Chapter 13
13-1
4. Taking Action
and Recycling
the Process
2. Measuring
Progress
3. Comparing Actual
with Planned
13-2
40
Cumulative
Budgeted Cost
20
Cumulative
Actual Cost
5
10
15 20 25 30 35 40 45 50
Elapsed Time (in weeks)
13-3
Milestone Analysis
Milestones are events or stages of the project
that represent a significant accomplishment.
Milestones
signal the team and suppliers
can motivate the team
offer reevaluation points
help coordinate schedules
identify key review gates
delineate work packages
13-4
Performance
Cost
Schedule
Cost
Earned
Value
Performance
Performance
Schedule
Tracking Control Charts
Schedule
13-6
Actual
Overspend
Cost
PV
EV
Budget
Slip
Scheduled
Performed
Schedule
13-9
Value
8=80%(10)
15
100
15
Blueprint
10
80
Prototype
10
60
33
38
30
Design
Mon Plan
17
Cmltv
15
21
38
Mon Act
11
13
Cmltv Act
19
27
40
Cumulative
40=8+11+8+13
Earned Value
30=15+8+6+1
Planned Value
38=15+10+10+3
13-10
13-12
Human Factors in
Project Evaluation & Control
Optimistic progress reports
Level of detail
Process evaluation
Non-technical performance measurement
13-13
Project mission
Top management support
Project plans & schedules
Client consultation
Personnel
Technical tasks
Client acceptance
Monitoring & feedback
Communication channels
Troubleshooting
13-14