Civic Office, King Street Regeneration

Group E: Faris Al Amer, Josiah Johnson, Nasrin Sadeghi & Zeishan Muhammad

Materials & Construction Sequence

More
sustainabl
e

Minimal
restrictions

Minimum
reduction in
floor heights

Steel

Cellular
Beams
No carbon
footprint

Construction
Sequence

Web
openings
for
services

25% to 30%
weight
savings

Foundations
Excavation, forming and placement of the concrete
foundations. Forming and placement of the ground floor
slabs.
Steel
Erection
The erection of the steel building frame, including
primary
& secondary beam members, columns, bracings &
temporary steel for construction.
Forming Floors, Roof & Masonry

Installing slabs. Forming, placing & finishing the concrete roof of the structure. The interior & exterior masonry of the
building, including the elevator & utility cores.

& of
Cladding
Placement of lightweight concrete fill andRoofing
installation
roof drains. Brickwork cladding on the structure's
exterior.
Windows & Closures

Installation of the metal framing and glazing components of the windows.

Building Finishes

The detailed work of completing the interior of the building. Insulation, drywall, paint, elevators, plumbing,
electrical, carpeting, furniture, and so on.

Structural Framing

12
m
8m

8m

8m

12
m

10
m

6m

12
m

10
m

6m

12
m

10
m

6m

6m

6m
12
m

6m

6m
12
m

5m

Basement Construction
Foundation
Foundation is located
within gravel which has a
high bearing capacity. Pad
foundations will be used.
Main advantages include:
Little excavation is
required
Suitable for tight site
Basement
Retaining Wall
areas
Economical
Advantages of secant piles:

Phase 1

Phase 2

Phase 3

Drilling

Withdrawal &
Concreting

Steel
Cage
Installation

Water table is approximately just below


basement so piles will give added
waterproof security.
Quickly constructed and cheap to
produce.
Little vibration is created during the
construction.
Hence minimum impact is caused to
surrounding.

Construction:

CFA rigs are used to drill and pump

Primary Piles

Secondary Piles

Site Constraints

Materials Delivery:

Delivered by trucks during times with


minimum traffic disruption.
Traffic and entry to the work area is
controlled during delivery times.
Trucks and vehicles must use main
roads for safety.
Plan storage areas to minimize
disruption.

Materials Storage:

Plan deliveries to keep the amount of


materials on site to a minimum.
Storage containers or temporary
warehouses can be used for on-site
storage.
Storage containers are more
preferable since they can be stacked,
hence reducing storage space.

Sustainability

Clock Tower