTRICAL/AUX.
TBH
TBH

2/16

MANPOWER SCHEDULE
2014

2015

2016

2/16

MANPOWER SCHEDULE
2014

2015

2016

3/16

SAFETY PROCEDURES AND INSPECTION

SAFETY PROCEDURES AND


INSPECTION
FIRE SAFETY
SECURITY MEASURES
DELIVERY PROCEDURES
EXISTING EXTERIOR BOARD UP/ FENCE
SAFETY NET SEQUENCE

3/16 SAFETY PROCEDURES AND INSPECTION

SAFETY MEASURES
The following Safety measures shall be strictly implemented:
Provide standard road signs where heavy equipment and
trucks will be crossing.
Material Safety Data Sheet (MSDS) shall be submitted by the
subcontractors for approval prior to work execution.
The subcontractors shall be responsible for providing the
necessary personal protective equipment (PPE) as deemed
required by their work scope.
The subcontractors shall observed the safety rules and
regulations being implemented by MDC while inside the project
site.

3/16 SAFETY PROCEDURES AND INSPECTION

FIRE SAFETY
2 x 5-kg capacity dry chemical (multi-purpose) fire
extinguisher shall be provided whenever necessary within the
construction site. One (1) fire extinguisher for every equipment
(i.e., generators, welding machine, gas cutting, etc.) shall be
provided.
A fire watch/safety enforcer shall be provided in areas
where welding and gas cutting activities are being performed.
Water supply and distribution facilities for fire fighting
purposes shall be provided at construction site.
Smoking shall be prohibited within the construction premises
except at the designated smoking area.

3/16 SAFETY PROCEDURES AND INSPECTION

SECURITY MEASURES
The following Security Measures shall be strictly implemented:

Workers will be required to wear Identification cards and color


coded uniforms before entering and while inside the
construction site.
All contractors shall assign skeletal forces during holiday
seasons.
Workers are prohibited from loitering inside and within the
periphery of the project site.
Dayshift and nightshift guards shall be posted in strategic
locations inside the premises to:
o Check and report any person seen loitering during and after
working hours
o Check and report any unauthorized usage of equipment
o Conduct regular inspection within the project premises and
report any violation of the house rules and regulations.
In addition, all security guards are required to frisk all
employees & workers entering and leaving the project site for
security reasons.

3/16 SAFETY PROCEDURES AND INSPECTION

DELIVERY PROCEDURES
All delivery vehicles shall be allowed access only through

the construction gate along Corrales Avenue.


Security Guard at the gate shall log the delivery details and
communicate with MDC for proper unloading, hauling and
warehousing.

3/16

SAFETY PROCEDURES AND INSPECTION

EXISTING EXTERIOR BOARD UP/FENCE

VIEW FROM CENTRIO


CENTRIOSTP
MALL

CENTRIO TOWER
SEDA
VIEW FROM CENTRIO
PARKING ENTRANCE

CORRALES AVE
NUE
VIEW FROM CORNER
CORRALES AVE. & CENTRIO
PARKING ENTRANCE

VIEW FROM CORRALES


AVE.

Residential area
made of light
weight materials

3/16

SAFETY NET

SAFETY
NET

4/16

QA/QC & INSPECTION PROCEDURES

QA/QC & INSPECTION PROCEDURES


INITIAL PHASE (1ST CONTROL)
INTERMEDIATE PHASE (2ND CONTROL)
FINAL PHASE (3RD CONTROL)
CURING TANK

4/16

QA/QC & INSPECTION PROCEDURES

INITIAL PHASE (1st CONTROL)


start

SUB
CONTRACTOR TO
PREPARE
SUBMITTAL
REVIEW FORM:
1.Material
Samples
2.Testing
Certificates
3.Installation
Methodology
4.Tolerances
5.Equipment
Requirement
6.Hazard Analysis
7.Forms
8.Schedules

DOCUMENT
CONTROLLER to
receive submittals
and logs.

QA / QC
to review, verify and
comment if submittal is
as per approved plans
and specifications.

QA / QC to verify
comments and forward
to SUB CONTRACTOR

NO
PROJECT MANAGER /
PIC
to review and forwards
to CONSULTANT for
APPROVAL.

APPROVED
?
YES
SUBCONTRACTOR
may proceed to
work

end

PM / PIC
reviews and
evaluates
comments

4/16

QA/QC & INSPECTION PROCEDURES

INTERMEDIATE PHASE (2nd CONTROL)


start

SUB CONTRACTOR
TO PREPARE WORK
REQUEST / WORK
INSPECTION
REQUEST
1.Structural / Civil
Works
2.Others

DOCUMENT
CONTROLLER to
receive and logs.

FIELD OPERATION
GROUP (FOG/MDC)
to check and verify
QA / QC to check and
verify if work is done
as per approved plan
and specifications.

FOG to check and


verify if rectifications
works is done as per
plan and specification

PROJECT MANAGER /
PIC to review and verify

NO
APPROVED?
YES
SUB-CONTRACTOR TO
PROCEED WORK

end

SUB CONTRACTOR to
rectify and repair
comments

4/16

QA/QC & INSPECTION PROCEDURES

FINAL PHASE (3rd CONTROL)


start

SUB CONTRACTOR to
submit WORK ACTIVITY
COMPLETION REPORT

DOCUMENT
CONTROLLER to
receive submittals
and logs.

FIELD OPERATION
GROUP (MDC) to
check and verify

QA / QC to check and
verify if work is done
as per approved plan
and specifications.

FOG checks and


verify if work is
rectified and
forward to QA/QC
NO

APPROVED?

QA / QC to issue
PUNCHLIST or
DEFECT list

YES
PROJECT
MANAGER / PIC
issues Work Activity
Completion

end

SUB-CONTRACTOR to
rectify items in the
PUNCHLIST / DEFECT
list.

PROJECT MANAGER / PIC


approves and forward
PUNCHLIST to Sub-Contractor
for rectification.

4/16

PROPOSED SAMPLE ROOM FOR CURING TANK


EXISTING
WALL

4.0m

6MM 50X50
WIREMESH
WALL

2.5m

1.0m

3.0m
3.0m

CURING
TANK

4/16

PROPOSED CURING TANK

1.0m

3.0m

4/16

PROPOSED FORMS ACCESSORIES STOCKING PER FLOOR

1.2m

3.0m

2.0m

5/16

DESIGN REVIEW, COORDINATION & DETAILING

DESIGN REVIEW, COORDINATION &


DETAILING
Continue review of plans and coordination of approved
construction drawings and detailing prior to implementation at site.

6/16

DESIGN REVIEW, COORDINATION AND DETAILING

Review
FCD Plans/Drawings
(by MDC Operation &
Subcontractors)

Seek alternative
Solutions
& Incorporate
Comments of
MDC Engg. &
Consultants

Conflicts,
Clashes &
Incomplete
Details

MDC/
Subcontractors
To Formulate
YES Solutions and
Shop drawings

NO

Approved
Resolution
& Drawings
Approval
should
By MDC
be signed
Engineering,
by
Consultants
MDC Engg.,
& APMC
YES
Consultants
& APMC

NO

Implementation

7/16

ELEMENTS OF EXECUTION PLANNING

BUILDING SERVICES ENGINEERING /


COORDINATION
COG1 will coordinate with the planning and design team by
providing information relevant to architectural and engineering
works that need to be incorporated into the design (e.g. existing
location of tapping points for water supply, sewers, power
supply, actual survey data).
COG1 will also provide the planning and design team with local
regulatory requirements such as those of local utility providers
and local government unit (LGU)
services design.

that will affect the building

7/16

ELEMENTS OF EXECUTION PLANNING

BUILDING INFORMATION MODELLING &


COORDINATED SERVICES DRAWINGS
BUILDING INFORMATION MODELLING

Bored piles, pile caps, mat footings and columns will


be modelled using BIM software to eliminate conflicts and
ensure correct calumniation.
MEPFS will be modelled also using BIM software to
eliminate conflicts/clashes such as Electrical
pipes, Plumbing/Sanitary pipes and Mechanical ducting.

8/16

ELEMENTS OF EXECUTION PLANNING

BUILDABILITY, VALUE ENGINEERING


& INNOVATION
Review of the design as to buildability and efficiency, with
careful analysis on the compatibility of the design with
structural, architectural and building services.
Apply value engineering with innovative construction
methodologies not just to lessen cost but to expedite
completion of the project

9/16

ELEMENTS OF EXECUTION PLANNING

CONSTRUCTION METHODS
AND TEMPORARY WORKS
FORMWORKS CONCRETING SEQUENCE
STRUCTURAL EXCAVATION SEQUENCE
FOUNDATION POURING SEQUENCE
CONCRETING OF GOUND FLOOR
EXTERIOR PC WALLS
STRUCTURAL CONCRETING SEQUENCE

9/16 STRUCTURAL EXCAVATION SEQUENCE

9/16

FOUNDATION POURING SEQUENCE

RETAINING WALL
VOL = 76.36m3
April 20, 2014

9/16

FORMWORKS & CONCRETING SEQUENCE

Total Contact Formworks Area = 61,173.73 m2


Total Formworks Equipment to be provided= 3164 m2
Total Translab Area = 20,065.50
m2
Slab Concrete Total Volume = 5,402.68 m3
Slab Concrete Total Volume/floor = 234.89
m3
Pouring Cycle = 2 floors/month
PODIUM (G ND & 3 fr FLRS) 2
FLOORS
Total Floor Area = 5,684.94 m2

9/16

CONCRETING OF GROUND FLOOR

10/16

STRUCTURAL CONCRETING SEQUENCE


TOPPING OFF
(MARCH 14, 2015)

PRECAST
AND
CONCRETE
CYCLE: 15
DAYS/FLOOR

4TH
JACKUP:
2DAYS

ARCHITECT
URAL

STRUCTUR
AL

RD : OCT 15, 2015


24TH : OCT 1, 2015
23RD :SEP 16, 2015

3RD
JACKUP:
2DAYS

21ST : AUG 15, 2015


19TH : JULY 21, 2015
17TH : JUNE 20, 2015

2ND
JACKUP: 2
DAYS

15TH : MAY 23, 2015


12TH : APRIL 22, 2015
10TH : MAR 24, 2015

1ST
JACKUP: 2
DAYS
INITIAL
JACKUP:
7DAYS

`
`

8TH : FEB 21, 2015


6TH : JAN 24, 2015
4TH : DEC 26, 2014
3

RD

: DEC 10, 2014

`
`
`
`

`
`
```

` FOUNDATION
CRANE

2ND: NOV 20, 2014


GF: NOV 8, 2014

RDRD
23
22TH
21TH
20TH
19TH
18TH
17TH
16TH
15TH
14TH
12TH
11TH
10TH
9TH
8TH
7TH
6TH
5TH
4TH
3RD
2ND

RD : March 14, 2015


23rd: March 5, 2015
21ST :FEB 9, 2015

19TH : JAN 16, 2015


17TH : DEC. 23, 2014
15TH : NOV. 29,
2014
12TH : NOV. 5, 2014

10TH : OCT. 12, 2014


8TH : SEPT 18, 2014
6TH : SEPT 6, 2014
4TH : AUG. 1, 2014
3RD : JULY 20, 2014

GF

2ND :JUNE 10, 2014


GF: APRIL 11, 2014

9/16

EXTERIOR PC WALL PANELSL PANELS

10/16

ELEMENTS OF EXECUTION PLANNING

CONSTRUCTION PHASING, TOWER


CRANES & SITE LOGISTICS
LOGISTIC & TOWER CRANE LAYOUT PLAN
VEHICULAR TRAFFIC FLOW
FORMS, REBAR AND CONCRETE USAGE
EQUIPMENT SCHEDULE

10/16

LOGISTIC AND TOWER CRANE LAYOUT


Existing CHB Fence
CLINIC

TOWER

TEMFACIL

POWER HOUSE
WAITING AREA

CORR
ALES
AVEN
UE

PEDESTRIAN
GUARD HOUSE

ENTRANCE / EXIT

4m

PRECAST CASTING BED

4m

9.3m

24m

REBAR FABRICATION

(5.0) P. 1 of 2

ARE
ARE
A
A

Int

ern

al
Cl i
mb
50
ing
M
JIB
TO
(M
WE
ax
RC
. lo
RA
ad
NE
10
(Lu
T&
fn
Tip
g-T
loa
yp
d3
e)
T)

REBAR
FABRICATION

Residential Area made of Light


weight materials

5/16

CONSTRUCTION PHASING AND SITE LOGISTICS

VEHICULAR TRAFFIC FLOW OF DELIVERIES OF MATERIALS ON SITE

TOWER

CORRALES

AVENUE

RO A
D

Residentia
l Area

CAP
ITOL

AREA

Residential Area made of


Light weight materials
(5.0) P. 2 of 2

10/16
CONSTRUCTION PHASING AND SITE
LOGISTICS
REBARS AND CONCRETE USAGE

10/16

CONSTRUCTION PHASING AND SITE LOGISTICS

EQUIPMENT SCHEDULE
Item

Equipment

Qty

Start

Finish

Remarks/Usage

Lufng Tower
Crane

March 30,
2014

Coming from
Davao Project

Mobile Crane
25T

March 15,
2014

Material Lifting

Construction
Elevator

Nov. 2,
2014

Material lifting
and workers

Day to day
transportation
requirement

Service Vehicle

Feb. 1,
2013

Generator
300kva

June 1,
2014

For emergency
brown-out

Transformer
100kva

Feb. 14,
2014

For construction
use

11/16

ELEMENTS OF EXECUTION PLANNING

PROCUREMENT
PROCUREMENT PROCESS FLOW

11/16

PROCUREMENT PROCESS FLOW

12/16

ELEMENTS OF EXECUTION PLANNING

WORKS PACKAGING &


PROCUREMENT MANAGEMENT
PROCUREMENT STRATEGY
PROCUREMENT STRATEGY & SCHEDULE

12/16

PROCUREMENT STRATEGY
MDC
CONTRACT
MECHANICAL

EXCAVATION
WORKS

SOIL TREATMENT

CIVIL/STRUCTURAL
ARCHITECTURAL
MEPF WORKS
WORKS
WORKS

PAPER BID

PAPER BID

PAPER BID
ARN BULIDERS
ACTUATE
AV PAMATONG
Momentum
Self Perform

PAPER BID

PAPER BID

Triplewell Con. Corp.


CDM

ELECTRICAL
Energy & Building
App.
Powerline Controls
Elec.
Energy Factors, Inc.
PLUMBING AND
Electrolyte
FIRE
PROTECTION
Engineering

HNH
KEVLAR
NOVICE
JS ASSOCIATE

ITEMS

EXCAVATION

CIVIL /
STRUCTURAL

ARCHITECTURAL

MEPF

STATUS

DONE

SELF PERFORM

SELF
PERFORM/SUBCO
N

AWAITING AWARD
FROM AVIDA

Marguad Trading
Alpa Plumbing
Works Inc.
Universal Macrotech
Triplewell
Construction

13/16

PROCUREMENT STRATEGY & SCHEDULE

Regular
Vendor
Not seen in Vendor
Search
Prospective New/Reactivate
Vendor

Admin
TARGET
PROCUREMEN
CONTRACTORS/SUPPLIERS
DATE OF
STATUS
T STRATEGY
AWARD

HNH BUILDERS
NOVICE CORPORATION
PAPER BID
1/26/2014
AWARDED
JS ASSOCIATES
HNH BUILDERS
NOVICE CORPORATION
PAPER BID
1/26/2014
AWARDED
JS ASSOCIATES
HNH BUILDERS
NOVICE CORPORATION

PROJECT :AVIDA CENTRIO TOWER


LEGEND:

CORRALES AVENUE, CAGAYAN DE


LOCATION :
ORO CITY

SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKS


as of :3/8/2014

CONTRACT
PACKAGE

WORK PACKAGES

FIXED LUM SUM (FLS)


CP-FLS-1

Construction of Temfacil

CP-FLS-2

Construction of Crane Foundation


Excavation and Disposal
Pile Hacking

CP-FLS-3 and Disposal

PAPER BID

1/26/2014

ADMIN

1/26/2014

AWARDED

JS ASSOCIATES

Clearing and Grubbing


Backfilling and Compaction of Imported
Materials
Base
Course - Imported Materials - filling to
beds
Formworks
Installation
Fabrication and Installation
of Rebars
Polythelene Sheet
CP-FLS-4

Cast in Place Concrete

ADMIN WORKERS

ON-GOING

13/16

PROCUREMENT STRATEGY & SCHEDULE

Regular
Vendor
Not seen in Vendor
Search

Prospective New/Reactivate
Vendor

Admin
TARGET
CONTRACT SOIL TREATMENT WORKS
PROCUREMEN
GEN PEST MANAGEMENT
WORK PACKAGES
CONTRACTORS/SUPPLIERS
DATE OF
STATUS
CP-FLS-5
PARTNERING
4/23/2014
PACKAGE
T STRATEGY
SERVICES
AWARD
JAN OWEN
FIXED LUM SUM (FLS)
MARTIN

CONSTRUCTION
CORPORATION
THI ENGINEERING SERVICES
RICH-FREE TRADING &
DEVELOPMENT
THERMAL & MOISTURE PROTECTION
SHASTA
Damproofing
MULTI DEVELOPMENT
CP-FLS-5
PAPER BID
3/30/2014
DORON BUILDERS &
Polyethelene Sheet, min.
CONSTRUCTION SUPPLIES
6mil thickness; To Slab on Grade
GLOSCORE PHILIPPINES
CONSTRUCTION, INC.
AC TROJAN INDUSTRIES, INC.
EC STRUCTURAL
COMPOSITES, INC.
GREEN BAY INDUSTRIAL
TRADING COMPANY
GEO-TRANSPORT AND
CONSTRUCTION, INC.
SUPPLY & DELIVERY OF READY MIXED
HORIZON CONCRETE
CP-FLS-6
CONCRETE
PAPER BID
1/26/2014 AWARDED
PRODUCTS, CORP.
8,000 psi, 6,000 psi, 5,000 psi, 3,000 psi
AV PAMATONG
OMMIX
PROJECT :AVIDA CENTRIO TOWER
LEGEND:
CORRALES AVENUE, CAGAYAN DE
LOCATION :
ORO CITY
SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKS
as of :3/8/2014

13/16

PROCUREMENT STRATEGY & SCHEDULE

Regular
Vendor
Not seen in Vendor
Search
Prospective New/Reactivate
Vendor

Admin
TARGET
PROCUREMEN
CONTRACTORS/SUPPLIERS
DATE OF
STATUS
T STRATEGY
AWARD

JAN OWEN MARTIN


CONSTRUCTION
CORPORATION
RICH-FREE TRADING &
DEVELOPMENT
TRADETEK RESOURCES, INC.
5/10/2014
PAPER BID

PROJECT :AVIDA CENTRIO TOWER


LEGEND:

CORRALES AVENUE, CAGAYAN DE


LOCATION :
ORO CITY

SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKS


as of :3/8/2014

CONTRACT
PACKAGE

WORK PACKAGES

FIXED LUM SUM (FLS)

Cementitious Deck
CP-FLS-7 Supply of Hardener

REBTRADE INTERNATIONAL
CORP.

CP-FLS-8

Supply of Skim Coat (Rubbed Concrete)

TECHNORESINS INDUSTRIAL
INC.
MGS BESSER BLOCK, INC.
NOVTEK CORPORATION
ERN CORPORATION
TECHNOTRUST CORP.

PAPER BID

8/2/2014

ADMIN WORKERS

ADMIN

5/31/2014

Pre-cast Concrete
CP-FLS-9

Precast
wheel stops

13/16

PROCUREMENT STRATEGY & SCHEDULE

Regular
Vendor
Not seen in Vendor
Search
Prospective New/Reactivate
Vendor

Admin
TARGET
PROCUREMEN
CONTRACTORS/SUPPLIERS
DATE OF
STATUS
T STRATEGY
AWARD

PROJECT :AVIDA CENTRIO TOWER


LEGEND:

CORRALES AVENUE, CAGAYAN DE


LOCATION :
ORO CITY

SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKS


as of :3/8/2014

CONTRACT
PACKAGE

WORK PACKAGES

FIXED LUM SUM (FLS)


Masonry
Finishes-Plastering
INSTALLATION OF TILES
CP-FLS-10

INSTALLATION OF STEEL DOORS


Installation
of Steel Doors with louvers
INSTALLATION OF WOOD
DOORS
INSTALLATION OF PVC DOORS

HNH
KEVLAR
ADMIN WORKERS
NOVICE

E.C. DAUGHSON, INC.


POWERBRIGHT ENTERPRISES
PHILGLOBAL ASIA INDUSTRIAL
CORPORATION
METAL WORKS
SSI METAL
LRC TRADING & ENGINEERING
Structural Metal
SERVICES
Framing - Elevator Hoisting Beam
DO ALL METAL INDUSTRIES
Metal
CP-FLS-11
Fabrications
GOMECO METAL
Steel
JEFF JAMES
Grating - recommended manufacturer
NORBENJAR ENTERPRISES
WEBFORGE - Arch
METRO STONERICH CORP.
Specs pg 16
WEBFORGE PHILIPPINES
AMSTEEL
AVECS CORP.

PAPER BID

05/9/2014

PAPER BID

05/30/2014

13/16

PROCUREMENT STRATEGY & SCHEDULE

Regular
Vendor
Not seen in Vendor
Search
Prospective New/Reactivate
Vendor

Admin
TARGET
PROCUREMEN
CONTRACTORS/SUPPLIERS
DATE OF
BIDDING
T STRATEGY
AWARD

DN STEEL MARKETING

PROJECT :AVIDA CENTRIO TOWER


LEGEND:

CORRALES AVENUE, CAGAYAN DE


LOCATION :
ORO CITY

SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKS


as of :3/8/2014

CONTRACT
PACKAGE

WORK PACKAGES

FIXED LUM SUM (FLS)

CP-FLS-12

SUPPLY AND INSTALLATION OF


ALUMINUM SPANDREL

ALI Recommended
Manufacturer/contractor Arch.
Specs page 48
UNION GALVASTEEL

PAPER BID

05/30/2014

PAPER BID

05/30/2014

PAPER BID

05/30/2014

PHILMETAL
REMACRIS BUILDERS
PZL CONSTRUCTION, INC.
NOVELL STEEL
MAKATI COVER-ALL AND
INTERIORS, INC.
12mm Thk Gypsum Board
ONEL BUILDERS RESOURCES,
CP-FLS-13 12mm Thk Moisture Resistant Gypsum INC. (OBRI) (Needs to Update)
Board
DRYWALL
INSUPHIL INDUSTRIAL
WORKS
LORETA RIGID URETHANE
Brand
INSULATION
for Gypsum Board: BORAL
KENT INTERNATIONAL
Arch.
CK BUILDERS
Specs page 85
SUPPLY AND INSTALLATION OF
GYPSUM BOARD - CEILING WORKS

SUPPLY & INSTALLATION OF WALL


COVERINGS
EIFS
CP-FLS-14
Dryvit
Systems, Inc. or BASF Wall Systems Arch

PIONEER

IRVINE

13/16

PROCUREMENT STRATEGY & SCHEDULE

Regular
Vendor
Not seen in Vendor
Search

Prospective New/Reactivate
Vendor

Admin
TARGET
PROCUREMEN
CONTRACTORS/SUPPLIERS
DATE OF
STATUS
T STRATEGY
AWARD

JEBSEN International Trading


Corp.
ALI Recommended
Manufacturer/contractor
FORMAL
05/30/2014
Arch.
CANVASSING
Specs page 99

PROJECT :AVIDA CENTRIO TOWER


LEGEND:
CORRALES AVENUE, CAGAYAN DE ORO
LOCATION :
CITY
SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKS
as of :3/8/2014

CONTRACT
PACKAGE

WORK PACKAGES

FIXED LUM SUM (FLS)

CP-FLS-15

SUPPLY AND INSTALLATION OF


DIVIDERS AND PARTITIONS Urinal
Partitions

MULTI RICH HOME


CP-FLS-16
CP-FLS-17

INSTALLATION OF T&B ACCESSORIES


STP ELECTROMECHANICAL

ADMIN WORKERS
ECOSYSTEMS

ADMIN
PARTNERING

05/30/2014
05/30/2014

14/16

ELEMENTS OF EXECUTION PLANNING

OPERATING PROJECT BUDGET


PROJECT BUDGET

14/16

OPERATING PROJECT BUDGET (AWARDED)

Proposed Contract Amount (FLS


ONLY)
Proposed Contract Amount (VAT
Exclusive)
Proposed OPB
Gross Operating Income (12.57%)
Indirect Cost (GAE 4.0%)
Net Income Before Tax (NIBT) 30%
Allowance for Corporate Taxes
Net Income After Tax (NIAT)
NIAT

221,079,737.53
197,392,622.79
172,576,169.61
24,816,453.19
7,895,704.91
16,920,748.28
5,076,224.48
11,844,523.79
6.0%

14/16

OPERATING PROJECT BUDGET (AWARDED)

15/16

ELEMENTS OF EXECUTION PLANNING

SUSTAINABILITY, CSR (Corporate


Social Responsibility) AND
ENVIRONMENT
Continue review on possible application of green building
features in the project
SUSTAINABILITY
NOISE LEVEL
DUST CONTROL
ROADS/ SIDEWALKS/COMMON AREAS

14/16

SUSTAINABILITY, CSR & ENVIRONMENT


SUSTAINABILITY
A material recovery area will be provided to sort rebar cutting
for ease of reuse.
Surplus ready-mix concrete (RMC) will be poured onto the dirt
road, potholes and other muddy areas within the construction
site.
All equipment will be required to pass emission testing
standards
to prevent air pollution.

NOISE LEVEL
Noise level during construction operations or use of equipment,
tools, and any sound source which would result in the emission of
noise above the ambient noise level standards will be limited to:
Period
Maximum Noise Level
Daytime ( 7AM 10PM )
75 db
Night
( 10PM onwards )
65 db
Noise generating activities shall be prohibited during Sundays.

14/16

SUSTAINABILITY, CSR & ENVIRONMENT


DUST CONTROL
To maintain cleanliness right outside the construction perimeter
area, housekeeping crew will be deployed on a regular basis to
address the dust and dirt on the road (Corrales Avenue) where the
equipment passes through.
The following measures will also be implemented:
- Regular wetting of dirt at the work area.
- Wash bay area shall be provided at entrance/exit gate to clean
vehicles coming out of the project site.
-Truck access ways and roadways shall be sprinkled with water
to confine dust particles.
- Dump truck haulers of excess excavated soil and construction
debris shall be covered to prevent spillage.
- Regular hauling of excess excavated soil and construction
debris shall be done at specified times.
- Catch pan for cleaning equipment tires, fuel, oil and lubricant
spillage shall be provided.

15/16

SUSTAINABILITY, CSR & ENVIRONMENT

15/16

SUSTAINABILITY, CSR & ENVIRONMENT


ROADS / SIDEWALKS / COMMON AREAS
- Sidewalks, roads & other common areas surrounding the
project site shall not be obstructed by construction
materials or equipment.
- Roads and sidewalks shall not be used as staging areas,
for mixing cement or fabrication, or temporary storage of
materials and supplies.
- Heavy equipment w/ track shoes shall not be allowed
passage to and from the construction site unless they are
carried on flat bed trailers.

16/16

ELEMENTS OF EXECUTION PLANNING

RISK MANAGEMENT
Incorporate the potential wage increase in the unit price.
Incorporate in the Terms & Conditions of the package that the
rebars supplied by the owner shall be under Gross Maximum
Quantity (GMQ ).

16/16 ELEMENTS OF EXECUTION PLANNING

16/16 ELEMENTS OF EXECUTION PLANNING

16/16 ELEMENTS OF EXECUTION PLANNING

16/16 ELEMENTS OF EXECUTION PLANNING

16/16 ELEMENTS OF EXECUTION PLANNING

The End...