Académique Documents
Professionnel Documents
Culture Documents
A Point of Reference
(based on the 5th Edition PMBOK
Guide)
By Tom Tiede
Agenda
This material will cover the following project management topics:
What is PMI and the PMP?
Why PMI Project Management Principles are
Useful to Know
A Few Basic PMI Definitions
Five Process Groups
o Initiating
o Planning
o Executing
o Monitoring and Controlling
o Closing
Adjourning
Communication Noise
Risk Probability and Impact Matrix
Contract Type
Stakeholder Power vs. Interest Grid
o Risk
o Procurement
o Respect
o Fairness
o Stakeholders
o Honesty
Project
Initiation
Project
Planning
Project
Execution
Project
Closure
The PMI approach places great emphasis on project initiation and planning when
requirements are clearly defined and agreed upon and the full scope of the project
is planned
4
Portfolio
Programs
Projects
Time
Cost
Quality
Scope
5
Process
Groups
Develop an
integrated project
management plan
to attain project
objectives
Authorize the
Work
Activitie
s
Key
Outputs
Planning
Project Charter
Stakeholder
Register
Executin
g
Monitorin
g&
Controllin
g
Closing
Project
Deliverables
Work Performance
- Scope
Data
- Requirements
Team Performance
- Schedule
Assessments
- Cost
Project
- Quality
Communications
- Human Resources
(e.g. status
- Communication
reports)
- Risk
Selected Suppliers
- Procurement
& Agreements
- Change
Change Requests
- Stakeholders
Issue Log
Change Logs
Final Product,
Service, or Result
Approved Change
Requests
(i.e. purpose of
Work Performance
project)
Information
Closed
Schedule Forecasts Procurement (e.g.
formal signature of
Cost Forecasts
acceptance)
Updates to Project
Plan
Quality Control
Measurements
Verified
Deliverable
Accepted
6
Deliverables
Closing
Initiating
Time
Planning
No
Executing
Monitoring
&
Controlling
No
Change
?
Yes
Complet
e?
Yes
Closing
7
Knowledge Areas
A project manager is responsible for applying and managing the
following ten knowledge areas:
Integration
Identify, define, combine, unify and coordinate activities within the Project
Management Process Groups
Scope
Ensure the project includes all work required to complete the project successfully
Time
Cost
Quality
Determine quality policies , objectives, and responsibilities so that the project will
satisfy the needs for which it was undertaken
Human
Resources
Organize, manage, and lead the project team, including the identification of roles,
responsibilities, required skills, and reporting relationships
Communication
Risk
Identify and assess risks, plan responses, and control risk to increase the likelihood
and impact of positive events and decrease the likelihood and impact of negative
events on the project
Procurement
Purchase or acquire and control products, services, or results needed from outside the
project team
Stakeholders
Initiating
Planning
Executing
Monitoring &
Controlling
Closing
Integration
Applicable
Applicable
Applicable
Applicable
Applicable
Scope
Applicable
Applicable
Time
Applicable
Applicable
Cost
Applicable
Applicable
Quality
Applicable
Applicable
Human Resources
Applicable
Applicable
Communication
Applicable
Applicable
Risk
Applicable
Procurement
Applicable
Stakeholders
Applicable
Applicable
Applicable
Applicable
Applicable
Applicable
Applicable
Define, prepare,
coordinate and
integrate all
subsidiary plans
into a
comprehensive
plan
Key:
Initiating
Planning
Executing
Monitoring & Controlling
Closing
ote, additional inputs, outputs, tools and techniques not depicted may apply
10
Project Charter
A project charter formally authorizes the project and the project
manager to apply resources to project activities. Per PMI,
without a charter, there is no project.
A typical charter will identify:
o
o
o
o
o
o
o
o
o
Project Charter
The charter must be signed by someone who can invest authority for
the project (typically senior management or a sponsor)
11
Change
Quality
Schedule
Scope
Project
Management
Plan
Cost
Process
Improvement
Configuration
Stakeholders
Risk
12
Scope
Determine,
document, and
manage
stakeholder
needs and
requirements
to meet
objectives
Subdivide project
deliverables into
smaller, more
manageable
components
Develop a
detailed
description
of the
project and
product
Key:
Initiating
Planning
Executing
Monitoring & Controlling
Closing
Monitor
status of
the project
scope and
manage
changes to
the scope
baseline
Gain formal
acceptance of
completed project
deliverables
13
Deliverable
1
Work
Packages
Deliverable
2
Work
Packages
Control
Account
Planning
Packages
Used when
insufficient detail
is available at
the work
package level
Work
Packages
14
ote, additional inputs, outputs, tools and techniques not depicted may apply
Monitor the
status of
project
activities to
update project
progress and
manage
changes to
the schedule
baseline to
achieve the
plan
15
Descriptions
Based on estimated Pessimistic (P), Optimistic (O), and Most Likely (M) durations
High level, top down estimate based on similar projects (usually by a SME - subject matter expert)
Estimate at the lowest level of the WBS (level 3) and then roll up for the total project estimate
Based on an existing, comparable parameter (e.g. $/ft. in the same neighborhood)
Contingency (buffer based on known risk) & include in project budget or Managerial (buffer based on
Reserve Analysis
unknown risks)
An iterative technique used when future details aren't known; near term is planned in detail; future is higher
Rolling Wave Planning
level
Finish to Start (FS)
Finish to Finish (FF)
Start to Start (SS)
Start to Finish (SF)
Rare, A starts before B
Default relationship; B
B cannot finish until A is
B cannot start until A
finishes (e.g. when
cannot start until A is
finished
starts
replacing an old system B
Predecessor
finished
with a new system A)
Relationships
A
Free Slack
Total Slack
Float
Lag
Lead
Schedule
Compression
Fast Tracking
Resource Leveling
Resource Smoothing
A
B
B
B
The latest an activity can start without B
delaying next activities
The latest an activity can start without delaying project finish date
Often referred to as the same as Slack
Lag (a delay) = the successor must wait due to some delay after the predecessor is complete
Lead (an accelerant) = the successor can begin before the predecessor is complete
Crashing or fast tracking the schedule to adjust the schedule to align with the plan
Compression technique based on overlapping sequential activities (risky)
Adjusting peaks and valleys to create a level usage of resources
Adjusting peaks and valleys to create a level usage of resources AND also accounts for individual resource
limitations
16
Establish the
policies,
procedures,
and
documentation
for planning,
managing,
expending, and
controlling
project costs
Develop an
approximation of the
monetary resources
needed to complete
project activities
Key:
Initiating
Planning
Executing
Monitoring & Controlling
Closing
Aggregate estimated
costs of individual
activities or work
packages to establish an
authorized cost baseline
17
Dollars
EAC
EAC
BAC
BAC
Actual Cost
(AC) at point in
time
AC
AC
PV
PV
EV
EV
Schedule
Variance
(SV)
Time
18
Key:
Initiating
Planning
Executing
Monitoring & Controlling
Closing
19
Quality Principles:
Quality Audits
Process Analysis
Inspection
85/15 Rule
80/20 Rule
Rule of 7
Mean Time Before Failure
Mean Time to Repair
Grade vs. Quality
Upper Control Limit
Lower Control Limit
Upper Specification Limit
Lower Specification Limit
Description
Fishbone (Ishikawa) diagram
Basic flow chart or GERT diagram with feedback loop
Check list (e.g. pre-flight list to ensure you are "cockpit ready" before taking flight)
Cumulative histogram (e.g. 80/20 rule)
Depiction of volume or frequency of occurrences of several events
Depiction of process output over time with UCL & LCL at 3 sigma from mean
Depicts pattern of results across two variables
Description
Comparing actual or planned processes to comparable projects to identify best practices
Variable based analysis (freeze all variables but one and assess outcome)
Using a % of the population and extrapolating the results within an acceptable confidence level
Identify best practices; identify gaps; share best practices; offer assistance to improve; highlight lessons
learned
Assess process, identify root causes, alleviate root causes
Examination of work product and comparison to documented standards (e.g. reviews, audits)
85% of quality relates to mgt.; 15% is worker related
80% of problems come from 20% of the issues
Must have 7 consecutive data points above or below mean to consider process "out of control"
MTBF, example quality metric
MTTR, example quality metric
Not the same; you can have a lower grade product with high quality and vice versa (e.g. automobile
models)
UCL = 3 sigma above mean (average)
LCL = 3 sigma below mean (average)
USL is customer established and can be above or below UCL
USL is customer established and can be above or below LCL
21
Confirm
availability and
obtain the
necessary team
Key:
Initiating
Planning
Executing
Monitoring & Controlling
Closing
Improve
competencies, team
interaction, the team
environment, and
enhance project
team performance
ote, additional inputs, outputs, tools and techniques not depicted may apply
22
Activity
Person
Ann
Ben
Carlos
Denny
Develop Schedule
Collect
Requirements
Develop Training
Plan
(C) Consulted those whose opinions are sought (typically subject matter experts); typically this is
a two way communication
(I) Informed those who are kept up-to-date on progress; typically this is a one way communication
23
Coaching
Initiating
Facilitating
Supporting
Closing
Time
Conflict Management
Conflict is inevitable. A project manager should be aware of
typical sources of project conflict and recommended techniques
to resolve them.
Sources of Conflict
Conflict Resolution
Techniques
Higher
Recommended:
Scheduling Priorities
1. Collaborate/Problem Solve
Scarce Resources
2. Compromise/Reconcile
Probabilit
Personal Work Styles
3. Force/Direct
y of
Methodology/Details
Conflict
Cost/Budget
Not Recommended:
Personalities
Lower
4. Smooth/Accommodate
5. Withdraw/Avoid
25
Create, collect,
distribute, store,
and retrieve
information
Key:
Initiating
Planning
Executing
Monitoring & Controlling
Closing
ote, additional inputs, outputs, tools and techniques not depicted may apply
26
Communication Management
Project managers should be aware of the basics of effective
communication across the broad stakeholder community.
Communication Methods
Communication Model
Sender/Enco
de
Noise
Communication Types
Active listening receiver verifies correct
interpretation
Effective listening receiver observes visual
and vocal cues
Feedback sender receives feedback from
receiver
Nonverbal - ~55% of communication (e.g.
body and facial language)
Para-lingual Voice characteristics
Transmi
t
Noise
Decode/Receiver
Acknowledgement
Response
Communication Paths
N
# of Communication
Paths
equals [N x (N-1)]/2
N equals # of
Stakeholders
Example: [4 x (4-1)]/2
=6
27
Key:
Initiating
Planning
Executing
Monitoring & Controlling
Closing
Develop options
and actions to
enhance
opportunities
and reduce
threats to
project
objectives
28
High
ed
Probability
of
Occurrence
Moderate
Ne e
s
ity on
r
io esp
r
rP kR n
e
a
gh Ris Pl
i
H or
f
success
Enhance improve the size of the
problem
Transfer re-assign to another
party
Low
Moderate
Level of Impact
High
29
Risk Management
Project managers should be aware of risk management terms.
Risk Management Terms
Monte Carlo simulation of possible outcomes
Risk Breakdown Structure breakdown by category (e.g. internal, external, technology,
organizational, etc.)
Risk Trigger an indicator that an event could occur
SWOT Analysis strengths, weaknesses, opportunities, and threats
Expected Monetary Value (EMV) summation of probability x impact of alternative decisions (
not to be confused with EVM earned value management)
Contingency Reserves for known risks (include in budget and schedule)
Management Reserves for unknown risks (excluded from baselines for budget and schedule)
Residual Risk risk remaining after risk response
Secondary Risk potential risk as a result of risk response
Workaround wing it response when other risk response plans dont work
Types of Risk Tolerance
o Averse Avoids risk
o Seeker Seeks risk
o Neutral Middle ground
30
Obtain seller
response, select a
seller, and award a
contract
Manage procurement
relationship, monitor
contract performance, and
make changes and
corrections as appropriate
Complete each
project
procurement,
including finalizing
open claims,
updating records to
reflect final results,
and archiving
information
Key:
Initiating
Planning
Executing
Monitoring & Controlling
Closing
ote, additional inputs, outputs, tools and techniques not depicted may apply
31
Contract Types
Project managers should be aware of the benefits and risks of
different contract types from a buyers perspective and a sellers
perspective.
Low
High
Buyers Risk
FFP
High
PO
CPFF
Sellers Risk
CPIF
CPAF
CPPC
Low
(FFP) Firm Fixed Price allows buyer to budget fixed price; requires seller to detail scope and accurately
estimate price; very common
(FFIF) Fixed Price Incentive Fee includes incentive to motivate seller to produce at greater speed
(FF EPA) Fixed Price Economic Price Adjustment compensates for year to year economic changes
(T&M) Time and Materials typically used for smaller initiatives
(PO) Purchase Order typically used for commodity items
(CPFF) Cost Plus Fixed Fee typically variable costs are cost-plus and predictable costs are fixed fee
(CPIF) Cost Plus Incentive Fee actual costs plus incentive to motivate seller to produce at greater speed
(CPAF) Cost Plus Award Fee actual costs plus award based on customer satisfaction with agreed criteria
(CPPC) Cost Plus Percent of Cost actual cost plus % of actual; the higher the cost, the higher the fees
32
Procurement Terms
Project managers should be familiar with additional procurement
terms in the table below:
Terms
Make or Buy Analysis
Bidder Conference
Independent Estimates
Contract (CCOLA)
Point of Total Assumption
Ceiling Price
Target Cost
Target Price
Share Ratio
RFP
RFQ
IFB
Design Scope of Work (SOW)
Functional Scope of Work
(SOW)
Sole Source
Single Source
Negotiation
Standard Terms & Conditions
Special Provisions
Claims Administration
ADR
Description
Is it more practical to insource or outsource (based on a cost comparison between the two)?
Prior to bid submission, offers opportunities for prospective sellers to obtain requirements clarification
from buyer
Used to validate proposal information
Must have 5 Components: Capacity, Consideration, Offer, Legal Purpose, Acceptance
Point at which seller is responsible for all cost overruns; PTA = (Ceiling Price - Target Price)/Buyer Share
+ Target Cost
% of Target Cost (e.g. Ceiling = 140% of target cost)
Expected cost of work in the contract
Equals Target Cost + Target Profit
Ratio of split between buyer and seller of cost savings or overruns (e.g. 70/30)
Request for Proposal, typically used for higher priced, customized services or products
Request for Quote, typically used for small dollar commodity type products
Invitation to Bid, used for government sealed bids (similar to RFP)
Buyer provides exact details; generally results in fixed price contract
Buyer provides functionality needed; generally results in cost plus contract
Go direct to a supplier without any available competition (e.g. supplier holds the patent)
Go direct to a supplier although competitors are available (e.g. "preferred supplier")
PMI prefers "win/win" negotiation approach
Typical common (non-negotiable) contract items with a tight range or parameters
Typically added to account for changes to standard terms and conditions
Means of administering contested changes or disagreements regarding compensation
Alternative dispute resolution (e.g. arbitration) used when claims cannot be negotiated between buyer
and seller
33
ote, additional inputs, outputs, tools and techniques not depicted may apply
Key:
Initiating
Planning
Executing
Monitoring & Controlling
Closing
Monitor overall
project
stakeholder
relationships and
adjust strategies
and plans for
engaging
stakeholders
34
Keep Satisfied
Manage Closely
Monitor
Keep Informed
Moderate
Low
Moderate
High
Interest
35
3. Respect
o Show high regard for yourself, others, and the resources (e.g. people, money, reputation, safety)
entrusted to you
o Engender trust confidence, performance excellence, and mutual cooperation in an environment of
diverse perspectives and views
4. Fairness
o Make decisions and act impartially and objectively
o Conduct yourself in a way free from competing self interest, prejudice, and favoritism
5. Honesty
o Understand the truth
o Act in a truthful manner both in your communication and in your conduct
36
Summary
This material covered the following project management topics:
What is PMI and the PMP?
Why PMI Project Management Principles are
Useful to Know
A Few Basic PMI Definitions
Five Process Groups
o Initiating
o Planning
o Executing
o Monitoring and Controlling
o Closing
Adjourning
Communication Noise
Risk Probability and Impact Matrix
Contract Type
Stakeholder Power vs. Interest Grid
o Risk
o Procurement
o Respect
o Fairness
o Stakeholders
o Honesty
37