Académique Documents
Professionnel Documents
Culture Documents
PROGRAMME
Prepared By:
K.Ramamurthy
Scope
The training program covers the
structural steel fabrication, testing &
erection requirements for Mild Steel,
Indian
standard
sections
and
Cylindrical welded water storage
tanks in various capacities.
The training will be specific for Rolled
plate sections used with various
welded & Bolted joints.
INTRODUCTION
Structural elements
Columns
Columns are elements that carry only axial force - either tension or
compression - or both axial force and bending (which is technically called a
beam-column but practically, just a column). The design of a column must
check the axial capacity of the element, and the buckling capacity.
Beams
A beam may be defined as an element in which one dimension is
much greater than the other two and the applied loads are usually
normal to the main axis of the element. Beams and columns are
called line elements and are often represented by simple lines in
structural modeling.
cantilevered (supported at one end only with a fixed connection)
simply supported (supported vertically at each end; horizontally
on only one to withstand friction, and able to rotate at the
supports)
continuous (supported by three or more supports)
a combination of the above (ex. supported at one end and in the
middle)
Beams are elements which carry pure bending only. Bending
causes one part of the section of a beam (divided along its length)
Plates
Plates carry bending in two directions. A concrete flat slab is an
example of a plate. Plates are understood by using
continuum mechanics, but due to the complexity involved they are
most often designed using a codified empirical approach, or
computer analysis.
They can also be designed with yield line theory, where an
assumed collapse mechanism is analyzed to give an upper bound
on the collapse load (see Plasticity). This is rarely used in practice.
Shells
Shells derive their strength from their form, and carry
forces in compression in two directions. A dome is an
example of a shell. They can be designed by making a
hanging-chain model, which will act as a catenary in pure
tension, and inverting the form to achieve pure
compression.
Arches
Arches carry forces in compression in one direction only,
which is why it is appropriate to build arches out of
masonry. They are designed by ensuring that the line of
thrust of the force remains within the depth of the arch.
IN USE :
Greater flexibility
Limited no. of internal supports
Adaptability of frame work to change of use
Increasing effective life of building
Ease in dismantling or demolition
FABRICATIO
N
Material
Structural engineering depends on the
knowledge
of
materials
and
their
properties, in order to understand how
different materials support and resist
loads.
Generally the material for the structural
steel is used IS2062 / IS226 of grade A. &
B
The property of the structural steel of
above grade..\can
be referred to IS 808
metal.docx
Bolting and
Bolt
Connection
Welding Connection
INTRODUCTION
What is welding?
ARC WELDING
WELDING ELECTRODE
Covered Electrodes for Manual Metal ARC
Welding of Carbon Manganese steel
..\814.pdf
WELDING QUALIFICATION
Code of practice
for training and Approval Test for
welders
when
testing of metal arc
Welding procedure
welding
approval
is
not
required
..\817.pdf
..\7318_2.pdf
TESTS ON WELDS :
Tests on Welds can be Classified under,
Destructive Test such as,
Visual Inspection for Fillet and Groove Welds
Root Bend Test for Groove Welds
Face Bend Test for Groove Welds
Nick Break Test for Fillet Welds
Non Destructive Test such as,
DP Test ( DYE PENETRANT ) for Fillet and groove Welds
Radiography Test , Tensile Strength etc. for Groove Welds
27
Tension face
FILM LENGTH
28
40
TP
TP
TP
TP
TP
TP
TP
TP
TP
TP
10
1.5 TO 2 MM
40
50MM DISCARD
300
600 TO 720
EQUAL PIECES
300
50MM DISCARD
29
In case Welder passes the test, the Welder shall be issued Identity Card
ADVANTAGES
LIMITATIONS
BASE METAL
CLIENT
FILLER METAL
CONSULTANT
DIA / THK
CONTRACTOR
PROCESS
CONTRACT NO
POSITION
WELDERS
PHOTOGRAPH
WELDER NO
DATE OF QUALIFICATION
VALID UPTO
APPROVED BY
NAME OF WELDER
CONTRACTOR
NAME
SIGNATURE / DATE
ENGINEER
NAME
SIGNATURE / DATE
32
Sr
Welde
Welde r
rs
Identi
name ficatio
n no
Visu
al
Insp
ectio
n
Date
of
Testi
ng
Radi
ogra
Destructive Test
phy
results
resul
ts
Rema
rk
33
PRODUCTIVE NORMS :
SRNO ACTIVITY
PRODUCTIVE NORM
Fitter
SAW Welder
SMAW Welder
Gas Cutting
Driller
Rigger
The Productivity Norms also depends upon the Structures i.e. Light or
Heavy and
the Site conditions.
34
POSITIONS IN WELDING :
FILLET
1F
2F
3F
4F
GROOVE
1G
5G
2G
PIPE IS ROTATED
DURING WELDING
3G
6G
4G
WELDING SYMBOLS :
The Identification of weld like Type, Thickness of the Weld is always
indicated in
the drawings with an Symbol , the common symbols are,
6 Denotes 6 mm Fillet Weld on one Side
6
6 300 (300)
6 300 (300)
37
SIZE OF WELD :
Size of Weld is determined by Design depending on the Size of the
member and the intended loading,
The Size of weld is indicated in the Shop drawings, and is interpreted
by its throat thickness,
Z=a2
Z = Leg length
a = Throat thickness
CONSTRUCTION :
Construction of Steel Structures are divided into two parts
namely,
Fabrication is a process of building Steel Structures which involves
Marking of
various Components and Elements as per the Shop Drawings, Cutting,
and
Welding ( either Tack welded or full welded ).
Erection is a process of Building the various fabricated materials to
form a
Structure as per the desired Design and Fabrication drawing.
Painting is optional which can be done either after fabrication or after
39
Erection
CLEAT ANGLE
SEAT ANGLE
CLEAT ANGLE
SEAT ANGLE
JOINT
FLANGE SPLICE
WEB SPLICE
CLEAT ANGLE
BEAM
COLUMN
WELD LENGTH
ERECTION BOLTS
BRACING ANGLE
GUSSET PLATE
WELD LENGTH SHALL BE SPECIFIED IN THE SHOP
DRAWING. THE SIZE OF THE GUSSET SHALL
GOVERN
THE WELD LENGTH.
42
BEAM
MS PLATE
FILLET WELD
BEAM WITH
COVER PLATE
COVER PLATES
COVER PLATES
MS CHANNEL
43
QUALITY ASSURANCE :
Specification of Steel material
Inspection of Steel Material
Transportation of material to Site
Stacking of materials
Cutting the materials to required dimensions as per the shop
fabrication drawings
Alignment of the members , Check for Fit up
Tack welding
Full Welding
Transportation of the fabricated materials to Erection site
Arranging various members as per the sequence
Erection of members
Welding of supports
Inspection of Erected members for its Alignment
Painting of Structure.
46
QUALITY CONTROL :
Structural Steel Fabrication and Inspection Record
Billing Control Chart for fabrication / Erection / Alignment of Structural
Steel
Field installation Checklist / Acceptance of Steel Structure
Release of Painting
Grouting Release
Welding Procedure Qualification Record
Welders Performance Qualification Test Record
Identity Card for Welders
Qualified Welders Log.
47
DEFECTS IN WELDS :
Craters
Splatters
Undercuts
Blowholes
Cracks
Slag Inclusions
The Defects in Welds are generally due to poor quality Electrodes,
Unqualified
Welders, Over / Low Current, Improper position, Welding speed,
Incorrect Polarity.
The remedial measures shall be taken accordingly depending on the
type of
48
VIDEO
Structural video\VID-201409
21-WA0000.mp4
VIDEO
Structural video\Structural Steel Co
nnections_(360p).mp4
ERECTION
Erection alignment
The steelwork shall be temporarily shop erected
complete or as arranged with the inspector so that
accuracy of fit may be checked before despatch. The
parts shall be shop assembled with sufficient numbers
of parallel drifts to bring and keep the parts in place.
In the case of parts drilled or punched, through steel
jigs with bushes resulting in all similar parts being
interchangeable, the steelwork may be shop erected
in such position as arranged with the inspector.
TOLERANCE
Tolerances for fabrication of steel structures
shall
conform to IS : 72 15 , Specification or agreed
between the approval of quality procedure.
Tolerances for erection of steel structures
shall
conform to the general guidance or
Specification requirement.
Field Connections
Field bolting - Field bolting shall be carried
out with the same care as required for shop
bolting.
Field welding - All field assembly and
welding shall be executed in accordance
with the requirements for shop fabrication
excepting such as manifestly apply to shop
conditions only.
Where the steel has been delivered painted,
the paint shall be removed before field
welding, for a distance of at least 50 mm on
CRANE GIRDER
In case of crane runway girder the maximum- vertical
deflection under dead and imposed loads shall not exceed
the following:
Refer IS Code: 800 1984 clause - 3.13.1.3 Page: 35.
Limiting Horizontal deflection for structural steel should
not exceed to clause No 3.13.2 Page No.35 of IS 800 1984.
Following Points should be noted during erection:
The joint between Girders should be at same level
The Expansion joint should be as per approved detail
drawing, No deviation should be accepted
The center line deviation of the Girder should not exceed
the thickness of web plate or as per requirement of the
Crane vendor
Walkway between CG & Structural Column should be min.
PEB STRUCTURAL
ERECTION
PEB Erection Guide
TESTING
Welding
Inspection:
Visual Inspection
Fit Up:
The Welding joint to
releasing for welding.
be
checked
before
TESTS ON WELDS :
Tests on Welds can be Classified under,
Destructive Test such as,
Visual Inspection for Fillet and Groove Welds
Root Bend Test for Groove Welds
Face Bend Test for Groove Welds
Nick Break Test for Fillet Welds
Non Destructive Test such as,
DP Test ( DYE PENETRANT ) for Fillet and groove Welds
Radiography Test , Tensile Strength etc. for Groove Welds
64
Welding
Defects
UNDERCUT
POROSITY
INCOMPLETE FUSION
OVERLAP
UNDERFILL
SPATTER
EXCESSIVE CONVEXITY
EXCESSIVE CONCAVITY
EXCESSIVE WELD
REINFORCEMENT
INCOMPLETE PENETRATION
&
EXCESSIVE PENETRATION
Safety
Compliance
Compliance to the following is mandatory:
Memorandum of Understanding
Employers Policy and Management System
The work to be done in accordance with
Employers SHE
Policy and Management systems.
Indian Statutory requirements
International standards, Guidelines & ISO
Introduction:
Unlike in any other type of engineering industry, civil
woks involving building and construction where so
many
different
works
are
carried
out,
is
or
the
consequent
damage;
simultaneous
potential
accidents
of
activities,
hazards,
involving
which
risk,
injury
and
and/or
Employment
being
temporary,
prominently
frequent
change
transient
of
or
manpower
is
therefore
highly
difficult
to
impart
safety
workforce
till
the
completion
of
the
contract;
However, the laws require making the worker and
environment safe. This can be achieved only by
making the worker, his supervisor, manager and
SAFETY IN FABRICATION :
The power supply to all Electrical Equipment and Hand Tools shall only
be through adequately rated ELCB.
Power Cables and Welding Cables used in the fabrication shop should
preferably be without any joint.
Temporary lifting lugs welded with any member should have adequate
strength and weld length to cater to the load.
Periodical checks shall be carried out to ensure good condition of
electrode holders, hand-held tools like Grinders, Drill, Oxy-Acetylene gas
regulators, Cutting torches and gas hoses etc.
House Keeping in Fabrication Yard
Area should be sufficiently illuminated during Fabrication at Night
hours.
Identification and Location of Scrap Yard
83
SAFETY IN ERECTION :
Ensure proper slinging of the member to avoid sliding / jerking of the
load during erection.
Avoid all erection activities during rains, heavy wind and night hours.
Structural members like Columns, Trusses, Lattice Girders etc. shall
be provided with adequate number of guy ropes to hold them till
alignment and final bolting / welding is completed.
Check adequacy of erection cleats ( especially if not shown on
drawings ).
Ensure that erection bolts are reasonably tight and not kept loose.
Cordon off the erection area / s to restrict the movement of
unauthorised persons.
Ensure the Crane used for erection is Load tested to lift the required
Member.
84
SAFETY
Welding installations
When the welding circuit is connected, the following guidelines
should be adopted:
the connection between the power source and the work piece
should be as direct as practicable
use insulated cables and connection devices of adequate
current-carrying capacity. The current for electric arc welding
must not exceed 300 Amps on a hand welding operation.
extraneous conductive parts should not be used as part of
the welding return circuit unless part of the work piece itself
the current return clamp should be as near to the welding arc
as possible.
All welding grounds and returns should be securely attached
to the work by cable lugs/ clamps/ bolts/ strip conductors.
GAS WELDING/CUTTING
OXYGEN CYLINDERS
ACETYLENE CYLINDERS
WELDING/CUTTING
Acetylene is stored in cylinders specially designed
for this purpose only.
Acetylene is extremely unstable in its pure form at
pressure above 15 PSI (Pounds per Square Inch)
Acetone is also present within the cylinder to
stabilize the acetylene.
Acetylene cylinders should always be stored in the
upright position to prevent the acetone form
escaping thus causing the acetylene to become
unstable
HEIGHT SAFETY .
COMPRESSED GASES
HAZARDS
Close the gas cylinder valves when not in use such as during
breaks, lunch, or
end-of-shift to avoid leaks.
All gas cylinders must be fixed with pressure regulator and dial
gauges.
Avoid getting any oil or grease on the cylinders or
regulators/gauges,particularly those containing oxygen, to avoid
fire or explosion.
THANK YOU