Académique Documents
Professionnel Documents
Culture Documents
Sanal S
Dy. Manager
(Insp.)
Schematics of Inventory in
Refinery
Leg Setting
Internal Inspections:
API-653 generally requires that all newly installed tanks receive
an internal inspection within 10 years of their entry into service.
Empty tank
Isolate
Clean and degas
Inspection blast of floor coating
API 653 inspection
Issue preliminary inspection report and develop
list of maintenance/repair items
Perform tank maintenance and repair work
Tank M&I
45.8 m 6 12
45.8 m 8 16
For the balance shell courses, thickness measurement shall be taken at three elevations covering bottom, middle and top of the shell
For tanks in Tank Shell
lighter
products
service such as
Motor Spirit &
Naphtha,
pitting is
generally
observed in the
middle courses
of the shell due
to frequent
wetting and
drying of the
shell plates at
this elevation.
In such cases,
thickness
survey should
be more
extensive on
middle shell
courses
Tank Evaluation
Shell:
1. Extreme upper, non wetted shell area often
experience accelerated corrosion. This is very real
possibility in sour crude or FO storage tanks due to
high sulfur content.
2. Flaws, deterioration greater than corrosion
allowance must be evaluated for continued use
suitability (4.3.1.1).
Tank Evaluation
Tank Roof/ Support Structural:
1. Roof plates corroded to an average t of less than
0.09(in any 100 inch2). Repair or replaced (4.2.1.2).
2. Should corrosion is found in the upper shell course, the
potential for a like loss should be suspected on the
internal roof plates, rafter/structural members & roof
support columns.
3. The supporting members shall be rejected when the
overall loss in thickness of material exceeds 25 % of
initial thickness (OISD-129).
Compression Plate Secondary Seal
with Wiper Tip on EFR Tank
Emergency roof drain sump shall be filled with clean water before
boxing up of the tank.
Roof Drain Hose Inspection
All swivel joints shall be thickness surveyed and serviced during every
outage and individually hydro tested.
Roof drain shall be hydro tested at a pressure of 3.5 Kg/cm2. The drain
lines including joints shall be tested for tightness by pressure testing
with water at 3.5 Kg/cm2 (ROS 67).
Other Tank Appurtenances
Spiral stairway
Ladders
Level gauges
Pressure vacuum vents : Frequency and procedure outlined in
OISD-STD-132 (Inspection of Pressure Relieving Devices) .
Shell and roof man ways
Drain sumps
Roof and Structural Members- All structures may be hammer
tested.
Wind Girders etc
Other Considerations
Roof nozzles - shall be thickness gauged
Welds of bottom shall be checked with vacuum box with air pressure between 20kPa and 70 kPa.
Vacuum testing is performed using a testing box approximately 150 mm (6 in.) wide by 750 mm
(30 in.) longwith a clear window in the top, which provides proper visibility to view the area
under examination .
Dye Penetrant Testing of Shell nozzle
Inspection Checklist:
Annex C of API-653 contains two comprehensive
sample checklists covering the internal and external
inspection of tanks:
In-service tanks
Out-of-service tanks
TYPES OF INSPECTIONS
In Addition:
OISD 130
Refinery Operating System (ROS-44 (Inspection and testing of
pipelines and , ROS-60 Guide lines for prevention of external of
pipelines )
Types of pipes
Electric Resistance Welded Pipes
Electric Fusion Welded Pipes
Double Submerged Arc Welding Pipes
Spiral Welded Pipes
Seamless Pipes
Frequency of inspection
The frequency and extent of inspection of piping system shall depend upon
the form of degradation that can affect the piping performance and
consequence of piping failures
The piping system shall be categorized into 3 classes based on the severity of
consequences of failure.
CLASS I
CLASS II
CLASS III
In case, high corrosion rates are observed and half the remaining life is less than the
shall be suitably reduced to ensure that maximum inspection interval shall not be
Visual Inspection:
Leaks (pipe connections, the packing glands of valves and expansion joints )
Bulging, Bowing and Sagging, Mechanical Damage from External Forces, Paint and Protective
Coating, Cracks, Insulation, Concrete Lining
EXTERNAL ON-STREAM INSPECTION:
Aboveground pipelines:
One reading shall be at the centre of the bend and two readings on the same line on
either side of this reading.
Minimum one ultrasonic scan each on the straight pipes on upstream and
downstream of the bend adjacent to welds of the bend to pipe
One ultrasonic scan on the entire circumference (four readings) upstream and
downstream of the weld joint for process pipelines
Minimum one ultrasonic scan (four readings) each on reducer/ expander and just
downstream on the pipe
EXTERNAL ON-STREAM INSPECTION:
Long range ultrasonic guided wave technology should be deployed to assess metal
loss in inaccessible location not covered under conventional ultra sonic thickness
measurement.
Hammer Testing
Pressure Testing
Pressure testing
Pressure testing of existing pipelines shall be carried out in the following conditions;
When the piping is out of service for more than six months
Austenitic stainless steel piping shall be hydro-tested using water with chloride
content less than 50 PPM
Stress due to testing shall not exceed 90% of the yield stress of the material of
construction of the piping.
Pressure testing
Hammer testing of piping undergoing a pressure test shall not be carried out.
Hammer testing of valves, pipes and fittings of cast iron construction, chrome-steel,
austenitic SS lines and stress relieved lines shall not be carried out
Pressure test shall not be carried out at metal temperatures near the ductile-to-brittle tem
Hydrostatic test pressure = 1.5 times design pressure * temperature correction (B 31.3)
Pneumatic test:
Piping system which cannot safely be filled with liquid due to their design or supports
Piping system where traces of testing medium (liquid) is not permitted in the process
( example flare lines)
Thermographic survey of internally lined hot piping helps in locating the hot spots.
Insulation shall be removed at specified locations including all bends and ultrasonic thickness
shall be carried out and the corrosion rate established.
Spring hangers and spring supports of high temperature piping shall also be checked during
shutdown.
.
INSPECTIONS IN SPECIFIC AREAS FOR CORROSION AND
CRACKING
Injection Points:
Deadlegs:
The corrosion rate in dead legs can vary significantly from adjacent active piping. The
wall thickness should be monitored on selected dead legs, including both the
stagnant end and at the connection to an active line.
Corrosion under insulation (CUI)
The most common forms of CUI are localized corrosion of carbon steel and chloride
stress corrosion cracking of austenitic stainless steels. ( Temp -4 degree up to 120
degree)
Painting, insulation, wrapping and coating shall be done as per the design code
External
Above piping ground is subject to atmospheric corrosion
Pipelines touching the ground are subject to corrosion due to dampness of the soil
Crevice corrosion may take place at the pipe supports or sleepers where pipes are resting on
them.
Deterioration takes place at the pipe support locations where relative movement between pipe
and pipe supports takes place.
Buried pipelines are subject to soil corrosion
Impingement attack may take place on pipelines in the vicinity of leaky pipes and steam traps.
Insulated lines where weather shielding is damaged are subject to external corrosion
Externally concrete-lined pipelines are subject to localised corrosion due to cracks in the
concrete.
Piping entering into or emerging from the underground may experience severe corrosion due to
coating damage
Piping corrodes at locations of water accumulation and acid vapour condensation such as in the
vicinity of fire hydrants sulphur recovery plants, cooling towers, jetty, etc
Likely area of metal deterioration
Internal
Usually a greater loss of metal wastage is observed near a restriction in the line or a
change in line direction because of the effects of turbulence or velocity. Therefore, it
is required to inspect pipe bends, elbows, and tees and also at restrictions such as
orifice flanges and throttling valves, and areas just down stream of the restriction.
Repairs by Welding:
Temporary repairs:
Temporary repairs, including on stream or off stream, a full encircle split sleeve or box
type enclosure designed to take care of internal pressure can be considered over
damaged or corroded area. Area with longitudinal cracks shall not be repaired by
encircle sleeve.
If repair area is small and localized, temporary repair may be carried out using
properly designed split coupling or fillet plate patch. The material of repair will match
with base metal.
Areas with minor leaks shall be attended by welding of properly designed enclosures
Temporary repairs shall be removed and replaced with permanent repairs at the next
available maintenance opportunity. Temporary repairs may remain in place for a
longer period of time only if approved and documented
Permanent repairs:
All repairs and alteration welding shall be done in accordance to the code to which
the piping system has been built ( ASME B31.3)
Corroded areas may be restored with weld deposits. However, Surface irregularities
and contaminations shall be removed before welding.
Insert plates may be used to repair the damaged or corroded areas provided
following are met
(i) Full penetration groove welds
(ii) 100% radiography of joints for hydrocarbon/ critical service
During out of service repair, the defective area shall be removed by cutting the
cylindrical sections and replacing it with piping component which meet the code
requirement.
Clamping: Bolted clamps: The effect of clamping (crushing) forces on the component
shall be considered.
Composite Sleeves: Composite sleeves shall not be used to repair leaks, metal loss
with a depth greater than 80% of the nominal wall thickness, cracks, or
circumferentially oriented defects.
INSPECTION DURING REPAIRS/REPLACEMENTS:
The metallurgy and dimensions of the new pipe shall match with those of the existing
pipe.
c) For longitudinally welded pipes, the weld seam shall be kept staggered and the
longitudinal seam shall be kept in the upper quadrants.
d) Piping systems repair work shall comply with applicable statutory requirements.
e) Repaired welds shall be subject to same pre and post-weld heat treatments as
required in the case of new pipes
DOCUMENTATION:
On the basis of records of previous and present inspection, a work schedule shall be
prepared for future on stream as well as comprehensive inspections
Links
001 fitup record format rev 4.doc
045 REQUEST FOR WELDER QUALIFICA
TION TEST.doc
047 Format for Deviation.doc
Thank you