on
Time Management
Numerical (Critical
Path, Lead, Lag, Float)
Namita Gupta, PMP
Agenda
Foundation
What is N/W Diagram
What is Lead, Lag
What are Relationships
What is Critical Path
What is float
How to calculate float
Questions
Foundation
Time Management
Time management is the process
where schedule is developed
In this KA schedule planning,
defining activities, sequencing
activities, estimating resources
and activities are performed to
develop the schedule & further to
control the schedule
Foundation
Time Management
Sequence activities is the process
where network diagrams are
created and enhanced in
following processes
Develop schedule is the process
where the schedule is created on
the basis of n/w diagram from
sequence activity, estimates and
putting schedule constraints
Agenda
Foundation
What is N/W Diagram
What is Lead, Lag
What are Relationships
What is Critical Path
What is float
How to calculate float
Questions
Activity
A
Activity
B
Agenda
Foundation
What is N/W Diagram
What is Lead, Lag
What are Relationships
What is Critical Path
What is float
How to calculate float
Questions
Agenda
Foundation
What is N/W Diagram
What is Lead, Lag
What are Relationships
What is Critical Path
What is float
How to calculate float
Questions
Question
Question: Look at below N/W diagram and
find out what is the project duration if there
is a lag between activity B & C of 3 days
Start
Activity A
(5days)
Activity B
(5days)
FS+3
Activity C
(5days)
End
15
12
18
Non of above
2013 iZenBridge | CONFIDENTIAL
Answer
ES 6
Start
Activity A
(5days)
ES 1
EF 10
Activity B
(5days)
FS+3
EF 5
Activity C
(5days)
ES 14
End
EF 18
Question
Question: Look at below N/W diagram and
find out what is the project duration if there
is a lead between activity B & C of 3 days
and relationship finish to finish
Start
Activity A
(5days)
Activity B
(5days)
FF-3
Activity C
(5days)
Activity D
(3days)
18
15
10
Non of above
2013 iZenBridge | CONFIDENTIAL
End
Question
ES 6
Start
Activity A
(5days)
ES 1
EF 10
Activity B
(5days)
EF 5
FF-3
Activity C
(5days)
ES xx
EF 7
Activity D
(3days)
ES 8
EF 10
18
15
10
Non of above
End
Question
Question: Look at below N/W diagram
and find out what is the project duration if
there is a lag between activity B & C of 2
days and relationship start to start
Start
Start
Activity A
(5days)
(5days)
Activity B
(5days)
(5days)
SS+2
Activity C
(5days)
Activity D
(3days)
18
15
10
Non of above
2013 iZenBridge | CONFIDENTIAL
End
Answer
ES 6
Start
Activity A
(5days)
ES 1
EF 5
EF10
Activity B
(5days)
SS+2
Activity C
(5days)
ES 8
EF 12
Activity D
(3days)
ES 13
EF 15
18
15
10
Non of above
End
Any Questions?
Agenda
Foundation
What is N/W Diagram
What is Lead, Lag
What are Relationships
What is Critical Path
What is float
How to calculate float
Questions
Activity A
(5days)
Activity C
(8days)
Activity E
(5days)
Activity D
(3days)
Activity B
(4days)
End
Activity A
(5days)
Activity C
(8days)
Activity E
(5days)
End
Activity D
(3days)
Activity B
(4days)
18
17
12
18
How to identify Early start, early finish, late start & late finish?
Activity Name
ES
EF
Forward Pass
Backward Pass
Duration
LS
LF
ES = EF+1
EF = ES+Duration-1
LS = LF-Duration+1
LF = LS-1
Agenda
Foundation
What is N/W Diagram
What is Lead, Lag
What are dependencies
What is Critical Path
What is float
How to calculate float
Questions
What is Float?
Free Float
Amount of time an
activity can be delayed
without delaying ES of
successor activity and
adhering to schedule
constraints
Total Float
Amount of time an
activity can be delayed
without delaying project
end date and adhering
to schedule constraints
2013 iZenBridge | CONFIDENTIAL
Agenda
Foundation
What is N/W Diagram
What is Lead, Lag
What are dependencies
What is Critical Path
What is float
How to calculate float
Questions
Activity Name
EF
Forward Pass
Backward Pass
LS
Duration
LF
Float = LS-ES
OR
Float = LF-EF
We shall discuss this in following Question
Agenda
Foundation
What is N/W Diagram
What is Lead, Lag
What are dependencies
What is Critical Path
What is float
How to calculate float
Questions
Question
Start
Activity A
(5days)
Activity C
(8days)
Activity D
(4days)
Activity B
(3days)
Activity E
(7days)
End
Activity F
(10days)
Activity A
Activity C
Activity E
23
13
14
Activity D
17
7 days
Start
8 days
5 days
Activity B
End
8
4 days
17
Activity F
3 days
10 days
ES = EF+1
EF = ES+Duration-1
26
Activity A
Activity C
14
Activity D
5 days
8 days
Activity B
11
3 days
7 days
27
17
21
24
13
Start
Activity E
13
End
8
14
4 days
17
18
Activity F
27
18
10 days
27
13
LS = LF-Duration+1
LF = LS-1
Answer - Float
18
6
1
Activity A
5 days
13
14
Start
Activity C
8 days
Activity B
Activity D
13
8
14
4 days
21
3 days
7 days
27
End
17
18
5
11
24
17
Activity E
18
27
13
Float = LS-ES
OR
Float = LF-EF
Activity F
10 days
27
Activity A
5 days
13
14
Start
Activity C
8 days
Activity B
Activity D
13
8
14
4 days
21
3 days
27
17
18
ACDE 24
ACDF 27
ABDE 19
ABDF 22
Activity F
27
13
18
7 days
End
5
11
24
17
Activity E
10 days
27
Activity A
(5days)
Activity C
(8days)
Activity D
(4days)
Activity B
(3days)
Activity E
(7days)
End
Activity F
(10days)
Agenda
Foundation
What is N/W Diagram
What is Lead, Lag
What are dependencies
What is Critical Path
What is float
How to calculate float
Questions
Namita Gupta