2,446,075 lbs/year
Original TMDL Strategy Plan was submitted in September,
2012
Comments received from PADEP dated February 26, 2015
All areas draining to or from Township Roads & Properties in Urbanized Areas
Included
Area of MS4 Responsibility = 5.725 sq. mi.
Proposed Project
Estimated
Sediment
Reduction
(lbs./year)
412
6,533
28,018
N/A
2014-2019
2017
75,105
Total
lbs./year
NEXT STEPS
Respond to any Public or Supervisor Comments
Finalize Proposed TMDL Strategy as required by PA
DEP
Response to PA DEP NOI Comments due