2 Budgeting is done at WBS element level Budgeting cant be done at Network activities level.
3. Cost planning at GL/cost element, Material In order to do cost planning at network activities,
and resources(BOQ) can be done at WBS material components needs to be assigned and as a
level result more efforts is required to achieve this.
4. WBS elements can be used with network Network activities cant be used without WBS
activities if minimum scheduling elements and as a result mapping between WBS
functionalities are required elements and network activities is key for designing
project structure.
5. Extensive logistic(MM) integration with PS is Network activities can be used for detail logistics(MM)
not supported with WBS elements integration with PS i.e. direct material planning,
procurement etc. from project system
6. Confirmation process is not supported with Confirmation process is supported in network
WBS element. activities.
Key decision driver for WBS elements vs
Network activities?
How much detail scheduling the business wants to
maintain/update?
The level of detail progress report in SAP?