NPSI
126 MW solar portfolio - Negros Occidental ( Bacolod)

Sugarlandia

TABLE of CONTENT

1. Project Snapshot
Introduction
Site Locations
2. Project Development
Project Development
Site Pictures
3. Technical Package
Soil & Flood Studies
Layout and Topo studies
Energy Yield Analysis
4. Commercial Package
Development Fee Proposal

NPSI

Project Snapshot
Introduction 1/2

NPSI

One site with 3 adjacent land owners up to 154 hectares that have been secured in Negros Occidental
Service Contract received Blocked ~800ha; ECC permit obtained
Preliminary Facility Study Grid received
Grid Impact Study / System Impact Study conducted and preliminary results received 50 MWp
PV Power plant to be connected to the NGCP 69 kV or 138 kV for capacity above ~ 60 MWp
No right of way needed. Direct access to 69 kV transmission line on site (north east plots)
All sites have DAR Certificate of Exemption and/or Notice of Non-Coverage
Non irrigated land, to date used for sugar cane plantation
All sites have proper land titles
Topography, Flood and Soil studies have been conducted and all sites are solar ready
Landlords and local LGUs are very supportive of the project

Project Snapshot
Introduction 2/2
Land lease option terms have been agreed 25yr lease ; Lease contract renewable
Average PHP 75k per hectare per annum excluding taxes
10% escalation every 5 years
Landlords are prominent local businessmen/politician with
good standing in society
Substation and Transmission lines have adequate capacity
for all solar plants (site approx. 1.5km direct line from the
NGCP substation or by road
4.5km)
Clean SPV set up for the project
No coconut trees

NPSI

Expansion sites have been identified


Discussions with NGCP at local and national level
All local LGU permits obtained
Good Site Access for Construction Equipment, and easy
access with flight Manila - Bacolod
Initial plant layout design done by juwi
Local construction contractors qualified

Sites locations

NPSI

Project Development
Site Pictures

NPSI

Technical Package
Site layout & Topographical studies

NPSI

Currently planned with 50 MWp, design on left shows up to 61MWp


69kV transmission line shown in red on east corner of upper plot
juwi conducted extensive site selection and engineering and project is
construction ready from engineering perspective
Topographical & hydrological studies for all sites conducive
Availability of local labor and construction assets

NPSI

Technical Package
Soil & Flood Studies

Flood and Soil studies for all sites have been


conducted
There is no flood risk on any site
Soil conditions are good
Initial screw pile solution has been identified

NPSI

Technical Package
Energy Yield Analysis

The yield analysis was


carried

out

with

the

simulation software PVSYST


and global Meteorological
data provided and generated
by SolarGIS.
A degeneration of 0.7% per
year of the initial first year
simulated output can be
calculated.

NPSI

Project Development in Partnership with juwi as


development & Technical Partner
EXCLUSIVE
Key Person
Ms Maricel Monfort

juwi - minority in Project SPV

Majority shareholder in Negros PH Solar ( Project


SPV)

Founded in 1996
juwi AG headquarter in Germany

Successful and prominent businesswomen


resident in Bacolod
Varied business interests in property, land,
agriculture, hospitals and water resources
Very strong local network and relationships

Renewable Energy specialist


~1,000 employees (worldwide)
> 3,200 MW in Wind, Solar and Bio
Investment volume (since 1996) > 7.6 billion USD

Supported by an experienced team of developers


Germany, Japan, USA/Canada , India, Singapore,
and technical specialists, incl land, legal, finance, Thailand, Malaysia, Australia, Philippines,South Africa,
regulatory, etc
Great Britain, Italy, Greece, Czech Republic, Chile

Commercial Package - Development Fee

NPSI

Executive Summary - Payment and Milestones


Summary

Proposal

Total MWp

50 MWp

Scenarios

BASE CASE

Land lease (5 year lease rental upfront)


Total Base Fee (US$/MWp)

Expansion - Exclusivity

~US$ 1MM

$150,000 per MWp

Signing Term Sheet & Lease Agreement

US $ 30,000 per MWp

Certificate of grid adequacy by NGCP

US$ 30,000 per MWp

Issuance of key permits (ECC, BOI, BOC and COC permits)

US $ 40,000 per MWp

Milestones

*
Milestones
Announcement of applicable solar policy or tariff or PPA

US $ 25,000 per MWp

Issuance of NTP

US $ 12,500 per MWp

Commercial Operation

US $ 12,500 per MWp

* to be proportionated based on final MW (SIS) approved by NGCP