Review of Progress of NHAI Works in Gujarat State

Regional Office Gandhinagar


National Highways Authority of India

1
2
Length of National Highways in Gujarat
Sr. NH Length in km
Description of Road
No. No. With NHAI
53 4-laning of Gujarat Maharashtra Border-Surat-Hazira Port section of NH-6
1 132.91
(Approx. 133 Km)
2 48 Ratanpur-Himmatnagar-Ahmedabad-Vadodara-Surat-Dahisar 629.00
3 27 Ahmedabad-Bamanbore-Maliya-Bhachu-G'dham-Kandla 179.40
4 41 Kandla-Mundra-Mandvi-Nalia-N. Sarovar 71.40
5 27 Porbandar-Rajkot 185
7 151 Jetpur-Gadu 98
8 27 Abu Road - Palanpur Radhanpur 151.62
9 27 Samakhiyali-Radhnapur-Bhabhar-Vav-Tharad 142.00
10 59 Ahmedabad-Balasinor-Godhra-Dahod 211.20
11 NE-1 Ahmedabad-Vadodara 93.00
12 51 Bhavnagar-Veraval-Gadu-Dwarka 470
TOTAL 2363.53
Providing NH connectivity to Backward areas/religious/tourist places:-Preparation of DPR
12 - Talaja(NH-8E)-Palitana-Sihor 64.00
13 - Modasa-Lunavada-Godhra 170
14 - Bodeli(NH-56)-Halol 49.4

15 - Abu Road(NH-27)-Mount Abu 40.9

TOTAL 324.3
Bharatmala Scheme:- State roads entrusted to NHAI for preparation of DPR in Gujarat State
16 - Dwarka(NH-51)-Khambalia-Jamnagar-Dhrol-Amran-Maliya 132.00
17 - Ahmedabad Dholera Expressway 110
3
BOT Projects under Construction
Total
Date of
Projec Name of Stipulated/
Contract commencem
t Cost Concessiona Anticipate Concession
S. Stretch Length ent/
(Rs. ire/ d Period(VGF/Pr
No (State)/NH (Km.) Cumulative
in Independen Completio emium)
No. physical
Crore t Engineer n
progress
s)
M/s. KM
19.01.2011
71.4 Tollway 16.07.2013
(64.4k Private Ltd. 25 Years
Kandla -
m on 954.0 PCC issued [42 Cr Premium
1 Mundra Port
ground 0 on with 5% annual
(NH 8A Ext.) 91% M/s K&J
) 04.11.2015 increment]
(for
55.8km)
Six laning of 11.09.2010 M/s L&T 11.03.2013
Samakhiyali- 56.16 24 Years
Gandhidham Complet [58.41 Cr
2 Section from e on 805 Premium with
100 % M/s K&J Nov 2016
Km 306.000 to ground 5% annual
Km 362.160(NH increment]
8A)
M/s. IRB AVSE 25 Years
01.01.2013 31.12.2015
Pvt. Ltd. [309.60 Cr
4 Premium with
Ahmedabad- 102.30 31.12.2015.
Date of
Total Name of
Contract commencem
Project Concessionair Stipulated Concession
S. Stretch Length ent /
Cost e/ Anticipated Period(VGF/Premi
No (State)/NH (Km.) Cumulative
(Rs. in Independent Completion um)
No. physical
Crores) Engineer
progress
M/s IRB Surat
239 12 years
Six laning 20.02.2009 Dahisar Tollway 15.02.2012
(237.5k revenue sharing
Surat- Dahisar Pvt. Ltd.
4 m on 1693.75 basis (38% share in
Section of PCC issued on
ground) 1st year increasing
NH-8 99.7% M/s CEG 06.04.2013 for
1% annually)
231km
M/s. Soma -
Isolux Surat -
30.03.10 25.09.2012 VGF (NHAI Grant)
Hazira Tollway
Gujarat / 133 Rs.556 Cr.
Pvt. Ltd.
Maharashtra (131.5k (Rs.301.83 Cr.
PCC 1 issued on
5 Border-Surat- m on 1509.00 Under
19.08.2015 for
Hazira Port ground) Construction +
M/s Frischman 117.4km. PCC 2
section (NH-6) 97% Rs. 254.17 Cr.
Prabhu issued on
Under O&M.
05.10.2016 for total
length 129km
M/s. IDFC and
31.03.2012 PLUS
27.09.2014
123.5 Expressway
Concessionaire
(103k Ltd.
Jetpur- Terminated. Bids
m on PCC-1 issued on
6 Somnath(NH8D 828.00 for EPC Tender
ground 04.05.2015 for
) received on
) 88.89 km . PCC 2
82.7% M/s MSV 26.12.2016
issued on 1.6.16 for
5
total length
EPC Projects under construction
Date of
Total Name of
Contract commenceme
S. Length Project Cost Concessionai Stipulated
Stretch nt /Cumulative
No. (km.) (Rs. in re/ Authority Completion
(State) Physical
Crores) Engineer
Progress
Construction of
a new four lane
Contractor
Narmada bridge 03.03.2014
M/s. L&T
(Extra dosed 6.745 92% Ltd Mumbai
1 bridge) across (2km on 407.00
M/s. Aarvee
river Narmada ground)
Associates
in the State of
Engineers
Gujarat on
EPC(NH8)

6
Vadodara Mumbai Expressway (473 km)

Length of main alignment : 378.68 km


Length in Gujarat 260.40km
Length in Maharashtra 112.83km
Length in Dadra & Nagar Haveli 5.45km
Total Length of main alignment 378.68 km

Length of spur alignment : 94.32 km


Length of spur in Maharashtra 94.32 km

Total Length = 378.68 km + 94.32 km = 473.00 km

7
Projects awarded in 2016-2017
Sr. Length Contract signing
Name of the stretch Cost(in Rs.Cr.) Agency Name
No. (km.) date

19.07.2016/
Four laning of Bhavnagar to Talaja section from 7.090 km to km
1 48.045 Appointed date 819 M/s. Sadbhav
53+585 PKg-I in the state of Gujarat
07.02.2017

Four laning of Talaja to Mahuva section from km 53+585 to km


2 45.460 08.07.2016 643.5 M/s. MEP SANJOSE
100+100 (Design Ch.54+990 to km 100+450) PKg-II

Four laning of Mahuva to Kagavadar section from km 100+100 to


3 40.020 09.08.2016 604.68 M/s. MEP Sanjose
km 139.915 (Design Ch.100+450 to km 140+470 ) PKg-III

Four laning of Kagavadar to Una section from km 139.915 to km


4 40.980 19.07.2016 555 M/s. Agroh
180+478 (Design Ch.140+470 to km 181+450 ) PKg-IV

19.07.2016/
Four laning of Una to Kodinar section from km 180+478 to km
5 40.950 Appointed date 623 M/s. Sadbhav
221+610 (Design Ch.181+450 to km 222.400 ) PKg-V
09.02.2017

Four laning of Kodinar to Veraval section from km 221+610 to km


6 40.780 19.12.2016 670 M/s. Agroh
263+000 (Design Ch.222.400 to km 263+180 ) PKg-VI

7 4 to 6 laning of Kamrej to Kadodara Section of NH-8 14.00 12.05.2016 426 M/s Unique

Package- VII of Kishangarh - Udaipur-Ahmedabad section (km LOA given on


8 15.310 315.95 M/s. KCC Buildcon Private Ltd
494.410 to km 509.550) 15.11.2016

Two laning with paved shoulder of Gadu-Porbandar section of LoA issued on


9 91.67 370 M/s Kalathia
NH-8E from km 263.200 to Km 356.766 15.12.2016
Projects awarded in 2016-2017
Sr. Length Contract signing
Name of the stretch Cost(in Rs.Cr.) Agency Name
No. (km.) date

Package VI of Kishangarh-Udaipur-Ahmedabad section LoA issued on


10 93.21 1292 M/s Atlanta
(km 401.200 to km 494.410) 24.01.2017

Total.......... 470.425 6319.13


Projects to be awarded shortly
Sr. Length Cost(in
Name of the stretch Remarks
No. (km.) Rs. Cr.)
1 Four laning of Porbandar Dwarka 118.33 Bids under
1446
section of NH-8E scrutiny
2 Construction of 4 lane bridge across 2.25 3 Bids received
Varsova river on
188.41 02.12.2016.
Under
scrutiny
Total 120.58 1634.41

10
Projects in pipeline
Tentaive date
Sr. Length
Name of the stretch of Status
No. (km.)
completion
Bharatmala Project. M/s RITES is Feasibility
Dwarka(NH-51)-Khambalia-
1 132 Sep-17 Consultant. Feasibility report submitted by
Jamnagar-Dhrol-Amran-Maliya
Consultant
Bharatmala Project
LoA for DPR studies given to SMEC(India)
2 Ahmedabad Dholera Expressway 110 Nov-17
Pvt. Ltd. Contract Agreement signed on
05.10.2016.

Bodeli(NH-56)-Champaner- Providing NH connectivity to Backward


3
Pavagadh -Archaelogical park- 40 areas/religious/tourist places:-M/s Mukesh &
Halol(NH-47); June 17 Associates in Association with M/s CoS
Consultancy Services appointed.
4 Abu Road-Mount Abu 49 Feasibility/DPR under progress.

5 Talaja(NH-8E)-Palitana-Sihor 64 Providing NH connectivity to Backward


areas/religious/tourist places: Consultant
NA
Idar-Modasa-Lunavada-Godhra yet to be appointed
6 170

11
Projects in pipeline
Length Tentative
Sr. Packag New
Stretch identified for Feasibility/DPR Study eligible for 4 date of Name of Consultant
No. e No. NH No.
laning (km) completion
M/s. ICT Pvt. Ltd
NH/IAH Feasibility /DPR of Junction with NH-41
1. 341 62.58 June 17
E/14 Bhimasar - Bhuj

Feasibility/DPR of Patan to Gozaria in the
3. 68 75 M/s SATRA
State of Gujarat.

12
BOT Projects under O&M
Date of
Total
Commencem
Total Project Name of Concessio
S. ent
Section Length Cost Concessionair n period Funding
No
(km) (Rs. e (years)
Date of
crore)
Completion
Vadodara to Bharuch M/s. L&T Vadodara
08.01.2007 BOT
Section BOT- (Pkg-I) Bharuch Tollway
1. 83.30 660.00 15 Negative grant of
(Six lane) Ltd.
June 2009 Rs. 497 Cr.
NH 8 (L&T IDPL)
Bharuch to Surat M/s. IDAA
03.01.2007 BOT
Section BOT- Pkg-II Infrastructure Pvt.
2. 65.00 492.00 15 Negative grant of
(Six lane) Ltd.
Sep 2009 Rs .502 Cr.
NH8 (M/s IRB)
Widening of the
Existing Jetpur -
Gondal Section (Km.
117/00 to 143/00) from
M/s. West Gujarat
Two lane Gondal Rajkot 22.09.2005
Expressway Pvt.
Section (Km. 143/00 to Net Negative
3 68.00 288.36 Ltd 20
Km. 175/00) and Grant of 240 Cr.
(M/s IL&FS)
widening (Km, 175/00 May 2008
to 185/00) from two
lane to four lane on
NH-8B in Gujarat, India
on BOT Basis

13
Building a Nation, Not Just Roads
BOT Projects under O&M
Date of
Total
Commenceme
Total Project Name of Concession
S. nt
Section Length Cost Concessionai period Funding
No
(km) (Rs. re (years)
Date of
crore)
Completion
Annuity basis
M/s. . L&T
Palanpur to Completion
Interstate Road Sep 2006
Swaroopganj (42 date.
4 34.00 498.00 Corridor Ltd. 17.5
km. in Raj & 34 km. 24.03.2024
(M/s L&T) March 2009
in Guj) NH14 (Rs. 43.21 Cr.- 6
Monthly basis)
M/s. Essel
27.12.10
Ahmedabad
Four laning of
Godhara Projects
Ahmedabad PCC-1 issued in
5 117.60 1155.40 Pvt. Ltd. 30 108 Cr Grant
Godhra section Oct-2013 and
(M/s Essel)
(Package-I)(NH59) PCC-2 issued in
Aug 2014

01.03.2011
Four laning of 7.83 Cr Premium
M/s. BSCPL Infra.
Godhra to per year with
87.29 750.00 Pvt. Ltd.
6 Gujarat/MP Border- 27 annual increase
(M/s BSCPL) Completion
section (Package-II) of 5 %..Premium
certificate issued
deferred.
in June 2016

Building a Nation, Not Just Roads 14


OMT Projects
Sr. Details of Package Name of Concessio Remarks
No. concessionaire / n Details
Contractor
9 Years 7th Year Operation, Total 9 Years
(Rs. 178 Cr. NH No. : NH-14 & 15
Operation and Maintenance of
M/s. Patel Highway Length(In Kms) : 260.50 Km
Palanpur - Radhanpur section of *COD 65.00
1 Management Pvt. Date of Start of OMT : 27.04.2010
NH-14 and Radhanpur - Cr. Fees + 10%
Ltd., Stipulated date of completion : 26.04.2019
Samakhiyali section of NH-15 Annual Funded by : OMT Basis
increase)

15
O&M Projects
Sr. Details of Package Name of Remarks
No. concessionaire /
Contractor
Operation and Maintenance of
Date of start/completion:14.05.2015/12.05.2016
1 Porbandar Bhiladi Jetpur Section of M/s. MV Rajani
(extension upto 30.14.2017 under process)
NH-8B
Operation & Maintenance of Ratanpur
Date of start/completion:08.11.2016/7.04.2017 (Eot
2 Himatnagar Ahmedabad stretch of M/s. MV Rajani
upto 31.12.2016 sought)
NH-8
Date of start/completion:27.03.2015/27.07.2016
Operation & Maintenance of Garamore M/s Jugal Kishor (extension upto 31.03.2017 sought from NHAI HQ)
3
Samakhiyali Sect. of NH-8A Ramkishan Agarwal

Operation & Maintenance of Date of start/completion:22.11.2015/21.11.2017


4 M/s. Laxmi Builders
Bamanbore Garamore Sect. of NH-8A

16
Thank You
17