Académique Documents
Professionnel Documents
Culture Documents
3rd Year,
PTMBA 2014-17,
NMIMS University,
Mumbai
What Is It ?
Earned
Value
Analysis
Why Do We Need It ?
How Do We Do It?
Todays
Situation
Numerous
projects
complex
(and
interrelated)
Theres
Room For
Improveme
nt
Behind schedule
52% of all projects finish at 189% of
their initial budget.
And some, after huge investments
of time and money, are simply
never completed.
How to
answer the
question:
Have we
done what
we said
wed do?
% complete estimating
% of Budget spent
% of work done
% of time elapsed
The Answer
is:
What Is
Earned
Value
Analysis
(EVA)?
Why Is EVA
Important?
Knowing
where
accomplished?
you
are
on
work
PV Planned Value
Some New
Terms
AC - Actual Cost
EV Earned Value
120000
100000
80000
60000
BCWS
40000
20000
Dec-03
Nov-03
Oct-03
Sep-03
Aug-03
Jul-03
Jun-03
May-03
Apr-03
Mar-03
Feb-03
0
Jan-03
PV
Planned
Value
or Budgeted
Cost of
Work
Scheduled
(BCWS)
60000
BCWP
ACWP
49000
40000
20000
Dec-03
Nov-03
Oct-03
Sep-03
Aug-03
Jul-03
Jun-03
May-03
Apr-03
Mar-03
Feb-03
0
Jan-03
AC
Actual Cost
or Actual
Cost of
Work
Performed
(ACWP)
120000
100000
80000
BCWP
55000
60000
BCWS
49000
40000
20000
Dec-03
Nov-03
Oct-03
Sep-03
Aug-03
Jul-03
Jun-03
May-03
Apr-03
Mar-03
Feb-03
0
Jan-03
EV
Earned
Value
or Budgeted
Cost of
Work
Performed
(BCWP)
120000
100000
80000
60000
BCWP
55000
49000
40000
ACWP
20000
Dec-03
Nov-03
Oct-03
Sep-03
Aug-03
Jul-03
Jun-03
May-03
Apr-03
Mar-03
Feb-03
0
Jan-03
The Whole
Story!
BCWS
56000
Some
Derived
Metrics
Schedule
Variance &
Cost
Variance
- $55,000
SV = - $ 6,000
Some More
Derived
Metrics
SPI: EV/PV
49,000/55,000 = 0.891
CPI: EV/AC
Performanc
e Metrics
49,000/56000 = 0.875
CSI: SPI x CPI
.891 x .875 = 0.780
The CPI and SPI are statistically accurate
indicators of final cost results.
Estimation
of Project
Cost &
Project
Duration
120000
103865
102000
90882
100000
80000
60000
BCWP
ACWP
40000
20000
Dec-03
Nov-03
Oct-03
Sep-03
Aug-03
Jul-03
Jun-03
May-03
Apr-03
Mar-03
Feb-03
Jan-03
Making
Projections
BCWS
140000
Estimate to
Complete
120000
116,571
100000
102000
80000
60000
40000
20000
0
BCWS
BCWP
ACWP
Value of
Earned
Value
Shortcomin
gs of
Earned
Value
Summary
Questions /
Discussion