Vous êtes sur la page 1sur 5

Albatha Group IT

WBS Element Vs Network


Activities
Objective
The objective of this presentation to provide a snapshot of
functionalities for WBS elements and network activities used
in SAP Project System along with comparative analysis to
enable the business to take the right decision.
Snapshot

WBS Elements- Structure element of the work breakdown


structure (WBS)which describes either a certain task or a
partial task that can be subdivided further. It has more finance
and controlling functionality than logistics functionality in SAP.

Network Activities- Network Activities which are assigned to


WBS elements, are used for detailed view of costs, dates, and
capacities. Its a task in a network which has a defined start
and finish. An activity can be broken down into activity
elements. It has more logistics functionality in SAP.
WBS Element Vs Network activities
(A comparative analysis)
SrNo WBS Elements Network Activities
.
1. WBS elements are used for basic/high level/ Network Activities are used for detail scheduling,
hierarchical scheduling. making relationship among different activities,
generating Floats etc.It is important to note that there
is considerably more administrative efforts required in
order to create/maintain/update/close network
activities.

2 Budgeting is done at WBS element level Budgeting cant be done at Network activities level.
3. Cost planning at GL/cost element, Material In order to do cost planning at network activities,
and resources(BOQ) can be done at WBS material components needs to be assigned and as a
level result more efforts is required to achieve this.
4. WBS elements can be used with network Network activities cant be used without WBS
activities if minimum scheduling elements and as a result mapping between WBS
functionalities are required elements and network activities is key for designing
project structure.
5. Extensive logistic(MM) integration with PS is Network activities can be used for detail logistics(MM)
not supported with WBS elements integration with PS i.e. direct material planning,
procurement etc. from project system
6. Confirmation process is not supported with Confirmation process is supported in network
WBS element. activities.
Key decision driver for WBS elements vs
Network activities?
How much detail scheduling the business wants to
maintain/update?
The level of detail progress report in SAP?

Vous aimerez peut-être aussi